Energy Harbor Nuclear Corp.
Beaver Valley Power Station P.O. Box 4 Shippingport, PA 15077 John J. Grabnar 724-682-5234 Site Vice President, Beaver Valley Nuclear October 21, 2022 L-22-232 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit Nos. 1 and 2 Docket No. 50-334, License No. DPR-66 Docket No. 50-412, License No. NPF-73 Withdrawal of a License Amendment Request Associated With Fire Protection Program Changes (EPID L-2022-LLA-0135)
By letter dated September 6, 2022 (Accession No. ML22249A366), Energy Harbor Nuclear Corp. submitted a license amendment request to the Nuclear Regulatory Commission (NRC) that would modify the bases for two licensing actions credited during the transition to a risk-informed, performance-based fire protection program. In an email on October 4, 2022, the NRC staff determined additional information would be needed before the submittal could be accepted. Based on the time necessary to develop the requested information, this license amendment request is hereby withdrawn.
There are no regulatory commitments contained in this submittal. If there are any questions or if additional information is required, please contact Mr. Phil H. Lashley, Manager - Fleet Licensing, at (330) 696-7208.
Sincerely, John J. Grabnar cc:
NRC Region I Administrator NRC Resident Inspector NRC Project Manager Director BRP/DEP Site BRP/DEP Representative John J Grabnar Digitally signed by John J Grabnar Date: 2022.10.21 12:41:58 -04'00'