Text

l=PL..

July 30, 2024 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN : Document Control Desk

SUBJECT:

DOCKET NO:

St. Lucie Units 1 and 2 50-335 and 50-389 L-2024-121 St. Lucie Unit 1 Subsequent License Renewal Commitment #30 Revision

References:

1. Safety Evaluation Report, Revision 1, "Related to the Subsequent License Renewal of St. Lucie Plant, Units 1 and 2," September 2023 (ADAMS Accession No. ML23219A003)
2. Florida Power & Light Company letter L-2021 -142, Application for Subsequent

Florida Power & Light Company (FPL) hereby submits this notification of a regulatory commitment change for St. Lucie Units 1 and 2. Reference 1 Section 3.0.3.3.23 documented that Appendix A 1 - Unit 1 Updated Final Safety Analysis Report Supplement in Reference 2 provided commitments, i.e., Table 19-3, List of Unit 1 SLR Commitments and Implementation Schedule. Commitment #30 regarding Buried and Underground Piping and Tanks included a schedule to install cathodic protection systems no later than 10 years prior to the subsequent period of extended operation (SPEO) (03/01/2026).

St. Lucie Unit 1 cathodic protection systems will be installed and operational by the end of 2029; consequently, Buried and Underground Piping and Tanks Program inspections will be delayed to the end of 2029. FPL is revising the Implementation Schedule of Commitment

  1. 30 to read, "Program inspections begin 6 years before the SPEO. Inspections that are to be completed prior to the SPEO are completed 6 months prior to the SPEO or no later than the last refueling outage prior to the SPEO. Install cathodic protection systems at least 6 years before the SPEO. Program and SLR enhancements are implemented 6 months prior to the SPEO, i.e.: PSL 1: 09/01/2035" Florida Power & Light Company 6501 S. Ocean Drive, Jensen Beach, FL 34957

Should you have any questions regarding this submission, please contact Mr. Kenneth Mack, Senior Manager, Licensing and Regulatory Compliance at 561-904-3635.

Sincerely, Paul Rasmus General Manager, Regulatory Affairs cc:

USNRC Regional Administrator, Region II USNRC Project Manager, St. Lucie Nuclear Plant, Units 1 and 2 USNRC Senior Resident Inspector, St. Lucie Nuclear Plant, Units 1 and 2 Mr. John Williamson, Florida Department of Health