L-08-095, Property Insurance Coverage

From kanterella
(Redirected from L-08-095)
Jump to navigation Jump to search
Property Insurance Coverage
ML080860529
Person / Time
Site: Beaver Valley, Davis Besse, Perry, Crane  Constellation icon.png
Issue date: 03/18/2008
From: Halnon G
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
5928-08-20045, L-08-095
Download: ML080860529 (3)


Text

FENOC FE, AIO, o-C 76 S. Main St.

Akron, Ohio 44308 March 18, 2008 L-08-095 5928-08-20045 (Three Mile Island Power Station Unit No. 2) 10 CFR50.54(w)(3)

ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Beaver Valley Power Station Unit Nos. 1 and 2 Docket Nos. 50-334 and 50-412, License Nos. DPR-66 and NPF-73 Davis-Besse Nuclear Power Station Unit No. 1 Docket No. 50-346, License No. NPF-3 Perry Nuclear Power Plant Unit No. 1 Docket No. 50-440, License No. NPF-58 Three Mile Island Power Station Unit No. 2 Docket No. 50-320, License No. DPR-73 Property Insurance Coverage In accordance with 10 CFR 50.54(w)(3), the FirstEnergy Nuclear Operating Company hereby submits the 2008 Annual Notification of Nuclear Property Insurance Coverage for FirstEnergy Corp. nuclear units. The attachment lists the insurers, policy numbers and coverage limits for the Beaver Valley Power Station Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1 and Three Mile Island Power Station Unit No. 2.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager -

Fleet Licensing, at 330-761-6071.

'Gregory"--. Halnon Director, Fleet Regulatory Affairs

ý\\ 00 1

Beaver Valley Power Station Unit Nos. 1 and 2 Davis-Besse Nuclear Power Station Unit No. 1 Perry Nuclear Power Plant Unit No. 1 Three Mile Island Power Station Unit No. 2 L-08-095 Page 2 008 Annual Notification of Nuclear Property Insurance Coverage cc:

Regional Administrator, NRC Region I Regional Administrator, NRC Region III NRR Project Manager, Davis Besse and Perry NRR Project Manager, Beaver Valley NRR Project Manager, TMI-2 NRC Resident Inspector, Beaver Valley NRC Resident Inspector, Davis Besse NRC Resident Inspector, Perry NRC Resident Inspector, TMI-2 Executive Director, OEMA Utility Radiological Safety Board Director BRP/DEP Site BRP/DE Representative File No. 08019

Attachment L-08-095 2008 Annual Notification of Nuclear Property Insurance Coverage Page 1 of 1 Insurer Policy No.

Amount of Insurance Perry Nuclear Power Plant Unit No. I -

Nuclear Electric Insurance Limited (NEIL)

Nuclear Electric Insurance Limited (NEIL)

P07-067 X07-065 TOTAL Davis-Besse Nuclear Power Station Unit No. 1 -

Nuclear Electric Insurance Limited P07-059 (NEIL)

Nuclear Electric Insurance Limited X07-035 (NEIL)

TOTAL Beaver Valley Power Station Unit Nos. 1 and 2 -

Nuclear Electric Insurance Limited P07-071 (NEIL)

Nuclear Electric Insurance Limited X07-014 (NEIL)

TOTAL Three Mile Island Power Station Unit No. 2 -

Nuclear Electric Insurance Limited P07-041 (NEIL)

TOTAL

$500,000,000

$2,250,000,000

$2,750,000,000

$500,000,000

$800,000,000

$1,300,000,000

$500,000,000

$2,250,000,000

$2,750,000,000

$150,000,000

$150,000,000