IR 05000219/2011007

From kanterella
Jump to navigation Jump to search
NRC Triennial Fire Protection Inspection Report 05000219/2011007
ML111250021
Person / Time
Site: Oyster Creek
Issue date: 05/05/2011
From: Rogge J
Engineering Region 1 Branch 3
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
References
IR-11-007
Download: ML111250021 (25)


Text

SUBJECT:

OYSTER CREEK NUCLEAR GENERATING STATION - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT O5OOO21 9/2011007

Dear Mr. Pacilio:

On April 1, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial fire protection inspection at Oyster Creek Nuclear Generating Station. The enclosed inspection report documents the inspection results, which were discussed on April 1, 201 1, with Mr. Michael Massaro, Site Vice President, and other members of your staff. A follow-up discussion to provide an update of the inspection findings was held with Mr. J. Chrisley by telephone on April 28,2011.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. The inspectors also reviewed mitigation strategies for addressing large fires and explosions.

Based on the results of this inspection, one finding of very low safety significance (Green) was identified. This finding was also determined to be a violation of NRC requirements. However, because of the very low safety significance, and because the issue was entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV)

consistent with Section 2.3.2 of the NRC Enforcement Policy. lf you contest this NCV in this report, you should provide a written response within 30 days of the date of this inspection report with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington D.C. 20555-0001; with copies to the Regional Administrator, Region l; the Director, Office of Enforcement; and the NRC Resident Inspector at Oyster Creek Nuclear Generating Station. In addition, if you disagree with the characterization of any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the RegionalAdministrator, Region l, and the Resident Inspector at Oyster Creek Nuclear Generating Station. The information you provide will be considered in accordance with Inspection Manual Chapter 0305. In accordance with Title 10 of the Code of Federal Regulations Part 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARs) component of the NRC's document system Administrative Document and Access Management System (ADAMS). ADAMS is accessible from the NRC Web Site at http://www.nrc.qov/readinq-rm/adams.html (The Public Electronic Reading Room).

Sincerely, John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket No.: 50-219 License No.: DPR-16 Enclosure: Inspection Report No. 0500021912011007 cc Mencl: Distribution via ListServ

SUMMARY OF FINDINGS

lR 0500021 912011007;0311412011 - 041011201 1; Exelon Generation Company, LLC; Oyster

Creek Nuclear Generating Station; Triennial Fire Protection Team Inspection.

The report covered a two-week triennialfire protection team inspection by specialist inspectors.

One finding of very low significance (Green) was identified. This finding was determined to be a non-cited violation (NCV). The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using lnspection Manual Chapter 0609, "Significance Determination Process" and the cross-cutting aspect was determined using IMC 0305, "Operating Reactor Assessment Program." Findings for which the significance determination process (SDP) does not apply may be Green or be assigned a severity levelafter NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

Gornerstone: M itigati ng Systems Green: The team identified an NCV of 10 CFR 50, Appendix R, lll.G.2, in that Exelon failed to maintain the credited reactor coolant inventory makeup system free of fire damage in the event of a fire in the 'B' 480 volt (V) switchgear room. Specifically, Exelon failed to assure that the 'A'

control rod drive (CRD) pump would remain available during 'B'480V switchgear room fire scenarios. Cables associated with the'A'CRD pump low pressure suction trip are located in the 'B' 480V switchgear room and are not protected by one of the methods specified in 10 CFR 50, Appendix R, Section lll.G.2. Fire damage to these cables could result in the trip of the credited 'A' pump and render it inoperable from the control room. Exelon entered this issue into its corrective action program for long term resolution as lssue Report (lR) 01 187591 and promptly established compensatory measures (an hourly fire watch) in the 'B' 480V switchgear room. Exelon also promptly performed an extent of condition review to ensure the 'B' CRD pump was not similarly affected for fire areas that credited its remote operation from the main control room.

This finding is more than minor because it is associated with the externalfactors attribute (fire)of the Mitigating Systems Cornerstone and adversely affects the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the availability of the credited 'A' CRD pump was not ensured for a 'B'480V switchgear room fire scenario. A Senior Reactor Analyst performed a Phase 3 Fire Protection Significance Determination Process analysis and determined that this finding was of very low safety significance (Green). The Phase 3 SDP conservatively assumed the 'A' CRD pump failed for eight separate fire scenarios initiated by electrical ignition sources or transient combustibles. The results of the SDP were largely dominated by the availability of the feedwater and condensate system for reactor coolant inventory control because its circuits were not routed through the 'B' 480V switchgear room.

This finding did not have a cross-cutting aspect because the performance deficiency occurred during development of the safe shutdown analysis in the 1980's and is not reflective of current licensee performance. (Section 1R05.06)

Other Findings

None

REPORT DETAILS

Backoround This report presents the results of a triennial fire protection inspection conducted in accordance with NRC Inspection Procedure (lP) 71 11 1.05T, "Fire Protection." The objective of the inspection was to assess whether Exelon has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and are being properly maintained at the Oyster Creek Nuclear Generating Station (OCNGS). The following fire zones (FZs) were selected for detailed review based on risk insights from the Oyster Creek Individual Plant Examination (lPE)/lndividual Plant Examination of External Events (IPEEE):

. OB-FZ-S Control Room;

. OB-FZ-68 'B'480 Volt Switchgear Room; o TB-FZ-11B Turbine Lube Oil Storage, Pumping & Purification Area; and

. TB-FZ-11C Switchgear Room - Turbine Building Mezzanine.

lnspection of these areaslzones fulfills the inspection procedure requirement to inspect a minimum of three samples.

The inspection team evaluated the licensee's fire protection program (FPP) against applicable requirements which included plant Technical Specifications, Operating License Condition 2.C.3, NRC Safety Evaluations, 10 CFR 50.48, 10 CFR 50, Appendix R, and Branch Technical Position (BTP) Chemical Engineering Branch (CMEB) 9.5-1. The team also reviewed related documents that included the Updated Final Safety Analysis Report (UFSAR), Section 9.5.1, the fire hazards analysis report (FHAR), and the post-fire safe shutdown analyses.

The team also evaluated two licensee mitigating strategies for addressing large fires and explosions as required by Operating License Condition 2.C.8. Inspection of these strategies fulfills the inspection procedure requirement to inspect a minimum of one sample.

Specific documents reviewed by the team are listed in the attachment.

REACTOR SAFETY

Cornerstones: lnitiating Events, Mitigating Systems, and Barrier Integrity

==1R05 Fire Protection (lP 711 11.05T)

==

.01 Protection of Safe Shutdown Capabilities

a.

lnspection Scope The team reviewed the FHAR, safe shutdown analyses and supporting drawings and documentation to verify that safe shutdown capabilities were properly protected.

b.

The team ensured that applicable separation requirements of Section lll.G of 10 CFR 50, Appendix R and the licensee's design and licensing bases were maintained for the credited safe shutdown equipment and their supporting power, control, and instrumentation cables. This review included an assessment of the adequacy of the selected systems for reactivity control, reactor coolant makeup, reactor heat removal, process monitoring, and associated support system functions.

Findinos A finding was identified involving a safe shutdown analysis error that resulted in the failure to protect all cables associated with the credited CRD pump. Refer to Section

==1R05.06 of this report.

Passive Fire Protection lnspection Scope==

The team walked down accessible portions of the selected fire areas to observe material conditions and the adequacy of design of fire area boundaries (including walls, ceilings, floors, fire doors, and fire dampers), electrical raceway fire barriers, and equipment fire barriers to ensure they were appropriate for the fire hazards in the area.

The team reviewed installation, repair, and qualification records for a sample of openings and penetration seals to ensure the fill material was of the appropriate fire rating and that the installation met the engineering design. The team reviewed similar records for the fire protection wraps to ensure the material was of an appropriate fire rating and that the installation met the engineering design. The team also reviewed completed surveillance and maintenance procedures for selected passive fire protection features to verify that maintenance and inspection activities are adequate.

Findinqs No findings were identified.

Active Fire Protection lnspection Scope The team reviewed the design, maintenance, testing, and operation of the fire detection and suppression systems in the selected plant fire areas. This included verification that the manual and automatic detection and suppression systems were installed, tested, and maintained in accordance with the National Fire Protection Association (NFPA) code of record and that each suppression system would control or extinguish fires associated with the hazards in the selected areas. A review of the design capabilities of the suppression agent delivery systems were verified to meet the code requirements for the a.

.02.03

b.

a.

b.

a.

.04 hazards involved. The team also performed a walkdown of accessible portions of the

detection and suppression systems in the selected areas as well as a walk down of major system support equipment in other areas (e.9. fire pumps and carbon dioxide storage tanks and supply system) to assess the material condition and the operational lineup and availability of the systems and components. The team reviewed electric and diesel fire pump flow and pressure tests to ensure that the pumps were meeting their design requirements. The team also reviewed the fire main loop flow tests to ensure that the flow distribution circuits were able to meet the design requirements.

The team assessed the fire brigade capabilities by reviewing training, qualification, and drill critique records. The team also compared pre-fire plans for the selected fire areas with as-built plant conditions and fire response procedures to verify fire-fighting pre-fire plans are consistent with the fire protection features and potentialfire conditions described in the FPP. In addition, the team inspected the fire brigade equipment (including smoke removal equipment) to determine operational readiness for fire fighting.

Findinos No findings were identified.

Protection From Damaqe From Fire Suppression Activities lnspection Scope The team performed document reviews and plant walkdowns to verify that redundant trains of systems required for hot shutdown, which are located in the same fire area, are not subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:

o A fire in one of the selected fire areas would not indirectly, through production of smoke, heat, or hot gases, cause activation of suppression systems that could potentially damage all redundant safe shutdown trains; r A fire in one of the selected fire areas (or the inadvertent actuation or rupture of a fire suppression system) would not indirectly cause damage to all redundant trains (e.9. sprinkler caused flooding of other than the locally affected train); and,

. Adequate drainage is provided in areas protected by water suppression systems.

Findinqs No findings were identified.

.05 Shutdown Caoabilitv - Normal and Alternative

lnspection Scope The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings (P&lDs), electrical drawings, the UFSAR, and other supporting documents for the selected fire areas to verify that the licensee had properly identified the systems and components necessary to achieve and maintain safe shutdown conditions.

The team assessed the adequacy of the selected systems and components for reactivity control, reactor coolant makeup, reactor heat removal, process monitoring, and support system functions. This review included verification that alternative post-fire shutdown could be performed both with and without the availability of offsite power. Plant walkdowns were also performed to verify that the plant configuration was consistent with that described in the safe shutdown and fire hazards analyses. The team verified that the systems and components credited for use during shutdown would remain free from fire damage.

The team verified that the training program for licensed and non-licensed operators included alternative shutdown capability. The team also verified that personnel required for safe shutdown using the normal or alternative shutdown systems and procedures are trained and available onsite at all times, exclusive of those assigned as fire brigade members.

The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps to ensure the implementation and human factors adequacy of the procedures. The team also verified that the operators could be reasonably expected to perform specific actions within the time required to maintain plant parameters within specified limits.

Specific procedures reviewed for normal and alternative post-fire shutdown included the following:

. ABN-1, Reactor Scram, Rev. 10; o ABN-29, Plant Fires, Rev.24; o ABN-30, Control Room Evacuation, Rev. 16; and,

. 346, Operation of the Remote and Local Shutdown Panels, Rev. 17.

The team reviewed manual actions to ensure that they had been properly reviewed and approved and that the actions could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each fire area. The team also reviewed the periodic testing of the alternative shutdown transfer capability and instrumentation and controlfunctions to ensure the tests are adequate to ensure the functionality of the alternative shutdown capability.

a.

b.

a,

.06 Findinqs

No findings were identified.

Circuit Analvsis Inspection Scope The team verified that the licensee performed a post-fire safe shutdown analysis for the selected fire areas and the analysis appropriately identified the structures, systems, and components important to achieving and maintaining safe shutdown. Additionally, the team verified that the licensee's analysis ensured that necessary electrical circuits were properly protected and that circuits that could adversely impact safe shutdown due to hot shorts, shorts to ground, or other failures were identified, evaluated, and dispositioned to ensure spurious actuations would not prevent safe shutdown.

The team's review considered fire and cable attributes, potential undesirable consequences, and common power supply/bus concerns. Specific items included the credibility of the fire threat, cable insulation attributes, cable failure modes, and actuations resulting in flow diversion or loss of coolant events.

The team also reviewed cable raceway drawings for a sample of components required for post-fire safe shutdown to verify that cables were routed as described in the cable routing matrices.

Cable failure modes were reviewed for the following components:

r Emergency Diesel Generator 2;

. Electromatic Relief Valves;

. 'A'Control Rod Drive Pump;

. 'B' Core Spray Pump; and,

. Reactor Vessel Wide Range Level Instrument Ll-1413.

The team reviewed circuit breaker coordination studies to ensure equipment needed to conduct post-fire safe shutdown activities would not be impacted due to a lack of coordination. Additionally, the team reviewed a sample of circuit breaker maintenance records to verify that circuit breakers for components required for post-fire safe shutdown were properly maintained in accordance with procedural requirements.

Findinqs Control Cables for the Reactor Coolant Inventorv Makeup Source Not Protected From Fire Damaqe

Introduction:

The team identified a Green, non-cited violation (NCV)of 10 CFR 50, Appendix R, lll.G.2, in that Exelon failed to maintain the safe shutdown credited reactor coolant inventory makeup system free of fire damage in the event of a fire in the b.

'8'480 volt (V) switchgear room. Specifically, Exelon failed to assure that the control cables associated with the'A' CRD pump low suction pressure trip circuitry were protected from the effects of a fire in this area. Without the required protection, fire damage to the cables could cause the pump to trip and could also prevent operators from starting the pump.

Descriotion: The team requested several electrical schematics and wiring diagrams of instrumentation, control, and power circuits associated with components the licensee's analysis credited to be operable and free of fire damage for the selected inspection fire areas. While collecting the documents, Exelon engineers identified that a low pressure suction trip control circuit for the 'A' CRD pump was not included in the safe shutdown analysis. Exelon evaluated the affected circuitry and determined that two cables, that contained conductors used in the low suction pressure trip circuit, passed through the

'B'480V switchgear room and were not protected from fire damage. Fire induced failures of either of these cables in the 'B' 480V switchgear room could spuriously trip the

'A'CRD pump and render it inoperable from the main control room. The NRC is treating this issue as a NRO-identified finding because, although Exelon engineers identified the safe shutdown analysis discrepancy, the discrepancy would not have been identified if the NRC inspectors did not select the'A' CRD pump as an inspection sample.

10 CFR 50.48(bX1) requires that all nuclear power plants licensed to operate prior to January 1, 1979, must satisfy the applicable requirements of 10 CFR Part 50, Appendix R, Section lll.G. Appendix R, lll.G.2, requires, in part, that where cables or equipment, including associated non-safety circuits that could prevent operation or cause maloperation due to hot shorts, open circuits, or shorts to ground, of redundant trains of systems necessary to achieve and maintain hot shutdown conditions are located within the same fire area outside of primary containment, one of three means of protecting cables to ensure that one of the redundant trains is free of fire damage shall be provided. The three acceptable methods described in Appendix R, Section lllG.2 for maintaining one of the redundant trains in the same fire area free of fire damage are based on the use of physical barriers, spatial separation, and fire detection and an automatic fire suppression system. OCNGS FHAR Section 7.0, Rev. 15, stated that for a fire in the'B' 480V switchgear room, hot shutdown will be achieved using isolation condenser'A'for decay heat removal in conjunction with CRD pump 'A'for reactor coolant makeup. The failure to ensure the'A' CRD pump low pressure suction trip circuitry was protected by one of the three acceptable methods described in Appendix R, Section lll.G.2 was a performance deficiency.

Exelon entered this issue into its corrective action program for resolution as lssue Report (f R) 01 187591and established compensatory measures (an hourly fire watch in the

'B' 480V switchgear room). Exelon also promptly performed an extent of condition review and confirmed the 'B' CRD pump was not similarly affected for fire areas that credited its remote operation from the main control room. The team concluded that Exelon's interim compensatory measures were implemented in a timely manner and commensurate with the risk significance of the issue.

Analvsis: Exelon's failure to ensure the'A' CRD pump was available and not subject to a spurious trip on low suction pressure for a postulated 'B' 480V switchgear room fire was a performance deficiency. This finding was more than minor because it is associated with the externalfactors attribute (fire) of the Mitigating Systems Cornerstone and adversely affects the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e. core damage). Specifically, the availability of 'A' CRD pump was not ensured for a 'B' 480V switchgear room fire scenario.

The team evaluated this issue using Phase 1 of IMC 0609, Appendix F, Fire Protection Significance Determination Process (SDP), and determined that a Phase 2 or Phase 3 SDP evaluation would be required because a high degradation rating was assigned (due to the lack of any physical protection for the affected cables) and the fire area total fire frequency was relatively high (greater than 1E-6). A Senior Reactor Analyst (SRA)performed a Phase 3 SDP evaluation in which it was conservatively assumed the 'A' CRD pump failed for eight separate fire scenarios involving electrical equipment failures or transient combustibles. The results of the SDP were dominated by the availability of the condensate and feedwater systems for reactor coolant makeup when it was determined that circuits for these components were not routed through the 'B' 480V switchgear room. The team reviewed electrical circuits and cable routes with Exelon engineers to confirm that the condensate and feedwater systems could be appropriately credited during the Phase 3 evaluation. Based on the results of the Phase 3 SDP evaluation the team determined the issue was of very low safety significance (Green).

The team also determined that no cross-cutting aspects were associated with this finding. The performance deficiency occurred during initial development of the fire safe shutdown analysis in the 1980's and was not identified during a licensee project to update the fire safe shutdown analysis in the 1990's. Because the error occurred more than three years ago, the performance deficiency is not considered to be indicative of current licensee performance.

Enforcement.

10 CFR 50.48(bX1) requires that all nuclear power plants licensed to operate prior to January 1, 1979, must satisfy the applicable requirements of 10 CFR Part 50, Appendix R, Section lll.G. Appendix R, lll.G.2, requires, in part, that where cables or equipment, including associated non-safety circuits that could prevent operation or cause maloperation due to hot shorts, open circuits, or shorts to ground, of redundant trains of systems necessary to achieve and maintain hot shutdown conditions are located within the same fire area outside of primary containment, one of three means of protecting cables to ensure that one of the redundant trains is free of fire damage shall be provided. OCNGS FHAR Section 7.0, Rev. 15, stated that for a fire in the 'B'480V switchgear room, hot shutdown will be achieved using isolation condenser'A'for decay heat removal in conjunction with CRD pump'A'for reactor coolant makeup. Contrary to the above, on March 15,2011, the NRC identified that Exelon did not meet this requirement and had not historically met this requirement for the 'B' 480 V switchgear room fire area. Exelon failed to protect the'A' CRD pump motor control circuits from a postulated fire-induced circuit failure resulting in the potential for pump trip due to a fire induced low pressure suction trip. Because this finding was of very low safety significance and was entered into Exelon's corrective action program (lR 01 187591), this violation is being treated as an NCV, consistent with Section 2.3.2, of the NRC

.07.08

.09 b.

a.

Enforcement Policy. (NCV 500021912011007-001, Gontrol Cables for the Reactor Coolant Inventory Makeup Source Not Protected From Fire Damage)

Communications Inspection Scope The team reviewed safe shutdown procedures, the safe shutdown analysis, and associated documents to verify an adequate method of communications would be available to plant operators following a fire.

During this review the team considered the effects of ambient noise levels, clarity of reception, reliability, and coverage patterns. The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The team also verified that communications equipment such as repeaters and transmitters would not be affected by a fire.

Findinqs No findings were identified.

Emerqencv Liohtinq Inspection Scope The team observed the placement and coverage area of eight-hour emergency lights throughout the selected fire areas to evaluate their adequacy for illuminating access and egress pathways and any equipment requiring local operation or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an eight-hour capacity. Preventive maintenance procedures, the vendor manual, completed surveillance tests, and battery replacement practices were also reviewed to verify that the emergency lighting was being maintained consistent with the manufacturer's recommendations and in a manner that would ensure reliable operation.

Findinqs No findings were identified.

Cold Shutdown Repairs lnspection Scope The team verified that the licensee had dedicated repair procedures, equipment, and materials to accomplish repairs of components required for cold shutdown which might be damaged by the fire to ensure cold shutdown could be achieved within the time frames specified in their design and licensing bases. The team verified that the repair b.

.10 b.

.12 b.

.11 equipment, components, tools, and materials (e.9. pre-cut cables with prepared

attachment lugs) were available and accessible on site.

Findinqs No findings were identified.

Compensatorv Measures lnspection Scope The team verified that compensatory measures were in place for out-of-service, degraded or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.9. detection and suppression systems and equipment, passive fire barriers, or pumps, valves or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures compensated for the degraded function or feature until appropriate corrective action could be taken and that the licensee was effective in returning the equipment to service in a reasonable period of time.

The team reviewed compensatory measures in the form of manual actions for 10 CFR Part 50 Appendix R, Section lll.G.2 areas to verify that there is reasonable assurance that manual actions can be accomplished. Specific attributes reviewed include diagnostic instrumentation, environmental consideration, staffing, communications, equipment availability, training, procedures, and verification and validation.

Findinqs No findings were identified.

Fire Protection Prooram Chanoes lnspection Scope The team reviewed recent changes to the approved fire protection program to verify that the changes did not constitute an adverse effect on the ability to safely shutdown.

Findinqs No findings were identified.

Control of Transient Combustibles and lqnition Sources lnspection Scope The team reviewed the licensee's procedures and programs for the control of ignition sources and transient combustibles to assess their effectiveness in preventing fires and

.13 a.

in controlling combustible loading within limits established in the FHAR. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that transient combustibles and ignition sources were being implemented in accordance with the administrative controls.

Findinqs No findings were identified.

Laroe Fires and Explosions Mitiqation Strateqies Inspection Scope The team reviewed the licensee's preparedness to handle large fire or explosions by reviewing two mitigating strategies to verify they continue to meet operating license condition 2.C.17 by determining that:

r Procedures are being maintained and adequate; o Equipment is properly staged and is being maintained and tested; and, o Station personnel are knowledgeable and can implement the procedures.

Findinos One finding was identified and is documented in NRC Inspection Report 0500021 9/201 1 009.

orHER ACTTVTTlES [OAI ldentification and Resolution of Problems Corrective Actions for Fire Protection Deficiencies Inspection Scope The team verified that the licensee was identifying fire protection and post-fire safe shutdown issues at an appropriate threshold and entering them into the corrective action program. The team also reviewed a sample of selected issues to verify that the licensee had taken or planned appropriate corrective actions.

Findinqs No findings were identified.

b.

4. 4c.42

.01 a.

b.

Meetinqs. lncludino Exit Exit Meetinq Summarv The team presented their preliminary inspection results to Mr. Michael Massaro, Site Vice President, and other members of the site staff at an exit meeting on April 1, 2011.

An updated status of the findings was provided to Mr. J. Chrisley by telephone on April 28, 2011. No proprietary information was included in this inspection report.

ATTACHMENT

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

M. Carlson Fire Protection Safe Shutdown Engineer

J. Chrisley Regulatory Assurance Specialist

N. Onuorah Fire Protection Safe Shutdown Engineer

C. Pragman Exelon Corporate Fire Protection Manager

T. Prosser Fire Marshall

M. Taylor Exelon Corporate Fire Protection

T. Trettel Fire Protection System Manager

NRC

J. Rogge Chief, Engineering Branch 3, Division of Reactor Safety

J. Kulp

Senior Resident Inspector, Oyster Creek Nuclear Generating Station

J. Ambrosini Resident Inspector, Oyster Creek Nuclear Generating Station
B. Keighley Resident Inspector, Acting, Oyster Creek Nuclear Generating Station

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

OPEN/GLOSED

050002191201107-01 NCV Control Cables for the Reactor Coolant Inventory Makeup Source Not Protected From Fire Damage (Section 1R05.06)

LIST OF DOCUMENTS REVIEWED