GO2-03-146, August 2003 Monthly Operating Report for Columbia Generating Station

From kanterella
Jump to navigation Jump to search
August 2003 Monthly Operating Report for Columbia Generating Station
ML032690924
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 09/11/2003
From: Oxenford W
Energy Northwest
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GO2-03-146
Download: ML032690924 (3)


Text

ENERGY NORTHWEST PO. Box 968 Richland, Washington 99352-0968 September 11, 2003 G02-03-146 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 MONTHLY OPERATING REPORT AUGUST 2003

Dear Sir or Madam:

Transmitted herewith is the Monthly Operating Report for the month of August 2003 as required by Technical Specification 5.6.4.

Respectfully, WS Oxenford Plant General Manager Mail Drop 927M cc:

TP Gwynn - NRC RIV BJ Benney - NRC NRR NRC Senior Resident Inspector - 988C TC Poindexter - Winston & Strawn INPO ANI Library Utility Data Institute RN Shernan - BPA / 1399 rO4

OPERATING STATUS REPORT for Columbia Generating Station Date: September 1, 2003

1.

Docket: 50-397

2.

Reporting Period: August 2003

3.

Utility

Contact:

Patricia Campbell (509) 377-4664

4.

Design Electrical Rating (Net MWe): 1153

5.

Maximum Dependable Capacity - summer (Net MWe): 1107

6.

-Hours Reactor Critical

7.

Hours Generator On-Line

8.

Unit Reserve Shutdown Hours

9.

Net Electrical Energy (MWH)

MONTH 744.0 744.0 0.0 819,854 YEAR 4,234.0 4,113.1 0.0 4,363,574 CUMULATIVE 123,929.5 -

120,484.6 3,274.7 119,616,353

UNIT SHUTDOWNS DOCKET NO.: 50-397 UNIT NAME:

Columbia Generating Station DATE: September 1, 2003 COMPLETED BY: P. Campbell TELEPHONE: (509) 377-4664 REPORT PERIOD: August, 2003 Type Method of Cause / Corrective Actions F: Forced Duration Shutting No.

Date S: Scheduled (Hours)

Reason (1)

Down (2)

Comments 1w

SUMMARY

The plant began and ended the month at 100% power.

(1) REASON A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training &

Licebse Examination F - Administiation G - Operatiolal Error H - Other (2) METHOD 1 - Manual 2 - Manual Trip/Scram 3 - Auto Trip/Scram 4 - Continuation 5 - Other (Explain) li