DD-19-01, Letter from the Secretary to Petitioners Regarding Directors Decision DD-19-01
| ML19120A241 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley, Davis Besse, Perry |
| Issue date: | 04/30/2019 |
| From: | Annette Vietti-Cook NRC/SECY |
| To: | Dabaghi A, Kearney M Environmental Law & Policy Ctr |
| SECY/RAS | |
| References | |
| DD-19-01 | |
| Download: ML19120A241 (3) | |
Text
UNITED ST ATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SECRETARY Ms. Margrethe Kearney Ms. Andrene Dabaghi Environmental Law & Policy Center 35 East Wacker Drive, Suite 1600 Chicago, IL 60601
Dear Ms. Kearney and Ms. Dabaghi:
April 30, 2019 Re:
Director's Decision DD-19-01 FirstEnergy Nuclear Operating Company Docket Numbers:
Beaver Valley 334 & 50-412 Davis Besse 346 Perry 440 This is to inform you that the Commission has declined to review Director's Decision DD-19-01. Accordingly, the decision became a final agency action on April 29, 2019.
Sincerely,
~~-~
Annette L. Vietti-Cook Secretary of the Commission cc: Service list
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of
)
)
FIRSTENERGY NUCLEAR OPERATING
)
COMPANY
)
)
(Beaver Valley Power Station, Units 1 and 2
)
Davis-Besse Nuclear Power Station, Unit 1
)
Perry Nuclear Power Plant, Unit 1
)
Docket Nos. 50-334 and 50-412 50-346 50-440 CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LETTER FROM ANNETTE L. VIETTI-COOK TO ENVIRONMENTAL LAW & POLICY CENTER RE: DIRECTOR'S DECISION DD-19-01, have been served upon the following persons by U.S. mail or through NRC internal distribution.
Margrethe Kearney Andrene Dabaghi Environmental Law & Policy Center 35 East Wacker Drive, Suite 1600 Chicago, IL 60601 Paul A Harden Senior Vice President, Chief Operating Officer and Chief Nuclear Officer FirstEnergy Nuclear Operating Company 341 White Pine Drive Akron, OH 44320 David B. Hamilton Site Vice President-Perry FirstEnergy Nuclear Operating Company Perry Nuclear Power Station Mail Stop A-PY-A290 PO. Box 97, Perry, OH 44081-0097 Mark Bezilla Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State, Route 2 Oak Harbor, OH 43449-9760 Richard D. Bologna Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SSB PO. Box 4, Route 168 Shippingport, PA 15077 Brooke Clark, Esq.
Office of the General Counsel Mail Stop 14A44 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Ho K. Nieh, Director Office of Nuclear Reactor Regulation Mail Stop- 0-13H16 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Perry H. Buckberg, Sr. Project Manager 2.206 Petition Coordinator Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Mail Stop 8B1A U.S. Nuclear Regulatory Commission Washington, DC 20555-0001,
DIRECTOR'S DECISION DD-19-01 FIRSTENERGY NUCLEAR OPERATING COMPANY Dockets: Beaver Valley (50-334 & 50-412), Davis Besse (50-346), and Perry (50-440)
Tanya E. Hood, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Mail Stop - T-9E3 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Herald M. Speiser
\\
Office of the Secretary of the Commission Dated at Rockville, Maryland, this 301h day of April, 2019 2