Nuclear Material Transaction Report for New Fuel
ML25015A052
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 01/14/2025
From: Darrell Adams
Pacific Gas & Electric Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
DCL-25-004
Download: ML25015A052 (1)


Text

!fl Pacific Gas and Electric Company"'

PG&E Letter DCL-25-004 NMMSS Operations U.S. Department of Energy 1000 Independence Avenue, SW NA-ESH-12/Germantown Bldg.

Washington, DC 20585-1290 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Nuclear Material Transaction Report for New Fuel Dallas L. Adams Manager, Program Engineering Diablo Canyon Power Plant Mail code 10414/427 P.O. Box 56 Avila Beach, CA 93424 805.545.6182 Dallas.Adams@pge.com 10 CFR 74.15 Pursuant to 10 CFR 74.15(a), the enclosure provides two files in a computer-readable format of the Nuclear Material Transaction Report for materials received on January 6, 2025, and January 8, 2025. The files were prepared in accordance with NUREG/BR-0006, Revision 9, "Instructions for Completing Nuclear Material Transaction Reports," dated August 2020, and Nuclear Materials Management and Safeguards System (NMMSS) Report D-24, "Personal Computer Data Input for Nuclear Regulatory Commission Licensees," dated March 24, 2020.

If you have any questions regarding the enclosure, please contact Mr. Santosh Patel at (805) 545-3255.

Dallas L. Adams Enclosure cc: Diablo Distribution Mahdi 0. Hayes, NRC Senior Resident Inspector Samson S. Lee, NRC Senior Project Manager John D. Monninger, NRC Region IV Administrator NRC Document Control Desk A member of the STARS Alliance

, //9 /as date Callaway

  • Diablo Canyon
  • Palo Verde