CP-201800479, Transmittal of Revised Emergency Plan
| ML18227A151 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 08/09/2018 |
| From: | Sewell S Luminant Generation Co, TXU Energy, Vistra Operating Co. (VistraOpCo) |
| To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
| References | |
| CP-201800479, TXX-18051 | |
| Download: ML18227A151 (2) | |
Text
CP-201800479 TXX-18051 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ENERGY
~!liTXU I
~
9'* energy Luminant Steven I<. Sewell Senior Director, Engineering & Regulatory Affairs Luminant P.O. Box 1002 6322 North FM 56 Glen Rose, TX 76043 o 254.897.6113 Ref 10CFR50.4{b)(5) 10CFR50.54(q) 8/9/2018
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NOS. 50-445, 50-446 and 72-74 TRANSMITTAL OF REVISED EMERGENCY PLAN
Dear Sir or Madam:
Pursuant to 10CFR50.54{q), Vistra Operations Company LLC {Vistra OpCo) hereby submits a report of changes made in Revision 42 of the Comanche Peak Nuclear Power Plant (CPNPP) Emergency Plan, effective August 2, 2018.
A summary of each 10CFR50.54{q) based change analysis is included in the attached report.
Vistra OpCo has evaluated the Emergency Plan revision and determined the changes do not reduce the effectiveness of the existing Emergency Plan, and the Plan continues to comply with the standards set forth in 10CFR50.47(b) and the requirements of Appendix E to 10CFR50; therefore, the revision was made effective without prior NRC approval.
The latest revision of the CPNPP Emergency Plan is enclosed.
This communication contains no new licensing basis commitments regarding Comanche Peak Units 1 and 2 or the Independent Spent Fuel Storage Installation.
6555 SIERRA DRIVE IRVING, TEXAS 75039 0214-812-4600 j1 )U./'?
- u11ssz~
,Jf_/-
VISTRAENERGY.COM JJH 5.5
TXX-18051 Page 2 of 2 Should you have any questions, please contact Jim Barnette at (254) 897-5866 or James.barnette@luminant.com.
Attachment Enclosure c-Sincerely,
~.~.5<:~
Steven K. Sewell 10CFR50.54(q) Change Report and Analysis Summary Comanche Peak Nuclear Power Plant Emergency Plan Revision 42 Kriss Kennedy, Region IV Margaret Watford O'Banion, NRR Resident Inspectors, Comanche Peak Paul Elkmann, Senior Emergency Preparedness Inspector, Region IV