BYRON 2002-0108, September 2002 Monthly Operating Report for Byron Station Units 1 and 2
| ML023010582 | |
| Person / Time | |
|---|---|
| Site: | Byron |
| Issue date: | 10/15/2002 |
| From: | Kuczynski S Exelon Generation Co, Exelon Nuclear |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 2.07.0200, BYRON 2002-0108 | |
| Download: ML023010582 (8) | |
Text
Exelkn.
Exelon Generation Company, LLC wwwexeloncorp com Nuclear Byron Station 4450 North German Church Road Byron, I L 61010-9794 October 15, 2002 LTR:
BYRON 2002-0108 File:
2.07.0200 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455
Subject:
Monthly Operating Report In accordance with Technical Specification 5.6.4, '!Monthly Operating Reports," we are submitting the Monthly Operating Report for Byron Station, Units 1 and 2. This report covers the period September 1, 2002, through Septembe'r 30, 2002.
If you have any questions regarding this report, please contact Mr. William Grundmann, Regulatory Assurance Manager, at (815) 406-2800.
Respectfully, Stephen E. Kuczynski Plant Manager Byron Nuclear Generating Station SEKIDD/rah Attachment cc:
Regional Administrator - NRC Region Ill NRC Senior Resident Inspector-'Byron 'Station NRC Project Manager - NRR - Byron Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety
ATTACHMENT BYRON STATION, UNIT 1 AND UNIT 2 MONTHLY OPERATING REPORT EXELON GENERATION COMPANY, LLC FACILITY OPERATING'LICENSE'NOS. NPF-37 AND NPF-66 NRC DOCKET NOS. STN 50-454 AND STN 50-455
OPERATING DATA REPORT UNIT ONE DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-454 Byron One 10/15/02 D. Drawbauqh (815) 406-2813 REPORTING PERIOD: September, 2002 (Month/Year)
MONTH YEAR TO DATE CUMULATIVE
- 1.
Design Electrical Rating (MWe-Net).
The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.
- 2.
Maximum Dependable Capacity (MWe-Net).
The gross electrical output as measured at the output terminals of the turbine-generator during the most restrictive seasonal conditions minus the normal station service loads.
- 3.
Number of Hours the Reactor was Critical.
The total number of hours during the gross hours of the reporting period that the reactor was critical.
- 4.
Number of Hours the Generator was On Line (also called Service Hours). The total number of hours during the gross hours of the reporting period that the unit operated with breakers closed to the station bus. The sum of the hours the generator was on line plus the total outage hours should equal the gross hours in the reporting period.
- 5.
Unit Reserve Shutdown Hours.
The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was available for operation.
- 6.
Net Electrical Energy (MWH).
The gross electrical output of the unit measured at the output terminals of the turbine-generator minus the normal station service loads during the gross hours of the reporting period, expressed in megawatt hours. Negative quantities should not be used.
1,187 1,163 720 720 0
865,136 N/A N/A 6,122.25 6,109.18
'0 7,259,089 N/A N/A 127,077.82 126,073.72 0
130,697,666
UNIT SHUTDOWNS DOCKET NO.
50-454 UNIT NAME Byron One DATE 10/15/02 COMPLETED BY D. Drawbaucqh TELEPHONE (815) 406-2813 REPORTING PERIOD: September 2002 NO.
DATE TYPE DURATION REASON (1)
METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)
SHUTTING S: SCHEDULED DOWN (2)
COMMENTS
SUMMARY
- Uhit 1 On-Line During the Month of September.
(1)
Reason (2)
A - Equipment Failure (Explain)
B - Maintenance Test C-Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
UNIQUE REPORTING REQUIREMENTS (UNIT ONE)
-for the month of September, 2002
- 1.
Safety/Relief valve operations for Unit One. This information is provided pursuant to the reporting requirements contained in Technical Specification 5.6.4, "Monthly Operating Report."
VALVES ACTUATED NO. & TYPE ACTUATION PLANT CONDITION DESCRIPTION OF EVENT
- 2.
Licensee generated changes to Offsite Dose Calculation Manual.
None
- 3.
Indications of failed fuel.
None. Fuel Reliability Indicator: (FRI) = 3.07 E-06 giCi/cc.
- 4.
Licensee Events Reports The following is a tabular summary of all Licensee Event Reports for Byron Station, Unit One, issued during the reporting period, September 1, 2002, through September 30, 2002. This information is provided,pursuant to the reportable occurrence reporting requirements as-set forth in 10 CFR 50.73, "Licensee Event Report System."
Report Date Title of Occurrence
-DATE None Licensee Event Report Number None
OPERATING DATA REPORT UNIT TWO DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-455 Byron Two 10/15/02 D. Drawbauqh (815) 406-2813 REPORTING PERIOD: September, 2002 (Month/Year)
- 1.
Design Electrical Rating (MWe-Net).
The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.
- 2.
Maximum Dependable Capacity (MWe-Net).
The gross electrical output as measured at the output terminals of the turbine-generator during the most restrictive seasonal conditions minus the normal station service loads.
- 3.
Number of Hours the Reactor was Critical.
The total number of hours during the gross hours of the reporting period that the reactor was critical.
- 4.
Number of Hours the Generator was On Line (also called Service Hours). The total number of hours during the gross hours of the reporting period that the unit operated with breakers closed to the station bus. The sum of the hours the generator was on line,plus the total outage hours should equal the gross hours in the reporting period.
- 5.
Unit Reserve Shutdown Hours.
The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was available for operation.
- 6.
Net Electrical Energy (MWH).
The gross electrical output of the unit measured at the output terminals of the turbine-generator minus the normal station service loads during the gross hours of the reporting period, expressed in megawatt hours. Negativequantities should not be used.
MONTH YEAR TO DATE 1,155 1,131 382.20 382.20 "0
431,775 N/A N/A 6,086.40 6,078.70 0
7,158,509 CUMULATIVE N/A N/A 119,169.78 118,387.98 0
123,152,502
UNIT SHUTDOWNS DOCKET NO.
50-455 UNIT NAME Byron Two DATE 10/15/02 COMPLETED BY D. Drawbauqh TELEPHONE (815) 406-2813 REPORTING PERIOD September 2002 NO.
DATE TYPE DURATION REASON (1)
METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)
SHUTTING S: SCHEDULED DOWN (2)
COMMENTS 1
09/16/02 S
337.8 C
2 B2R10
SUMMARY
- Unit Two was off-line for scheduled refuel outage.
(1)
Reason A - Equipment Failure (Explain)
B - Maintenance Test C - Refueling D - RegUlatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
(2)
Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
UNIQUE REPORTING REQUIREMENTS (UNIT TWO) for the month of September, 2002
- 1.
Safety/Relief valve operations for Unit Two. This information is provided pursuant to the reporting requirements contained in Technical Specification 5.6.4, "Monthly Operating Report."
- VALVES, ACTUATED NO. & TYPE ACTUATION PLANT CONDITION DESCRIPTION OF EVENT
- 2.
Licensee generated changes to Offsite Dose Calculation Manual.
None
- 3.
Indications of failed fuel.
None. Fuel Reliability Indicator: (FRI) = 4.95 E-06 [tCi/cc.
- 4.
Licensee Events Reports The following is a tabular summary of all Licensee Event Reports for Byron Station, Unit Two, issued during the reporting period, September 1, 2002, through September 30, 2002. This information is provided pursuant to the reportable occurrence reporting requirements as set forth in 10 CFR 50.73, "Licensee Event Report System."
Report Date Title of Occurrence DATE None Licensee Event Report Number None