Progress Energy JUL 0 9 2004 SERIAL: BSEP 04-0092 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Docket Nos. 50-325 and 50-324/License Nos. DPR-71 and DPR-62 Operator Licensing Examination Data Ladies and Gentlemen:
This submittal provides the Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc. (PEC) response to NRC Regulatory Issue Summary 2004-10, "Preparation and Scheduling of Operator Licensing Examinations" for the Brunswick Steam Electric Plant, Unit Nos. 1 and 2. The enclosed NRC Form 536, "Operator Licensing Examination Data," provides a proposed operator licensing examination schedule, the estimated number of applicants to be tested, and a proposed generic fundamentals examination schedule for calendar years 2005 through 2008.
Please refer any questions regarding this submittal to Mr. Leonard R. Beller, Supervisor -
Licensing/Regulatory Programs, at (910) 457-2073.
Sincerely, Edward T. O'Neil Manager - Support Services Brunswick Steam Electric Plant GLM:glm
Enclosure:
NRC Form 536, "Operator Licensing Examination Data" Progress Energy Carolinas, Inc.
Brunswick Nuclear Plant P.O. Box 10429 Southport, NC 28461 MOO
Document Control Desk BSEP 04-0092 / Page 2 cc:
U. S. Nuclear Regulatory Commission, Region II ATIN: Dr. William D. Travers, Regional Administrator Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATIN: Mr. Michael E. Ernstes, NRC Region II Chief, Operator Licensing and Human Performance Branch Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATTN: Mr. Eugene M. DiPaolo, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission ATTN: Ms. Brenda L. Mozafari (Mail Stop OWFN 8G9) (Electronic Copy Only) 11555 Rockville Pike Rockville, MD 20852-2738 Ms. Jo A. Sanford Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510
Enclosure Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Docket Nos. 50-325 and 50-324/License Nos. DPR-71 and DPR-62 Operator Licensing Examination Data NRC Form 536. "Operator Licensing Examination Data"
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 07131=2005 (5-203)
Estimated burden per response to comply with this voluntary Information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This Information collection Is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records Management Branch (T-6 E6). U.S. Nutear Regulatory Commission, Washington. DC 20555-0001. or by Internet e-mail to EXAMINATION DATA infocoliects @nrc.gov. and to the Desk Officer. Office of Information and
.TRegulatory Afairs NEOB-10202. (3150-0131). Oce of Management and
.!I Budget. Washington. DC 20503.
If a means used to Impose an Information
.collection does not display a currenty valid 0MB control number, the NRC may
,not conduct or sponsor, and a person Is not required to respond to, the informnaton collection.
FACILITY NRC REGION Brunswick Steam Electric Plant, Unit Nos. 1 and 2 2
A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2005 cy2Y06 l
2007 cy2008 ESTIMATED NUMBER OF LICENSEE-PREPARED 1
0 0
0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0
0 1
1 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2005 Cy200 6
Cy2007 Cy2008 NUMBER OF REACTOR 0
OPERATORS 0
6 6
NUMBER OF SENIOR REACTOR 3
OPERATORS - INSTANT 0
3 NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 0
0 3
3 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 6
0 0
PROPOSED DATES PRIMARY DATE 08/15/2005 N/A 02/12/2007 11/03/2008 ALTERNATE DATE 10/24/2005 N/A 02/05/2007 11/17/2008 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED CY 2005 CY 2006 NUMBER MARCH JUNE SEPTEMBERDECEMBER MARCH JUNE SEPTEMBERDECEMBER ESTIMATED NUMBER OF 0