BSEP-83-3625, Monthly Operating Repts for Oct 1983
| ML20078R655 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 10/31/1983 |
| From: | Harrison F CAROLINA POWER & LIGHT CO. |
| To: | Deyoung R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
| References | |
| BSEP-83-3625, NUDOCS 8311150245 | |
| Download: ML20078R655 (18) | |
Text
-.
~
-APPENDIX
-DOCKET NO.: 050-325 UNIT: Brunswick No. 1 DATE: November 1983 COMPLETED BY: Frances Harrison OPERATIONS
SUMMARY
-BRUNSWICK UNIT NO. 1 Brunswick Unit No.1 operated at a 54.96% availability factor for the month of October with a 49.73% capacity factor. There were four power reductions and one scheduled off-line outage. Details are in Appendix D, the Unit Shutdowns and Power Reductions log.
There are 656 BWR and 160 PWR spent fuel bundles in the Brunswick No. 1 fuel pool.
P'2Wam.
Y PDR
...;~.,-,.--....---
P:
^
APPENDIX'B
[.i
? AVERAGE' DAILY' POWER LEVEL
- ^
DOCKET NO. 050-0325 j.
UNIT BRUNSWICK UNIT 1 DATE 11/02/83
[
i COMPLETED BY FRANCES HARRISON I
. TELEPHONE (919)457-9521 l-j' ; OCTOBER
-L1983 r
AVG.: DAILY POWER LEVEL
= DAY.
AVG. DAILY POWER LEVEL
(.
' DAY.
L (MWE-NET),
(MWE-NET) 2
'l 730-17 68ti t
ll 2
"724 18 3
729 19
-11
'3
" 4 72B I 20
-10 4
'5-
'729-21-
-11 i
~6-7261 2 2- -
-11
.7 728 23
-12 I
8-682 24
-12 j
9
-733 25
-12, i
g 10' 730' 26
-10 11
'731 27
-7
'12 729 28
-6 13
'732 29
-5 14 731 30
-6 1
15 729 31
-6 l
l 16 736 i
1.16 e
OPERATING DATA REPORT DOCKET NO. 050-0325 DATE 11/01/03 COMPLETED BY FRANCES HARRISON TELEPHONE (919)457-9521 OPERATING STATUS.
1.
UNIT'NAME: BRUNSWICK UNIT 1 i NOTES I
2.
REPORTING PERIOD: OC"0BER 83 I
I 3.' LICENSED'THERNAL POV'R (MWT): 2436 i
I 4.
NAMEPLATE RATING (GROSS MWE): 867.0 l
I 5.
DESIGN ELECTRICAL RATING (NET MWE): 821.0 1
l 6.
MAX DEPENDADLE CAPACITY (GROSS MWE): 815.0 1 I
7.
MAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.
IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
9.
POWER LEVEL TO WHICH RESTRICTED IF ANY '(NET MWE):
- 10. REASONS FOR RESTRICTION IF-ANY:
THIS YR TO CIP,bl MONTH DATE ATIVE
- 11. HOURS IN REPORTING PERIOD 745.00 7296.00 58057.00
- 12. NUMBER OF HOURS REACTOR CRITICAL 409.43 1533.41 35421.88
- 13. REACTOR RESERVE SHUTDOWN HRS
.09
.00 1647.10 i
- 14. HOURS GENERATOR ON LINE 409.43 1210.23 33180.26 15; UNIT RESERVE SHUTDOWN HOURS
.00
.00
.00
- 16. GROSS THERMAL ENERGY GEN. (MWH) 939393.71 2547049.43 66443868.29
- 17. GROSS ELEC. ENERGY GEN. (MWH) 306319.00 821411.00 21883599.00
- 18. NET ELEC. ENERGY GENERATED (MWH) 292703.00 750010.00 20975129.00
- 19. UNIT SERVICE FACTOR 54.96 16.59 57.15
- 20. UNIT AVAILABILITY FACTOR 54.96 16.59 57.15
- 22. UNIT CAP. FACTOR (USING DER NET) 47.86 12.52 44.01
- 23. UNIT, FORCED OUTAGE RATE
.00
.00 23.35 24.-SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
CRD 10-18 11-12-83 l
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
126.'
UNITS IN TEST STATUS.(PRIOR TO COMMERCIAL OPERATION): FORCAST ACHEIVED INITIAL CRITICALITY
~~
INITIAL ELECTRICITY
-~~-----
COMMERCIAL OPERATION 1 16 - 9 g
y -
w
UNIT SHUTDOWNS AND POWER REDUCHONS DOCKET NO. 050-0325 UNIT NAME Brunswick 1 DATE November 1983 October 1983 COMPLETED BY Frances Harrison REPORT MONTH TELEPHONE 457-9521 w.
~
B g
w Lic s##
Cause & Corrective
'g G
.E g a:
Event ts T Action to No.
Date g
j
$ 5.
E jd Repor: #
iN0 d"
g Prevent Recurrence i
83-014 831002 F
0.00 A
5 NA XX CRDRVE Control Rod 38-19 uncoupled preventing 100% power opera.. ion.
.r
/
I i
t i
I 2
3 4
F: Forced Reason:
Method:
Exhibit G. instructions S: Scheduled A-Equipment Failure (Explain)
I-Manual for Preparation of Data B-Maintenance of Test 2 Manual Scrarn.
Entry Sheets for Licensee C. Refueling 3 Automatic Scram.
. Event Reporn (LER) File (NUREG-D Regulatory Restriction E-Operator Training & Ucense Examination 4-Continuatlons -
0161)
F-Administrative 5-Load Reductions 5
j G-Operational Error (Explain) 6-Other Exhibit I-Same Source l'8/77)
Il-Other(Explain) 1 I
t
... ~...
o n n..
UNIT SHUTIX)WNS AND POWER REDUCTIONS DOCKET NO. 050-0325 UNIT NAME Brunswick l DATE November 1983 REPORT MONTil October 1983 COMPLETED BY Frances Harrison TELEPilONE 457-952:
i q
% m3 a
a r.
No.
Date E
353 LI'*"5
.E, *
$*3 Cause & Corrective b.' ' " '
E,3
$u Action to f3"g O:$
N B
U
- g m Repwa#
mo g
Prevent Recurrence 6
1 83-016 831008 S
0.00 B
5 NA
'Z XXXXXX PT completion (PT-01.3. lP and PT-14.1).
4 t
1 I
2 3
4 F: Forced Reason:
Method:
Exhibit G. Instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram.
Entry Sheets for Licensee C Refueling 3 Automatic Scram.
Event Report (LER) File (NUREG-D. Regulatory Restriction 0161)
E. Operator Training & Ucense Examination 4-Continuations -
F: Administrative 5-Load Reductions 5
G-Operational Error (Explain) 6-Other Exhibit 1.Same Source (4/77)
Il4)ther(Explain)
U"
- 2 1.
' " ~
^
W-
UNIT SilUTDOWNS AND POWER REDUCDONS DOCKETNO. 050-0325 UNIT NAME Brunswick 1 DAyg November 1983 October 1983 COMPLETED BY Frances Harrison REPORT MONTil TELEPilONE 457-9321 w.
E E
w
.$ g
'h jY5 Licensee p,
Cause & Corrective No.
Date g
3g s
,g g 5 Event g,3 Eb
^ ' " " ' "
H fE jig Report #
mo Prevent Recurrence g
d
!Z XXXXXX 83-017 831017 S
0.'00 B
5 NA Commence shutdown as prescribed in CP-01 for CRD outage.
.e l
1 i
I I
2 3
4 F: Forced Reason:
Method:
Exhibit G Instructions S: Scheduled A Equipment Failure (Explain)
I Manual for Preparation of Data B-Maintenance of Test 2-Manual Scram.
Entry Sheets for Licensee C Refueling 3-Automatic Scram.
. Event Report (LER) File (NUREG.
D-Regulatory Restriction E-Operalor Training & IJcense Examination 4-Continuations -
0164)
F: Administrative 5-Load % ductions s
G-Operational Error (Explain) 6-Otner Exhibit I-Same Source 14/77) 11-01her(Explain)
. ~ ~
^'
^
UNITSHUTDOWNS AND POWER REDUCTIONS DOCKET NO. _050-0325 UNIT NAME Brunswick I DATE November 1983 REPO'tT MON 11f October 1983 COMPLETED BY _ Frances Harrison TELEPHONE 457-952I
.! E 3
Y Licensee
,E,
- k*.
Cause & Corrective No.
Date g
g 5j g
,g g y Event u7 Action to P
$E 5
j di g Report #
AG u
Prevent Recurrence 6
0)00 83-018 831017 F
A 5
NA
- D Penetr Received multiple trips on MSL monitor fesulting in approximately eight to twelve half scrams and half Group is.
Cause of trips:
Introduction of ladders into MSIV pit striking
~
detectors on main steam line.
l e
r i
i 1
2 3
4 i
F: Forced Reason:
Method:
Exhibit G -Instructions S: Scheduled A E uipment Failure (Explain) 1-Manual for Preparation of Data B. Maintenance of Test 2 ManualScram.
Entry Sheets for Licensee C-Refueling 3 Automatic Scram.
Event Report (LER) File (NUREG-D Regulatory Restriction 0161)
E-Operator Training & Ucense Examination 4-Continuatlons -
F: Administrative 5-Load Reductions 5
G-Operational Error (Explain) 6-Other Exhibit I Same Source
('8/77) ll-Other (Explain)
^-
v-
' ' ~ " " ' '
,-y-
.--gn
.v.au_m.... u a a
- i.
050-0325 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
UNITNAME Brunswick 1 DATE November 1983 REPORT MONTH October 1983 t N-TED BY Frances Harrison TELEPHONE 457-9521 l
E
.! E
'h
)Y5 Licensee Eg vt Cause & Corrective No.
Date k
Eg s
55 Event g3 3
Action to H
$E 5
jsy Repost #
mo u
d Prevent Recunence S83-019 831018 S
335.57 B
2 NA XX CRDRVE CRD outage.
1 I
I 2
3 4
F: Forced Reason:
Method:
Exhibit G Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance of Test 2-Manual Scram.
Entry Sheets for I.icensee C Refueling 3 Automatic Scram.
. Event Report (LER) File (NUREG-D Regulatory Restriction 0161)
E-Operator Training & Ucense Examination 4-Continuations F Administrative S-Load Reduetions 5
G-Operational Error (Explain) 6-0ther Exhibit I-Same Source 19/77) llother(Explain)
APPENDIX DOCKET NO.-
050-324 UNIT:
Brunswick No. 2 DATE: November 1983 COMPLETED BY: Frances Harrison OPERATIONS
SUMMARY
BRUNSWICK UNIT NO. 2 Brunswick Unit No. 2 operated at a 100% availability factor for the month of October with a 97.90% capacity factor. There were six power reductions.
Details are in Appendix D, the Unit Shutdowns and Power Reductions log.
There are 424 BWR and 144 PWR spent fuel bundles in the brunswick No. 2 fuel pool.
- 2 APPENDIX B-
~
AVERAGE DAILY POWER LEVEL DOCKET NO. 050-0324 UNIT BRUNSWICK UNIT 2 DATE 11/02/83 COMPLETED BY FRANCES HARRISON.
TELEPHONE (919)457-9521
'CCTOBER
~1983
' DAY
- AVG.
- DAILY POWER LEVELL DAY AVG. DAILY POWER LEVEL
-(MUE-NET)
.(MWE-NET) 1-749.
17' 780 2
782 18' 775 3
764
' 19 -
771 14 758 20 768
'5 770 21 761 6-759 22 765 7
786 23 761 B'
760.
24 790
^
- 9 786
'25 790
+
L10 786 26 790 P-11; 785 27 786 12 780_
28 788 "13 -
778 29 776^
11 4.
777.
30 791 15' 778 31 742 16~
7A6 1.16 - 8
OPERATING DATA REPORT DOCKET NO. 050-0324 DATE 11/01/83 COMPLETED BY FRANCES HARRISON TELEPHONE (919)457--9521 OPERATING STATUS 1.
UNIT NAME:' BRUNSWICK UNIT 2 1 NOTES I
2.
REPORTING PERIOD: OCTOBER 83 i
i 3.
LICENSED THERMAL POWER (MWT): 2436 I
I 4.
NAMEPLATE RATING (GROSS MWE): 867.0 1
5.
DESIGN ELECTRICAL RATING (NET MWE): 821.0 I
i 6.
MAX DEPENDABLE CAPACITY (GROSS MWE): 815.0 I i
7.
HAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.
IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
9.
POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE):
- 10. REASONS FOR RESTRICTION IF ANY:
THIS YR TO CUMUL MONTH DATE ATIVE
- 11. HOURS IN REPORTING PERIOD 745.00 7296.00 70081.00
- 12. NUMBER OF HOURS REACTOR CRITICAL 745.00 5916.72 44692.84 13.~ REACTOR' RESERVE SHUTDOWN HRS
,00
.00
.00
- 14. HOURS GENERATOR ON LINE 745.00 5607.88 41758.62
- 15. UNIT RESERVE SHUTDOWN HOURS
.00
.00
.00
- 16. GROSS THERMAL ENERGY GEN. (MUH) 1764998.93 12224465.79 78521449.15
- 17. GROSS ELEC. ENERGY GEN. (MWH) 594110.00 4074948.00 26091640.00
- 18. NET ELEC. ENERGY GENERATED (MWH) 576213.00 3930559.00 25022485.00
- 19. UNIT SERVICE FACTOR 100.00 76.86 59.59
- 20. UNIT AVAILADILITY FACTOR 100.00 76.06 59.59
- 21. UNIT CAP. FACTOR (USING MDC-NET) 97.90 68.19 45.20
- 22. UNIT CAP. FACTOR (USING DER NET) 94.21 65.62 43.49
- 23. UNIT FORCED OUTAGE RATE 00 10.22 15.98
- 24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
IGSCC Inspection 10/30/83 - 11/12/83
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORCAST ACHEIVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 1.16 - 9
9 UNIT SHUTDOWNS r MD POWER REDUCTIONS DOCKET NO. 050-0325 UNIT NAME Brunswick 2 DATE November 1983 REPORT MONTH October 1983 COMPLETED BY _ Frances Harrison TFLEPHONE 457-9521 q
':5 c 3 E
c re No.
Date E.
h_5 3 5b Li'*"'**
b'=
{4 Cause & Corrective
~
Ei 2
5 3m Event g7 AC8I"" 8" O :*$
s
- g a y Report a mo Eu g
Prevent Recurrence S
-l 83-098 831003 F
0.00 A
5 NA HC HTEXCH Waterbox work - maintenance on outlet manway.
1 l
.t g
l t
- i I
2 3
4 F: Forced Reason:
Method:
Exhibit G -Instructions S: Scheduled A. Equipment Failure (Explain) l-Manual for Preparation of Data B-Maintenance of Test 2-Manual Scram.
Entry Sheets for Licensee C-Refueting 3-Automatic Scram.
Event ReporI(LER) File (NUREG-(
D-Regulatory Restriction E-Operator Training & Ucense Examination 4-Continuations -
0161)
F Administrative 5-Load Reductions 5
G-Operational Error (Explain) 6-Other Exhibit 1.Same Source (4/77)
Il-Other (Explain)
,n-
- - - - ~..
-- - -. - ~
-.--w-
UNITSHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
050-0326 UNITNAME Brunauick 2 DATE November 1983 l
REPORT MONTH October 1983 COMPLETED By Frances Harrison TELEPHONE 457-9521 Ye
.! 3 Y
licensee
,Eg Cause & Corrective I
H(
3g g
2g5 Event gg l
No.
Date f}
o-Action to
$E 5
jdi g Report #
mU Prevent Recurrence i
6 83-099 831006 F
0 00 A
5 NA CH PUMPXX 2A Rx. Recire. pump tripped.
er I
I 2
3 4
F: Forced Reason:
Method:
Exhibit G Instructions S: Scheduled A-Equiprnent Failure (Explain) 1 Manual for Preparation of Data B-Maintenance of Test 2 Manual Scram.
Entry Sheets for Licensee C-Refueling 3 Automatic Scram.
Event Report (LER) File (NUREG.
D-Regulatory Restriction EOperator Training & Ucense Examination Is-Continuations -
0161)
F: Administrative 5-Load Reductions 5
G-Operational Error (Explain)
(,-Other Exhibis 1 Same Source 1"/77)
Il-Other(Explain)
. m www, +, =mc a -
s me v-w.
r w*
.w-
=.,,*a
--e-
-, e w,,-++-*-4
.==4--e-.-
---<e
4 UNITSilUTDOWNS AND POWER REDUCTIONS DOCKET NO. 050-0324 i
UNIT NAME Brunswick 2 DATE November 1983 REPORT MONTH October 1983 COMPLETED BY Frances Harrison TELEPHONE 457-952I I
q
)e5 E
e c
No.
Date E.
j_$
j g53 h
"5 Cause & Corrective y
!i S 2
-5 3%
"I E3 o
Action to g 6i g Repor #
mo gO o=
m g
Prevent Recurrence 6
i j
83-100 831008 S
0.00 B
5 NA ZZ XXXXXX Reduced power to perform PT-40.2.5, PT-14.1, PT-01.3.lP, and PT-01.3.2P-2.
i i
.l
.e
.i I
I
+
J a
l t
I 2
3 4
1 F: Forced Reason:
Method:
Exhibit G. Instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2 Manual Scram.
Entry Sheets for Licensee j
C. Refueling
- 3. Automatic Scram.
. Event Repor (LER) File (NUREG.
D-Regulatory Restriction l
E-Operator Training & IJcense Examination 4-Continuatlons -
0161)
F Administrative 5-Load Reduetions 5
G Operational Error (Explain) 6-Other Exhibit I.Same Source j
('8/77) llother(Exp!ain) i I
i i
UNIT SHUTDOWNS AND POWER REDUCHONS DOCKET NO. 050-0324 UNIT NAME Brunswick 2 DATE November 1983 REPORT MONDI October 1983 COMPLETED BY Frances Harrison TELEPHONE 457-952I q
C FB Q M C
S.
7 53 L
- "S*C 5'(
g"3 S.$
f Cause & Corrective No.
Date E.
0 5 3" E"'
E3 Qo Action to Q *@
$5l Report #
vi o Prevent Recurrence 1
6 4
83-101 831016 S
0.'00 B
5 NA
'Z XXXXXX Removed 2A CDD from service for changeout.
}
s I
i l
l i
l l
l I
4 I
2 3
4 l
F: Forced Reason:
Method:
Exhibit C. instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B4taintenance of Test 2-Manual Scram.
Entry Sheets for Licensee i
C-Refucting 3 Automatic Scram.
Event Repor (LER) File (NUREG.
D Regulatory Restriction 0161)
E4)perator Training & Ucense Examination 4-Continuatlons -
i F Administrative 5-Load Reductions S
j G-Operational Error (Explain) 6-Other Exhibit I.Same Source (4/77)
II-Other (Explain) i 1
m o
. o su
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 050-0324 UNIT NAME Brunswick 2 DATE November 1983 REPORT MONTil october 1983 COMPLETED BY _ Frances Harrison TELEPif0NE 457-9521 w.
E C
98 o ta "E.
$,5 3
y Licensee E*
Cause & Corrective Nii.
Date
- o
=
.c s a:
Event g,,
.y
$5 5
j di g Report #
N0 3
Action to Prevent Recurrence
,d 83-102 831023 F
0.'00 A
5 NA IIC flTEXCll Reduced power due to the temperature rise across A-N waterbox. Will j
perform OP-29, Section K, Clearing Clogged Debris Filter.
.e I
I 2
3 4
F: Forced Reason:
Method:
Exhibit G-Instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance of Test 2-Manual Scrarn.
Entry Sheets for Licensee C-Refueling 3 Automatic Scram.
Event ReporI (LER) File (NUREG.
D Regulatory Restriction E-Operator Training & Ucense Examination 4-Continuatlons -
0161)
F-Administrative 5-Load Reductions 5
G Operational Error (Explain) 6-Other Exhibit I Same Source
('8/77)
Il-Other (Explain)
4 UNIT SilUTDOWNS AND POWER REDUCTIONS DOCKET NO. 050-0324 UNITNAME Brunswick 2 DATE November 1983 COMPLETED BY Frances Harrison REPORT MONTil ne.rnhar 1983 TELEPif0NE 457-9521 w.
I 4 sa 5 3
e_
ci
.E e E
g.E 'A Licensee g *,
g%
Cause & Currective No.
Date g
3g g
jg5 Event t: Y o3 Action to t
b
$E 5
j@g Report #
- d gu Prevent Recurrence 8
83-104 831031 S
0.00 H*
5 NA HC HTEXCH Removed A-S waterbox from service to comply with winter flow minimization schedule.
1 1
t I
4 s
t l
c a
- EPA Permit Restriction y
3 4
F: Forced Reason:
Method:
Exhibit G. Instructions S: Scheduled A Equiprnent Failure (Explain) 1-Manual for Preparation of Data B-Maintenance of Test 2-Manual Scrarn.
Entry Sheets for Licensee i
C-Refueling 3 Automatic Scram.
Event ReporI (LER) File (NUREG-s D-Regulatory Restriction E-Operator Training & Ucense Examination Is-Continuations -
0161)
F: Administrative 5-Load Reductions 5
G-Operational Error (Explain) 6-0ther Exhibit 1.Same Source (9/77)
Il-OLher(Explain)
~ '"~
" * ^ ^
g e Q..
....r...
m._.
CD&L I
Carolina Power & Light Company Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 28461-0429 November 4, 1983 FILE: B09-13510C SERIAL:
BSEP/83-3625 Mr. R. C. DeYoung, Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 LICENSE NOS. DPR-71 AND DPR-62 DOCKET NOS. 50-325 AND 50-324 MONTHLY OPERATING REPORT
Dear Mr. DeYoung:
In accordance with Technical Specification 6.9.1.6 for the Brunswick Steam Electric Plant, Unit Nos. 1 and 2, Carolina Power & Light Company herewith submits the report of operating statistics and shutdown experience for the month of October 1983.
Very truly yours, C. R. Dietz, General Manager Brunswick Steam Electric Plant FH/c1h/ LETCH 2 Attachment cc:
Ms. J. C. Baker Mr. S. W. McDowell Mr. J. P. O'Reilly Mr. S. L. Rosen