.fEf BOSTON ED60N Executive Offices 800 Boylston Street Boston, Massachusetts 02199 November 20, 1987 Ralph G. Bird BECo 87-185 Senior Vice President - Nuclear U. S. Nuclear Regulatory Commission Document Control Desk Hashington, DC 20555.
License DPR-35 Docket 50-293 ADDITIONAL INFORMATION REGARDING PILGRIM STATION SAFETY ENHANCEMENT PROGRAM (SEP)
OPERATOR-ORIENTED IMPROVEMENTS
Dear Sir:
The purpose of this letter is to transmit additional descriptive materials related to the Pilgrim Nuclear Power Station Safety Enhancement Program (SEP) which Boston Edison Company (BECo) is implementing pursuant to 10 CFR 50.59.
Attached for your information is detailed documentation addressing operator-oriented improvements involving emergency operating procedures and training.
BECo provided this information to the NRC in preliminary form during the August 4, 1987 meeting on the SEP.
The documentation submitted here supersedes the preliminary versions of the information previously provided.
A summary description of the BECo Pilgrim Nuclear Power Station Emergency Operating Procedures (EOP) Training Program is also attached for your information.
It describes the program goals and major elements and the manner in which the E0P training is evaluated and revised.
Following the NRC generic approval of the BHROG Emergency Procedure Guidelines (Rev. 4), BECo plans to prepare a Procedure Generation Package and submit it for NRC review in accordance with discussions held during the August 4, 1987 meeting between J. E. Howard (BECo) and R. H. Hessman (NRC).
L-R. G. Bird JWP/jcp/1398 V
0 O
Q g201oo73g733po_
g p
ADDCK 05000293 PDR i
h.
BOSTON EDIS0N COMPANY U. S. Nuclear Regulatory Commission Page 2 Attachments:
- 1. Pilgrim Nuclear Power Station Plant-Specific Technical Guidelines For Emergency Operating Procedures
- 2. Appendices To the Pilgrim Nuclear Power Station Plant-Specific Technical Guidelines
- 3. Pilgrim Nuclear Power Station Collection of Plant Operating Procedures Utilized to Develop, Process and Issue Plant-Specific Emergency Operating Procedures
- 4. Pilgrim Nuclear Power Station Emergency Operating Procedures (E0Ps)
Training Program Summary Description cc:
Mr. R. H. Hessman, Project Manager Division of Reactor Projects I/II Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20814 U. S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406 Senior NRC Resident Inspector Pilgrim Nuclear Power Station b