3F0702-02, June 2002 Monthly Operating Report for Crystal River Unit 3
| ML021980452 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 07/09/2002 |
| From: | Franke J Florida Power Corp |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0702-02 | |
| Download: ML021980452 (3) | |
Text
Florida Power A Progress Energy Company Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 July 9, 2002 3F0702-02 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Florida Power Corporation hereby submits the Crystal River Unit 3 (CR-3) June 2002 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, J. A. Franke P lant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager cr,.s"a H cL P3442 Piý.
APPENDIX A OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD (Month/Year):
50-302 FLCRP-3 July 2, 2002 J.E. Lane (352) 795-6486 x3698 June 2002 MONTH DESIGN ELECTRICAL RATING (MWe-Net)
MAXIMUM DEPENDABLE CAPACITY (Mwe-Net)
NUMBER OF HOURS REACTOR WAS CRITICAL NUMBER OF HOURS THE GENERATOR WAS ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 1 2
3 4
5 6
YEAR TO DATE 825 834 CUMULATIVE 720.0 720.0 0.0 605,412 4,324.0 4,316.4 0.0 3,642,561 153,731 151,439 0
117,611,824
APPENDIX B UNIT SHUTDOWNS DOCKET NO.
50-302 UNIT NAME FLCRP-3 DATE July2, 2002 COMPLETED BY J.E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
June 2002 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments None
SUMMARY
Crystal River Unit 3 operated the entire month without an outage or significant downpower.
(1) Reason:
A-EQUIPMENT FAILURE (Explain)
B-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION
&-OPERATOR TRAINING / LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explain)
(2) Method 1-MANUAL 2-MANUAL TRIP / SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATION 5-OTHER (Explain)