LER-1981-002, Forwards LER 81-002/02L-0.Detailed Event Analysis Submitted |
| Event date: |
|
|---|
| Report date: |
|
|---|
| 4091981002R00 - NRC Website |
|
text
_
3 2-gl LO gM
/~WW D DAMYLAND
&W k
COOPERAT/VE 90 eor Bir. 2 sis East av sou a
E wisconsis s4so, 1608, 786 4 000 February 25, 1981 In reply, please refer to LAC-7382 DOCKET NO. 50-409 Mr. James G. Keppler Regional Director
'i (i q,,
U. S. Nuclear Regulatory Commission 7'
bk j Q.
Directorate of Regulatory Operations
//f s
Region III N
p D
799 Roosevelt Road g
Q Q
Glen Ellyn, IL 60137 S
Og g
t;g
SUBJECT:
DAIRYLAND POWER COOPERATIVE h,,
Y A($
LA CROSSE BOILING WATER REACTOR (LACBWR) o',
- - Id PROVISIONAL OPERATING LICENSE NO. DPR-45
//.
REPORTABLE OCCURRENCE NO. 81-02 M[*.0 M
References:
(1)
LACBWR Technical e ifications, Section 3. 9.2.b. (2)
(2)
LACBWR Technical Specifications, Section 4.2.3.1.1 (3)
LACBWR Technical Specifications, Section 4.2.3.2.1 Dear Mr. Kepp.*
In accordance with Reference 1, this report is notification of operation in a degraded mode permitted by a limiting condition l
for operation.
Reference (2) requires that the physically independent circuit between the off-site transmission network and the onsite power distribution system and the electrical feeds from 2400V bus lA l
and 1B be operable during Operating Condition 1.
Reference (3) requires that specified AC electrical buses be operable and energized from sources of power othr:r than a diesel generator, but aligned to an operable diesel generator.
On February 1, 1981, at 1134, at 28% Reactor Rated Thermal Power, the physically independent circuit between the off-site transmis-sion network and the onsite power distribution system was interrupted when the switchyard operator opened manual Disconnect Switch 25NA.t, which disconnected the reserve auxiliary transformer from the 69KV 0y transmission line.
(See attached sketch).
The emergency diesel i(0 l
generators started automatically and supplied the essential buses gjI l
The reactor shut down automatically.
All systems functioned prop-g erly.
Off-site power was restored within 14 minutes.
l W 2M 810 G 16 0 p
Mr. James G. Keppler, Regional Director LAC-7382 U. S. Nuclear Regulatory Commission February 25, 1981 The circumstances surrounding the incident are as follows:
At 1125 on February 1, the turbine operator closed switch 25NB1 to close oil circuit breaker (OCB) 25NB1 to synchronize the generator output with the DPC electrical grid.
In closing the switch, he used too much force, breaking the switch internal spring pin.
The switch was then reopened.
In reaching across the switch, a super-visor's shirt sleeve brushed against the switch handle.
Due to the broken spring pin, the slight pressure was enough to cause the 4
switch contacts to close, thus initiating a momentary closing action on OCB 25NB1, with the generator electrically out of phase with the DPC grid.
Therefore, it was decided to open the airbreak disconnect switch for 25NB1 as a precaution, to prevent inadvertent or self-closure of OCB 25NB1 and to allow repair.
The switchyard operator was given a switching order to open 25NA1, the air break disconneet to the main transformer.
Though the dis-
.. 3d correctly and the operator had performed connect switch is labe a visual check of the.abel and order, he incorrectly 'pened 25NA4, o
the air break disconnect to the reserve auxiliary transformer, which was supplying station power.
All subsequent automatic actions functioned and the Control Room Operators carried out the loss of off-site power procedure properly.
Disconnect awitch 25NA4 was re-closed after the oil circuit breaker 25NB4 was opened and the correct disconnect switch, 25NA1, was opened.
The actions of the switchyard operator were reviewed by plant ranage-l ment.
The operator was interviewed to determine the reason for the mis-switching.
The problems entountered with the Control Roor switch for OCB 25NB3 caused concern for that event and may have interfered with his concentration.
Whenever possible, outside switching orders will be executed in the presence of a second person to provide a double check.
Also, additignal practical training on the switchyard will be provided for all operators.
A Licensee Event Report (Reference:
Regulatory Guide 1.16, Revision 4) is enclosed.
If you have any questions, please centact us.
Very truly yours, DAIRYLAND POWE COOPERATIVE i
m w
Frank Linder, General Manager FL:LSG:af Enclosures !
l a
Mr. James G. Keppler, Regional Director LAC-7382 l
U. S. Nuclear Regulatory Comission February 25, 1981 cc:
Director, Office of Inspection and Enforcement (30)
U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Director, Office of Management Information and (3)
Program Control U. S. Nuclear Regulatory Commission Washington, D. C.
20555 NRC Resident Inspectors l
i l
I l
I
,--w-,,_.--
___,,... +,
___, ~..,
,,.n,
,,._,-,.-,_,_,,n,
_._,q,
(*..
Wl 8 6.50 = 3 36.400 1
~.
.. amm.ame muun summen ammme amme emma mumm name mamma meme suma =Ese ammme mamm..marisi. amm een a.
LIN E - Ql I-2750 30 o -*C
,-. 4 9 13. f-
$ Nr a
P3
).
j/~0. 3 C 1
i / f'
- I.
7
[
3 MN s
o-D e
/'> n OWNED BY. N. i.I sum mm. -.
0 375-4/O l
LIN E - N 53 el 4
- ]N
>.N CI !
..y
\\ PKC 4 -
o l*- *'KYI [
! 2 h ) 4,
.d2 So 9 I1:xai
[.!Nd 33,5 37 s
N i
y~
as
\\
e 2 A Al 24t.3{
- 2, 4 4 E
e qc N~
a I<b\\
e _ _ _a -
.,2 7.. *
' Je A6 hs267 F r 1. -
If
..2496 L. :'ki ?
12 "
l.:
,,2.I
,, \\;
' 2 e'. S e.06 2<C7 h
.-, et I
s,r.-
e5..
u
/.;
s/n>7
.e 4 k'q, 500.1 M
i.0 X,
' d) A.-
a W.
.O s
- 5. (f' r G 3 4 5 " ~*'<
M
,s.
' 69 345 ^T^. '
,p...'
C 4 16 i CGc.y WJ '
N 3'".
4 s I?.
N 4iG-44 7 3 g 2..E l'
2~ B6 92Gi:7
- 12',03 a',3 L 3,.i i s 6 2, <a 1.:-
O
/
y f-L_
d b -- 0 0
0 0
< 2 *. A f. *. I e'
.e?*
5 / ; $./
i-2GEs _'
't 0 3']
2G(s4[
-[ ' -
_1--
,, m..
i( )
2
.- s As
.-s t - uu.
E
(;
rs) t ' ve -
, n.w.
r,o e-I 5,
t-u.
4uw 4.w c a e, m.wy, 4
g m.w.
.2.v.
p 1 m,... :.
c.
.w.
.a
/ 2 rls
'/ ? t< c o
/
r,
/;.
GENOA No. l
- - E.
._ a STATION
'. 2.
.s 2
.~
u
.asema.-g -=.mm rd I :8 ;0 s
f
- - A 5
'> 2 4 'y/+,t.94 e
i.
]
y a
2's f J t. 4 4
U g I
a:
0
.. =(
I g
g L /.!. VI, > e rJ i 5,et; i
Apomo mai
- s n t.3 e.. i.
't i c/. i n. i u.
m L. M v D V V n A
_L i.
c>..n>
~f 3 i
Sil.TIOf J No.Pb
.,'?' * " l,." NO3 i ' i t,.
.n f3
. f,,oc(... ; ',' f, * ],
.~..
9..
t '.' '.
no, y u s s u.'.
TO 13 C NCA HC. 3 GE NOA No.2
)
- nL FIG.ls.1 n L.
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000409/LER-1981-001, Forwards LER 81-001/02L-0 | Forwards LER 81-001/02L-0 | | | 05000409/LER-1981-001-02, /02L-0:on 810201,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Disconnected.Caused by Disconnect Switch Opened Due to Operator Error.Two Operators to Operate Switching Order | /02L-0:on 810201,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Disconnected.Caused by Disconnect Switch Opened Due to Operator Error.Two Operators to Operate Switching Order | | | 05000409/LER-1981-001-03, /03L-0:on 810116,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Disconnected.Caused by Maint on Main Transformer Airbreak Switch 25NA1 Due to Ice in Swivel Joint.Ice Melted | /03L-0:on 810116,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Disconnected.Caused by Maint on Main Transformer Airbreak Switch 25NA1 Due to Ice in Swivel Joint.Ice Melted | | | 05000409/LER-1981-002, Forwards LER 81-002/02L-0.Detailed Event Analysis Submitted | Forwards LER 81-002/02L-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-002-02, /02L-0:on 810201,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Was Disconnected.Caused by Operator Opening Incorrect Disconnect Switch.Switch Reclosed.Operators Retrained | /02L-0:on 810201,independent Circuit Between Offsite Transmission Network & Onsite Power Distribution Sys Was Disconnected.Caused by Operator Opening Incorrect Disconnect Switch.Switch Reclosed.Operators Retrained | | | 05000409/LER-1981-003-03, /03L-0:on 810202,gross Alpha Activity of Primary Coolant Sample Exceeded Tech Spec.Caused by Degraded Fuel Cladding During Previous Fuel Cycles.Primary Purification Sys Operation Reduced Concentration to Allowable Level | /03L-0:on 810202,gross Alpha Activity of Primary Coolant Sample Exceeded Tech Spec.Caused by Degraded Fuel Cladding During Previous Fuel Cycles.Primary Purification Sys Operation Reduced Concentration to Allowable Level | | | 05000409/LER-1981-003, Forwards LER 81-003/03L-0.Detailed Event Analysis Encl | Forwards LER 81-003/03L-0.Detailed Event Analysis Encl | | | 05000409/LER-1981-004, Forwards LER 81-004/03L-0.Detailed Event Analysis Also Submitted | Forwards LER 81-004/03L-0.Detailed Event Analysis Also Submitted | | | 05000409/LER-1981-004-03, /03L-0:on 810309,during Condition 3,480-volt Diesel Bldg Essential Switchgear Bus 1B Was Energized from 1B Emergency Diesel Generator for Approx 25 Minutes W/Control Power Key in on Position | /03L-0:on 810309,during Condition 3,480-volt Diesel Bldg Essential Switchgear Bus 1B Was Energized from 1B Emergency Diesel Generator for Approx 25 Minutes W/Control Power Key in on Position | | | 05000409/LER-1981-006-01, /01T-0:on 810518,during Installation of Attachment on Containment Pressure Sensing Line,High Containment Bldg Pressure Starting Signal to HPCS Pump 1B,auxiliary Cooling Sys Pump & AC Valve Was Isolated.Procedures Not Followe | /01T-0:on 810518,during Installation of Attachment on Containment Pressure Sensing Line,High Containment Bldg Pressure Starting Signal to HPCS Pump 1B,auxiliary Cooling Sys Pump & AC Valve Was Isolated.Procedures Not Followed | | | 05000409/LER-1981-006, Forwards LER 81-006/01T-0.Detailed Event Analysis Encl | Forwards LER 81-006/01T-0.Detailed Event Analysis Encl | | | 05000409/LER-1981-007-01, /01T-0:on 810601,during Initial Integrated Sys Test W/Plant Shut Down,Emergency Svc Water Supply Sys Did Not Produce 900 Gpm at 90 Psig,As required.Three-way Distributor Fabricated.Sys Retested Satisfactorily | /01T-0:on 810601,during Initial Integrated Sys Test W/Plant Shut Down,Emergency Svc Water Supply Sys Did Not Produce 900 Gpm at 90 Psig,As required.Three-way Distributor Fabricated.Sys Retested Satisfactorily | | | 05000409/LER-1981-007, Forwards LER 81-007/01T-0 | Forwards LER 81-007/01T-0 | | | 05000409/LER-1981-008-01, /01T-0:on 810729,main Steam Bypass Valve Did Not Open During Momentary Pressure Spikes Approx 20 Psi Above Nominal Reactor Pressure.Caused by Decrease in Pressure Prior to Valve Opening Due to Short Duration & Spikes | /01T-0:on 810729,main Steam Bypass Valve Did Not Open During Momentary Pressure Spikes Approx 20 Psi Above Nominal Reactor Pressure.Caused by Decrease in Pressure Prior to Valve Opening Due to Short Duration & Spikes | | | 05000409/LER-1981-008, Forwards LER 81-008/01T-0.Detailed Event Analysis Submitted | Forwards LER 81-008/01T-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-009-03, /03L-0:on 810917,upscale Trip Setpoint on Nuclear Instrument Channel 7 Found in Excess of Tech Spec Limit. Cause Not Determined.Setpoint Reset | /03L-0:on 810917,upscale Trip Setpoint on Nuclear Instrument Channel 7 Found in Excess of Tech Spec Limit. Cause Not Determined.Setpoint Reset | | | 05000409/LER-1981-009, Forwards LER 81-009/03L-0.Detailed Event Analysis Submitted | Forwards LER 81-009/03L-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-010, Forwards LER 81-010/01T-0.Detailed Event Analysis Submitted | Forwards LER 81-010/01T-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-010-01, /01T-0:on 810923,during Normal Operation Mechanical Interlock Preventing Simultaneous Opening of Both Doors of Containment Bldg Personnel Airlock Failed.Caused by Worn or Misadjusted Actuating Mechanism.Drawings Encl | /01T-0:on 810923,during Normal Operation Mechanical Interlock Preventing Simultaneous Opening of Both Doors of Containment Bldg Personnel Airlock Failed.Caused by Worn or Misadjusted Actuating Mechanism.Drawings Encl | | | 05000409/LER-1981-011-03, /03L-0:on 811031,observed That Radiation Hose on High Pressure Svc Water Diesel Engine 1B Was Slightly Cracked.Cause Not Stated.Hose Replaced & Diesel 1B Tested Satisfactorily | /03L-0:on 811031,observed That Radiation Hose on High Pressure Svc Water Diesel Engine 1B Was Slightly Cracked.Cause Not Stated.Hose Replaced & Diesel 1B Tested Satisfactorily | | | 05000409/LER-1981-011, Forwards LER 81-011/03L-0.Detailed Event Analysis Submitted | Forwards LER 81-011/03L-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-012-03, /03L-0:on 811101,gasoline Levels in Three Emergency Svc Water Supply Sys Gasoline Engine Driven Pumps & Spare Pump Found to Be Less than 5 Gallons During Monthly Insp.Cause Unknown.Gasoline Added to Fill Tanks | /03L-0:on 811101,gasoline Levels in Three Emergency Svc Water Supply Sys Gasoline Engine Driven Pumps & Spare Pump Found to Be Less than 5 Gallons During Monthly Insp.Cause Unknown.Gasoline Added to Fill Tanks | | | 05000409/LER-1981-012, Forwards LER 81-012/03L-0.Detailed Event Analysis Submitted | Forwards LER 81-012/03L-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-013-03, Following scram,1B 2,400-volt Bus Reserve Feed Breaker Did Not Close Automatically.Cause Undetermined.Reserve Feed Breaker Control Switch Flagged to Trip Position | Following scram,1B 2,400-volt Bus Reserve Feed Breaker Did Not Close Automatically.Cause Undetermined.Reserve Feed Breaker Control Switch Flagged to Trip Position | | | 05000409/LER-1981-013, Forwards LER 81-013/03L-0.Detailed Event Analysis Submitted | Forwards LER 81-013/03L-0.Detailed Event Analysis Submitted | | | 05000409/LER-1981-014-03, /03L-0:on 811223,following Scram,Offsite Transmission Network Did Not Automatically Supply Onsite Power Distribution Sys.Cause Undetermined.Transformer Breaker Closed | /03L-0:on 811223,following Scram,Offsite Transmission Network Did Not Automatically Supply Onsite Power Distribution Sys.Cause Undetermined.Transformer Breaker Closed | | | 05000409/LER-1981-014, Forwards LER 81-014/03L-0 & Updated LER 81-013/03X-1. Detailed Event Analysis Encl | Forwards LER 81-014/03L-0 & Updated LER 81-013/03X-1. Detailed Event Analysis Encl | | | 05000409/LER-1981-015, Forwards LER 81-015/01T-0.Detailed Event Analysis Encl | Forwards LER 81-015/01T-0.Detailed Event Analysis Encl | | | 05000409/LER-1981-015-01, /01T-0:on 811224,following Reactor Scram,Temp of 1B Forced Circulation Loop Piping Decreased Below Tech Specs Limit.Caused by Inoperation of Pump Due to Seal Problems & Lack of Monitoring.Personnel Reinstructed | /01T-0:on 811224,following Reactor Scram,Temp of 1B Forced Circulation Loop Piping Decreased Below Tech Specs Limit.Caused by Inoperation of Pump Due to Seal Problems & Lack of Monitoring.Personnel Reinstructed | |
|