05000333/LER-2003-002, Safety Relief Valve Setpoints Outside of Allowable Tolerances
| ML032960221 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 10/16/2003 |
| From: | Ted Sullivan Entergy Nuclear Northeast, Entergy Nuclear Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| CR-JAF-2003-04321, JAFP-03-0142 LER 03-002-00 | |
| Download: ML032960221 (6) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
| 3332003002R00 - NRC Website | |
text
.r-1%Enter~gy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. Fitzpatrick NPP RO. Box 110 Lycoming, NY 13093 Tel 315 349 6024 Fax 315 349 6480 T.A. Sullivan Site Vice President - JAF October 16, 2003 JAFP-03-0142 United States Nuclear Regulatory Commission Attn: Document Control Desk Mail Station P1-1 37 Washington, D.C. 20555
Subject:
Docket No. 50-333 LICENSEE EVENT REPORT: LER-03-002 (CR-JAF-2003-04321)
Safety Relief Valve Setpoints Outside of Allowable Tolerances
Dear Sir:
This report is submitted in accordance with 10 CFR 50.73(a)(2)(i)(B), 'Any operation or condition which was prohibited by the plant's Technical Specifications...'
There are no commitments contained in this report.
Questions concerning this report may be addressed to Mr. Darren Deretz at (315) 349-6851.
Very truly yours, T. A. Sullivan TAS:DD:dd Enclosure cc:
USNRC, Region 1 USNRC, Project Directorate USNRC Resident Inspector INPO Records Center C,,, 9
": 7,
.i
Abstract
Review of the as-found setpoints for I 1 Safety Relief Valve (SRV) [SB] pilot assemblies, removed at the end of Cycle 15, determined that 3 SRVs were outside the allowable as-found tolerance of 1145 psig +/- 34.3 psig (+/- 3%) required by Technical Specifications (TS) Surveillance Requirement (SR) 3.4.3.1. This report documents the failure to meet this SR for 3 of the 11 SRVs.
The effect of 3 SRVs being out of tolerance during Cycle 15 is analyzed in this report. The results of this analysis show that Reactor Pressure Vessel (RPV) overpressure protection and nuclear plant safety were not adversely affected. The cause of the two high out of tolerance SRV setpoints was determined to be corrosion bonding between the SRV pilot disc and seat, a recognized industry generic problem.
The cause of the low out of tolerance SRV pilot test failure was determined to be sticking of the air operator following the pilot diagnostic test. This SRV pilot tested satisfactorily on 3 subsequent test lifts.
NRC FORM 366 (7-2001)U.S. NUCLEAR REGULATORY COMMISSION 161998)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET (2)
LER NUMBER (6)
PAGE (3)
YEAR l SEOUENTIAL I REVISION 2
OF 5
NUMBER NUMBER James A. FitzPatrick Nuclear Power Plant 05000333 03 002 00 TEXM fif more space is required, use additional copies of NRC Form 366A) (17)
EIIS Codes in[ I Fvent Description On August 19, 2003, while the plant was operating at 100 percent power, FitzPatrick was notified that three Safety Relief Valve (SRV) [SB] pilot assemblies removed at the end of Cycle 15 had as-found setpoints outside the allowable tolerance of 1145 psig +/- 34.3 psig (+/- 3%).
This allowable tolerance (1110.7 to 1179.3 psig) is required per Technical Specifications (TS) Surveillance Requirement (SR) 3.4.3.1. Two SRVs exceeded the high limit of 1179.3 psig and one SRV exceeded the low limit of 1110.7 psig.
The removed SRV pilots were tested at Wyle Laboratories during the period July 29 through August 5, 2003. The results from these tests were reported to FitzPatrick by Wyle Laboratories on August 19, 2003.
Test Results:
Pilot Plant Pass/Fail Serial Valve As-Found (pass unless Number Number Setpint atherise noted) 1053 02RV-71B 1140 1236 02RV-71H 1197 Fail 1191 02RV-71E 1142 1087 02RV-71J 1168 1111 02RV-71D 1134 1239 02RV-71K 1158 1045 02RV-71A 1222 Fail 1013 02RV-71C 1104 Fail 1235 02RV-71G 1146 1051 02RV-71F 1143 1110 02RV-71L 1139 TS LCO 3.4.3 requires nine operable SRVs when in Modes 1, 2 or 3. Specifically, the TS states:
The safetyfunction of 9 SIRVs shall be OPERABLE.
Since three pilot valves exceeded the allowable setpoint range, this report is being made under 10 CFR 50.73(a)(2)(i)(B),
"Any operation or condition which was prohibited by the plant's Technical Specifications..."
Cutim of Event-The cause of the two high out of tolerance pilot setpoints was determined to be corrosion bonding between the SRV pilot disc and seat [Cause Code B]. With a bond forming between the pilot disc and seat, more pressure is needed to raise the pilot disc off the seat. Since the normal balance of pilot assembly spring force and steam pressure force necessary to lift the pilot disc corresponds to the nominal setpoint of the SRV, the pilot disc to seat bond results in a higher pilot setpoint.
- - XU.S. NUCLEAR REGULATORY COMMISSION (6-1998)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL REVISION
- - 3 OF 5
NUMBER NUMBER James A. FitzPatrick Nuclear Power Plant 05000333 03 002 00 TEXr (If more space is required, use additional copies of NRC Form 366A) (17)
==Cause of Event==An oxygen rich environment in the pilot assembly, due to the radiolytic breakdown of water to hydrogen and oxygen, causes the corrosion bonding. Oxygen accumulates in the area of the pilot disc because the pilot assembly is a high point on the main steam [SB] line.
The cause of the SRV testing low out of tolerance was determined to be sticking of the air operator stem in conjunction with the pilot diagnostic test that preceded the SRV test failure. The diagnostic test is performed to determine the presence of pilot disc-seat corrosion bonding. During subsequent troubleshooting, abnormal air actuator stem movement was observed, which indicated increased friction or "stickiness". This initial pre-test cycling of the operator pilot set spring, combined with the observed friction, prevented the pilot set spring from fully extending, creating a "preloaded" condition.
This preloaded condition reduced the overall steam pressure required for lifting the pilot disc, thereby causing the SRV to lift at a lower pressure. [Cause Code B]
On 3 subsequent tests of this SRV pilot, it lifted at 1142 psig, 1 138 psig and 1142 psig, respectively. No pilot diagnostic test was performed immediately prior to these subsequent tests, which precluded the potential for a pilot set spring preloaded condition. Consequently, this performance is likely most representative of the setpoint during the operating cycle, because the potential for spring preloading would be precluded by the environmental vibration conditions.
Evnt Analysis The SRVs provide overpressure protection for the Reactor Coolant Pressure Boundary (RCPB) as required by the ASME Boiler and Pressure Vessel Code. SRV pilots actuating at pressures higher than the required setpoint may be significant if adequate overpressure protection is not available.
Two analyses are used in determining the adequacy of overpressure protection; the RCPB Overpressure Analysis and the Anticipated Transient Without Scram (ATWS) analysis. The RCPB Overpressure Analysis is performed each fuel cycle based on the worst case anticipated transient with nine SRVs opening at an analyzed Upper Limit pressure of 1195 psig, and two SRVs out of service. Additionally, the current ATWS analysis was performed using the worst case ATWS with two SRVs out of service and the other nine opening at setpoints derived from Cycle 13 as-found test results. Review of the Cycle 15 test results has determined that the associated worst case setpoints are bounded by both of the above analyses.
The out-of-tolerance condition reported by this LER did not compromise overpressure protection for either analyzed event.
Thus, the current analysis demonstrates satisfactory results with two SRVs failing above the setpoint range and one SRV failing below the setpoint range.
The safety significance of this event is therefore minimal because the system safety function would have been achieved in accordance with the assumptions made in the design basis safety analysis.U.S. NUCLEAR REGULATORY COMMISSION (6-1 998)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL REVISION 4
OF 5
NUMBER NUMBER James A. FitzPatrick Nuclear Power Plant 05000333 03 002 00 TEXT (If more space is required, use additional copies of NRC Form 366AJ (17)
Extent of Condition All of the SRVs are susceptible to setpoint drift due to pilot disc to seat bonding. This is an industry issue that has been the subject of both NRC and BWROG generic assessment. In general, FitzPatrick SRV pilot performance has improved over the past few cycles, as indicated by a reduced number of out of tolerance high pilot test failures from each group of pilot assembly tests. However, failures due to the generic industry issue continue to occur.
The BWROG recommended modification to provide pressure switch actuation of the SRVs was operational during Cycle
- 15. This modification provides an electric actuation of SRV pilot valves based upon a pressure switch setpoint. This provides a diverse, redundant method of SRV actuation, which overcomes the pilot disc-seat bonding effect. As such, this modification will mitigate and limit the extent of condition to one part of a diverse SRV actuation methodology.
The SRV pilot that tested low out of tolerance due to sticking of the air operator stem is considered a unique case, as there is no industry evidence of a previous occurrence of an air operator stem sticking.
Corrective Actipnm; Corrective Actions Completed Prior to this Report:
- 1.
All SRV Pilots were removed from the plant during Refuel Outage 15 (October 2002) and replaced with newly refurbished and test certified pilots for Cycle 16.
- 2.
The BWROG recommended modification to provide pressure switch actuation of the SRVs was operational during Cycle 15 when these valves were in service.
- 3.
All SRV pilot assemblies are tested and replaced each operating cycle.
Corrective Actions for this Event:
- 1. Ensure Pilot # 1013 air actuator is refurbished, and the affected air operator stem and body are replaced, as part of the pilot rebuild prior to certification testing. This action will be completed prior to Refuel Outage 16 (October 2004). (JAF CR-2003-04321-CA-05)
(Scheduled Completion Date 07/15/2004)
- 2. Discontinue performance of the pilot diagnostic test as part of as-found setpoint testing. This test no longer provides useful information and has the potential to bias pilot lift test results. This action will be completed prior to the next SRV pilot assembly tests. (JAF CR-2003-04321-CA-06)
(Scheduled Completion Date 06/15/2004)
Safety Syntem Ftinctinniil Failitre Reviews This event did not result in a safety system functional failure as defined by NEI 99-02, Revision 2.U.S. NUCLEAR REGULATORY COMMISSION (6-1998)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET (2)
LER NUMBER (6) l PAGE (3)
YEAR SEQUENTIAL REVISION 5
OF 5
l NUMBER NUMBER James A. FitzPatrick Nuclear Power Plant 05000333 03 002 00 TEXT (If more space is required, use additional copies of NRC Form 366A) (17)
Similar Fvents
- 1. JAF LER-01-005 "Safety Relief Valve Setpoint Drift," August 17, 2001.
- 2. JAF LER-99-003 "Safety Relief Valve Setpoint Drift," March 16, 1999.
- 3. JAF LER-98-002 "Safety Relief Valve Setpoint Drift," April 9, 1998.
Failed Component Identification-Manufacturer:
Model Number:
NPRDS Manufacturer Code:
NPRDS Component Code:
FitzPatrick Component ID:
Target Rock Corporation 7567F-10 T020 Valve 02RV-07 IA, C & H
- 1. JAF Condition Report CR-JAF-2003-04321, associated cause analyses and Wyle Laboratories Notice of Anomalies Number I for Entergy Purchase Order 4500524037.
- 2. GE-NE-A42-00137-2-01 rev 1, 'ATWS Overpressure Analysis for FitzPatrick,' dated July, 2003.