| | | Reporting criterion |
|---|
| 05000313/LER-1989-001, :on 881217,RCS Hot Leg Resistance Temp Detector Calibr Using Wrong Calibr Data Since Installation in May 1982.Caused by Procedural Inadequacy.Calibr Procedure for TE-1041/1042 Revised to Reflect Correct Calibr |
- on 881217,RCS Hot Leg Resistance Temp Detector Calibr Using Wrong Calibr Data Since Installation in May 1982.Caused by Procedural Inadequacy.Calibr Procedure for TE-1041/1042 Revised to Reflect Correct Calibr
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-001-01, :on 890503,reactor Protective Sys Instrumentation Declared Inoperable Due to Channel Failing Low Intermittently.Caused by Misinterpretation of Procedure. Procedural Guidance Will Be Issued |
- on 890503,reactor Protective Sys Instrumentation Declared Inoperable Due to Channel Failing Low Intermittently.Caused by Misinterpretation of Procedure. Procedural Guidance Will Be Issued
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-002-01, :on 890120,reactor Trip Occurred Due to Failure in Main Generator Exciter & Two Reactor Coolant Pumps Tripped on Undervoltage When Bus H1 Failed to Fast Transfer to Offsite Power.Caused by Arcing in Exciter |
- on 890120,reactor Trip Occurred Due to Failure in Main Generator Exciter & Two Reactor Coolant Pumps Tripped on Undervoltage When Bus H1 Failed to Fast Transfer to Offsite Power.Caused by Arcing in Exciter
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-002, :on 890109,discovered That Tech Spec Required 14-day Periodic Surveillance Test for Svc Water Flow Rate to Containment Cooling Units Not Performed.Caused by Personnel Error.Personnel Counseled |
- on 890109,discovered That Tech Spec Required 14-day Periodic Surveillance Test for Svc Water Flow Rate to Containment Cooling Units Not Performed.Caused by Personnel Error.Personnel Counseled
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-003-01, :on 890216,personnel Determined That Valve Associated W/Train a Hydrogen Analyzer Exceeded Environ Qualification Parts Replacement Interval Since 1983.Caused by Personnel Error.Components Replaced |
- on 890216,personnel Determined That Valve Associated W/Train a Hydrogen Analyzer Exceeded Environ Qualification Parts Replacement Interval Since 1983.Caused by Personnel Error.Components Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) |
| 05000313/LER-1989-003, :on 880907,determined That Floor Penetration Located in Fire Barrier at Elevation 335 of Auxiliary Bldg Sealed Using Unqualified styrofoam-type Matl.Caused by Personnel Error.Penetration Seals Repaired |
- on 880907,determined That Floor Penetration Located in Fire Barrier at Elevation 335 of Auxiliary Bldg Sealed Using Unqualified styrofoam-type Matl.Caused by Personnel Error.Penetration Seals Repaired
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-004, :on 890301,discovered Plant Startup Procedure Inadequate Resulting in Inability to Automatically Transfer HPSI Pump Suction Prohibited by Tech Specs.Caused by Inadequate Procedure.Procedures Revised |
- on 890301,discovered Plant Startup Procedure Inadequate Resulting in Inability to Automatically Transfer HPSI Pump Suction Prohibited by Tech Specs.Caused by Inadequate Procedure.Procedures Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(p)(2)(v) |
| 05000313/LER-1989-004-01, :on 890120,high Pressure Injection Line Check Valve Failed to Reseat.Caused by Inadequate Design Change Process.Program of Visual Insp & NDEs Completed to Identify Any Sys Degradations Due to Thermal Stresses |
- on 890120,high Pressure Injection Line Check Valve Failed to Reseat.Caused by Inadequate Design Change Process.Program of Visual Insp & NDEs Completed to Identify Any Sys Degradations Due to Thermal Stresses
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-005, :on 890201,calculated Reactor Shutdown Margins Less Conservative than Assumed in Design Basis.Caused by Personnel Error Resulting in Inadequate Procedure.Reactivity Balance Procedure Revised |
- on 890201,calculated Reactor Shutdown Margins Less Conservative than Assumed in Design Basis.Caused by Personnel Error Resulting in Inadequate Procedure.Reactivity Balance Procedure Revised
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-005-01, :on 890518,25 & 31,void Found in Silicone Foam Matl.Caused by Inadequate Procedural Guidance to Ensure Voids Not Present in Sealing Matl After Installation.Repairs Initiated to Restore Seals to Working Order |
- on 890518,25 & 31,void Found in Silicone Foam Matl.Caused by Inadequate Procedural Guidance to Ensure Voids Not Present in Sealing Matl After Installation.Repairs Initiated to Restore Seals to Working Order
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-005, :on 890518 & 25,damping Board Removed from Penetration Containing Cable Tray.On 890531,voids Noted in Penetration Seals.Caused by Erroneous Vendor Procedures. Penetrations Restored & Procedures Revised |
- on 890518 & 25,damping Board Removed from Penetration Containing Cable Tray.On 890531,voids Noted in Penetration Seals.Caused by Erroneous Vendor Procedures. Penetrations Restored & Procedures Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(c)(2)(1) |
| 05000368/LER-1989-006, :on 890418,high Pressure Turbine Extraction Ruptured Resulting in Reactor Trip on High RCS Pressure. Caused by Pipe Wall Thinning Due to erosion-corrosion. Defective Wiring Replaced & Sys Satisfactory |
- on 890418,high Pressure Turbine Extraction Ruptured Resulting in Reactor Trip on High RCS Pressure. Caused by Pipe Wall Thinning Due to erosion-corrosion. Defective Wiring Replaced & Sys Satisfactory
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-006-01, :on 890209,analytical & Procedural Inadequacies Noted Re Use of Hpis in Piggyback Flowpath Alignment.Caused by Deficient ECCS Analysis.Affected Portions of Piggyback Piping Reanalyzed & Mods Implemented |
- on 890209,analytical & Procedural Inadequacies Noted Re Use of Hpis in Piggyback Flowpath Alignment.Caused by Deficient ECCS Analysis.Affected Portions of Piggyback Piping Reanalyzed & Mods Implemented
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-007, :on 890318,determined That Postulated Break in HPI Line Upstream of Hpi/Rcs Cold Leg Connection & Downstream of First Rcs/Hpi Boundary Check Valve Could Constitute Loca.Caused by Inadequate Design |
- on 890318,determined That Postulated Break in HPI Line Upstream of Hpi/Rcs Cold Leg Connection & Downstream of First Rcs/Hpi Boundary Check Valve Could Constitute Loca.Caused by Inadequate Design
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
| 05000313/LER-1989-007-01, :on 890318,determined That Postulated Break in HPI Line Upstream of Hpi/Rcs Cold Leg Connection Could Constitute LOCA Not Enveloped by Plant Design Basis.Caused by Inadequate Design Change Process |
- on 890318,determined That Postulated Break in HPI Line Upstream of Hpi/Rcs Cold Leg Connection Could Constitute LOCA Not Enveloped by Plant Design Basis.Caused by Inadequate Design Change Process
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-007, :on 890424,snubber on Valve (2CV-4653) on Pressurizer Spray Line Found Disconnected While Performing Inservice Insp of Mechanical Snubbers.Caused by Inadequate Work Controls.Snubber on 2CV-4653 Replaced |
- on 890424,snubber on Valve (2CV-4653) on Pressurizer Spray Line Found Disconnected While Performing Inservice Insp of Mechanical Snubbers.Caused by Inadequate Work Controls.Snubber on 2CV-4653 Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-008, :on 890122,determined That When Bypass Valve GCH-29 Normally Open,Ability of Radiation Monitors to Perform Required Functions Not Ensured.Caused by Error in Design Change in Bypass Line & Valve |
- on 890122,determined That When Bypass Valve GCH-29 Normally Open,Ability of Radiation Monitors to Perform Required Functions Not Ensured.Caused by Error in Design Change in Bypass Line & Valve
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) |
| 05000368/LER-1989-008-01, :on 890506,overspeed Trip of Steam Turbine Driven Emergency Pump Occurred.Caused by Degraded Ramp Generator.Ramp Generator Replaced & Entire Speed Circuit Calibr |
- on 890506,overspeed Trip of Steam Turbine Driven Emergency Pump Occurred.Caused by Degraded Ramp Generator.Ramp Generator Replaced & Entire Speed Circuit Calibr
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-009-01, :on 890420,determined That Emergency Diesel Generator 18-month Test Procedure Did Not Verify Fuel Pump Transfer Capabilities.Caused by Personnel Error.Procedure to Be Revised |
- on 890420,determined That Emergency Diesel Generator 18-month Test Procedure Did Not Verify Fuel Pump Transfer Capabilities.Caused by Personnel Error.Procedure to Be Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-009, :on 890224,control Room Emergency Ventilation Sys Unexpectedly Started.Cause Not Determined.Area in Vicinity of Chlorine Monitors Posted to Prohibit Use of Radios |
- on 890224,control Room Emergency Ventilation Sys Unexpectedly Started.Cause Not Determined.Area in Vicinity of Chlorine Monitors Posted to Prohibit Use of Radios
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-010, :on 890425,discovered That Valve Stroke Surveillance Test for LPSI Sys & Refueling Water Tank Had Not Been Performed.Caused by Personnel Incorrectly Indicating Tests as Already Performed |
- on 890425,discovered That Valve Stroke Surveillance Test for LPSI Sys & Refueling Water Tank Had Not Been Performed.Caused by Personnel Incorrectly Indicating Tests as Already Performed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-010-01, :on 890516 & 17,daily RCS Unidentified Leakrate Determination Indicated That Leakage Increased from Previous Day.Root Cause Not Positively Know.Visual Insp Indicated Possibility of Pinhole.Reactor Shutdown |
- on 890516 & 17,daily RCS Unidentified Leakrate Determination Indicated That Leakage Increased from Previous Day.Root Cause Not Positively Know.Visual Insp Indicated Possibility of Pinhole.Reactor Shutdown
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-011-01, :on 890608,discovered That Fire Door Separating Plant Fire Areas Being Propped Open W/O Fire Watch Stationed as Required by Tech Specs.Caused by Personnel Error.Fire Door Opened.Periodic Training Provided |
- on 890608,discovered That Fire Door Separating Plant Fire Areas Being Propped Open W/O Fire Watch Stationed as Required by Tech Specs.Caused by Personnel Error.Fire Door Opened.Periodic Training Provided
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(e)(2)(i) |
| 05000313/LER-1989-011, :Between 890326 & 0421,control Room Emergency Ventilation Sys (CREVS) Unexpectedly Automatically Actuated 13 Times.Caused by Spiking of Radiation Monitor & Inadequate Corrective Actions from Previous Events |
- Between 890326 & 0421,control Room Emergency Ventilation Sys (CREVS) Unexpectedly Automatically Actuated 13 Times.Caused by Spiking of Radiation Monitor & Inadequate Corrective Actions from Previous Events
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(i)(2)(iii) |
| 05000368/LER-1989-012-01, :on 890626,RCS Backleakage Through Safety Injection Sys Check Valve Occurred Three Times.Caused by Missing Internal Parts.Cause of Missing Rollpins Could Not Be Determined.Rollpins Replaced |
- on 890626,RCS Backleakage Through Safety Injection Sys Check Valve Occurred Three Times.Caused by Missing Internal Parts.Cause of Missing Rollpins Could Not Be Determined.Rollpins Replaced
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-012, :on 890402,discovered That High Energy Line Break Door Covered,Resulting in Condition Outside Design Basis of Main Feedwater Line Break in Piping Penetration Room.Caused by Personnel Error.Cover Removed |
- on 890402,discovered That High Energy Line Break Door Covered,Resulting in Condition Outside Design Basis of Main Feedwater Line Break in Piping Penetration Room.Caused by Personnel Error.Cover Removed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(ii)(8) |
| 05000368/LER-1989-012, :on 890626,RCS Backleakage Through Safety Injection Sys Check Valve Occurred Three Times.Caused by Missing Rollpins Which Connect Valve Disc to Valve Disc Shaft.Rollpins Replaced & Valves Reassembled |
- on 890626,RCS Backleakage Through Safety Injection Sys Check Valve Occurred Three Times.Caused by Missing Rollpins Which Connect Valve Disc to Valve Disc Shaft.Rollpins Replaced & Valves Reassembled
| 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-013, :on 881025,anchor Support for Core Flood Tank (CFT) T2A Vent Line Not Seismically Qualified & Operability of CFT Could Not Be Assured.Caused by Missing Anchor Support.Anchor Support Modified |
- on 881025,anchor Support for Core Flood Tank (CFT) T2A Vent Line Not Seismically Qualified & Operability of CFT Could Not Be Assured.Caused by Missing Anchor Support.Anchor Support Modified
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-014-01, :on 870710,discovered That Portions of Piping & Supports,Associated W/Auxiliary Spray Piping Designed to Max Temp of 120 Degrees Instead of Possible Temp of 479 Degrees. Caused by Error in Analysis.Insp Performed |
- on 870710,discovered That Portions of Piping & Supports,Associated W/Auxiliary Spray Piping Designed to Max Temp of 120 Degrees Instead of Possible Temp of 479 Degrees. Caused by Error in Analysis.Insp Performed
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) |
| 05000313/LER-1989-014, :on 890426 & 0504,control Room Emergency Ventilation Sys Automatically Actuated Nine Times as Result of Spiking of Radiation Monitor 2RE-8750-1.Detector Replaced & Bad Connection in Holder Repaired |
- on 890426 & 0504,control Room Emergency Ventilation Sys Automatically Actuated Nine Times as Result of Spiking of Radiation Monitor 2RE-8750-1.Detector Replaced & Bad Connection in Holder Repaired
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-015-01, :on 890809,personnel Identified Discrepancy Re Single Failure Design Criterion of Containment Hydrogen Analyzers.Caused by Inadequate Design Review Process. Evaluations Being Conducted to Correct Design |
- on 890809,personnel Identified Discrepancy Re Single Failure Design Criterion of Containment Hydrogen Analyzers.Caused by Inadequate Design Review Process. Evaluations Being Conducted to Correct Design
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-015, :on 861209,RCS Loop B Flow Transmitters Sensing Line Not Properly Supported.Cause Undetermined.Engineering Insp of Similar Components Conducted During 1R7 & Revealed No Other Discrepancies |
- on 861209,RCS Loop B Flow Transmitters Sensing Line Not Properly Supported.Cause Undetermined.Engineering Insp of Similar Components Conducted During 1R7 & Revealed No Other Discrepancies
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-016-01, :on 890903 & 18,continuous Fire Watch to Monitor Nonfunctional Fire Barriers Removed Due to High Airborne Activity.Caused by Failure to Establish Contingencies.Tech Spec Change Issued |
- on 890903 & 18,continuous Fire Watch to Monitor Nonfunctional Fire Barriers Removed Due to High Airborne Activity.Caused by Failure to Establish Contingencies.Tech Spec Change Issued
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-016, :on 890414,noted That Firewater Deluge Valve for Emergency Diesel Generator Not Repaired Since Crack Fitting Identified in Oct 1988.On 890201,sys Inoperable While Attempting to Replace Fitting |
- on 890414,noted That Firewater Deluge Valve for Emergency Diesel Generator Not Repaired Since Crack Fitting Identified in Oct 1988.On 890201,sys Inoperable While Attempting to Replace Fitting
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-017-01, :on 891005,discovered That Number of Operable Logarithmic Power Level Instrumentation Channels Less than Required by Tech Specs.Caused by Personnel Error.Shift Supervisor & Senior Reactor Operator Counseled |
- on 891005,discovered That Number of Operable Logarithmic Power Level Instrumentation Channels Less than Required by Tech Specs.Caused by Personnel Error.Shift Supervisor & Senior Reactor Operator Counseled
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-017, :on 890420,discovered That Dhr/Low Pressure Injection Cooler Discharge Isolation Valves Not Tested Quarterly.Caused by Inadequate Mod Review Process.Provisions Made to Test Valves Every 3 Months |
- on 890420,discovered That Dhr/Low Pressure Injection Cooler Discharge Isolation Valves Not Tested Quarterly.Caused by Inadequate Mod Review Process.Provisions Made to Test Valves Every 3 Months
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-018-01, :on 891017,inadvertent Plant Protection Sys Actuation Occurred When 120 Volt Ac Vital Electrical Distribution Panel Breaker Opened.Caused by Personnel Error. Personnel Reinstructed on Removal of Channel |
- on 891017,inadvertent Plant Protection Sys Actuation Occurred When 120 Volt Ac Vital Electrical Distribution Panel Breaker Opened.Caused by Personnel Error. Personnel Reinstructed on Removal of Channel
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation |
| 05000313/LER-1989-018, :on 890501,reactor Tripped & Inadvertently Jarred Turbine Control Panel Containing Mercoid Switches for Turbine Trip Functions.Caused by Caution Label Missing from Control Panel.Warning Placard Installed |
- on 890501,reactor Tripped & Inadvertently Jarred Turbine Control Panel Containing Mercoid Switches for Turbine Trip Functions.Caused by Caution Label Missing from Control Panel.Warning Placard Installed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-019-01, :on 881209,emergency Feedwater Initiation & Control Sys Actuation Occurred on Indicated Low Water Level. Caused by Personnel Error.Memo Issued Describing Event & Recognition of Need for Valve Use Emphasized |
- on 881209,emergency Feedwater Initiation & Control Sys Actuation Occurred on Indicated Low Water Level. Caused by Personnel Error.Memo Issued Describing Event & Recognition of Need for Valve Use Emphasized
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) |
| 05000368/LER-1989-019-02, :on 890927,identified That Closing Torque on Valves May Be Insufficient Against Postulated Worst Case Differential Pressure.Caused by Initial Plant Construction. Mod to Replace Gearing Made to Motor Operator |
- on 890927,identified That Closing Torque on Valves May Be Insufficient Against Postulated Worst Case Differential Pressure.Caused by Initial Plant Construction. Mod to Replace Gearing Made to Motor Operator
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-019, :on 880517,discrepancies Identified in Piping Supports for HPI Sys Which Have Impacted Seismic Qualification.Caused by Deficiencies Resulting from 1979 Sys Mod Which Were Not Detected During Review |
- on 880517,discrepancies Identified in Piping Supports for HPI Sys Which Have Impacted Seismic Qualification.Caused by Deficiencies Resulting from 1979 Sys Mod Which Were Not Detected During Review
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-020, :on 890530,manual Actuation of Emergency Feedwater Pump Occurred.Caused by Tube Failures in Feedwater HX & Leaking B Startup Control Valve Which Necessitated Opening of Valve FW-8B.Tube Leaks Repaired |
- on 890530,manual Actuation of Emergency Feedwater Pump Occurred.Caused by Tube Failures in Feedwater HX & Leaking B Startup Control Valve Which Necessitated Opening of Valve FW-8B.Tube Leaks Repaired
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-020-01, :on 891029,due to Maint Activities on Radiation Monitoring Equipment,Min Radiation Monitoring Equipment,Required by Tech Specs,Unavailable.Caused by Personnel Error.Personnel Trained |
- on 891029,due to Maint Activities on Radiation Monitoring Equipment,Min Radiation Monitoring Equipment,Required by Tech Specs,Unavailable.Caused by Personnel Error.Personnel Trained
| 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(e)(2) |
| 05000313/LER-1989-021, :on 890601,inadvertent Main Steam Line Isolation Occurred During Maint.Caused by Defective Instrument Modules.Defective Modules Replaced & Affected Channels Tested |
- on 890601,inadvertent Main Steam Line Isolation Occurred During Maint.Caused by Defective Instrument Modules.Defective Modules Replaced & Affected Channels Tested
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-021-01, :on 891111,when Low Level Radwaste Water in Waste Condensate Tank Aligned to Be Released,Discovered That Radiation Monitor Inoperable for Duration of Release.Caused by Personnel Error.Procedure Revised |
- on 891111,when Low Level Radwaste Water in Waste Condensate Tank Aligned to Be Released,Discovered That Radiation Monitor Inoperable for Duration of Release.Caused by Personnel Error.Procedure Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-022, :on 891114,4,160-volt Ac ESF Electric Bus Unexpectedly Deenergized During post-maint Testing on Auxiliary Relay.Caused by Inadequate Test Controls.Job Order Changed to Include Test Switch |
- on 891114,4,160-volt Ac ESF Electric Bus Unexpectedly Deenergized During post-maint Testing on Auxiliary Relay.Caused by Inadequate Test Controls.Job Order Changed to Include Test Switch
| 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) |
| 05000313/LER-1989-022, :on 890120,RCS Backleakage Occurred Through failed-open Check Valve Resulted in Design Temp of Hpis Piping Being Exceeded.Caused by Failure of Support Designer to Use Correct Load.New Support Replaced |
- on 890120,RCS Backleakage Occurred Through failed-open Check Valve Resulted in Design Temp of Hpis Piping Being Exceeded.Caused by Failure of Support Designer to Use Correct Load.New Support Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-022-01, :on 891114,inadequate post-maint Test Controls Resulted in de-energizing 4,160 Volt Ac ESFs Electric Bus Uexpectedly.Caused by Inadequate post-maint Test Controls. Job Order Instructions Changed |
- on 891114,inadequate post-maint Test Controls Resulted in de-energizing 4,160 Volt Ac ESFs Electric Bus Uexpectedly.Caused by Inadequate post-maint Test Controls. Job Order Instructions Changed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) |
| 05000313/LER-1989-023, :on 890605,determined That Power Range Nuclear Instrumentation Calibr Required by Tech Specs Had Not Been Performed within Specified Frequency.Caused by Lack of Procedural Guidance.Procedure Revised |
- on 890605,determined That Power Range Nuclear Instrumentation Calibr Required by Tech Specs Had Not Been Performed within Specified Frequency.Caused by Lack of Procedural Guidance.Procedure Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) |
| 05000368/LER-1989-023, :on 891117,noted That Channel a Not Responding to Change in Power Level & Declared Inoperable.Caused by Defective Preamplifier.Evaluation of Sys Design & Channel Functional Test Initiated |
- on 891117,noted That Channel a Not Responding to Change in Power Level & Declared Inoperable.Caused by Defective Preamplifier.Evaluation of Sys Design & Channel Functional Test Initiated
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) |