ML091540661
| ML091540661 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 06/15/2009 |
| From: | Bamford P J Plant Licensing Branch 1 |
| To: | Pardee C G Exelon Generation Co, Exelon Nuclear |
| Bamford, Peter J., NRR/DORL 415-2833 | |
| References | |
| RIS 2000-17, TAC ME1086, TAC ME1087 | |
| Download: ML091540661 (9) | |
See also: RIS 2000-17
Text
UNITED NUCLEAR REGULATORY
WASHINGTON, D.C. 20555-0001
June 15, 2009 Mr. Charles G. Pardee
President
and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC
4300 Winfield Road Warrenville, IL 60555 LIMERICK GENERATING STATION, UNITS 1 AND 2 -
AUDIT OF EXELON
GENERATION
COMPANY, LLC'S MANAGEMENT
OF REGULATORY
COMMITMENTS (TAC NOS. ME1086 AND ME1087) Dear Mr. Pardee: In Regulatory Issue
Summary 2000-17, "Managing
Regulatory
Commitments Made by Power
Reactor Licensees to the NRC Staff," dated
September
21 J 2000, the
Nuclear Regulatory
Commission (NRC) informed licensees that the Nuclear Energy Institute (I'JEI) document NEI 99-04, "Guidelines
for Managing NRC Commitment
Changes," contains acceptable
guidance for controlling
regulatory
commitments
and encouraged
licensees to use the NEI
guidance or similar administrative
controls to ensure that regulatory
commitments
are implemented and that changes to the regulatory
commitments
are evaluated and, when appropriate, reported to the NRC. The NRC Office of
Nuclear Reactor Regulation (NRR) has
instructed
its staff to perform an audit
of licensees'
commitment
management
programs once every 3 years to
determine
whether the licensees'
programs are consistent with the industry
guidance in NEI 99-04, and that regulatory
commitments are being
effectively
implemented. An audit of the
commitment
management program for Limerick
Generating Station (LGS), Units 1 and 2 was
performed during the period of May 11 through May 15, 2009. Based on the audit, the NRC
staff concludes that: (1) LGS had
implemented
NRC commitments on a timely basis; and (2) LGS had
implemented
an effective program for
managing !\IRC commitment changes. Details of the audit are set forth in the
enclosed audit report.
Sincerely, ,/'7. Peter Bamford, Project
Manager Plant Licensing Branch
1-2 Division of Operating
Reactor Licensing Office of Nuclear
Reactor Regulation Docket Nos. 50-352 and
50-353 Enclosure: Audit Report cc w/encl: Distribution via
Listserv
UNITED NUCLEAR REGULATORY
WASHINGTON, D.C. 20555-0001
AUDIT REPORT BY THE OFFICE OF
NUCLEAR REACTOR REGULATION
REGULATORY
COMMITMENTS MADE BY EXELON
GENERATION COMPANY, LLC TO
THE NUCLEAR REGULATORY
COMMISSION
FOR LIMERICK GENERATING
STATION, UNITS 1 AND 2
DOCKET NOS. 50-352 AND 50-353
1.0 INTRODUCTION
AND BACKGROUND
In Regulatory
Issue Summary 2000-17, "Managing
Regulatory
Commitments Made by Power
Reactor Licensees to the NRC Staff," dated
September 21, 2000 (Agencywide
Documents
Access and Management
System (ADAMS) Accession
No. ML003741774), the Nuclear Regulatory
Commission (NRC) informed licensees that the Nuclear Energy Institute (NEI)
document I\IEI99-04, "Guidelines for Managing NRC
Commitment
Changes" (ADAMS Accession
No. ML003680088)
contains acceptable
guidance for controlling
regulatory
commitments
and encouraged
licensees to use the NEI
guidance or similar administrative controls to
ensure that regulatory
commitments
are implemented and that changes to the regulatory
commitments
are evaluated and, when
appropriate, reported to the NRC. The NRC Office of
Nuclear Reactor Regulation (NRR) has instructed
its staff to perform an audit
of licensees'
commitment
management
programs once every 3 years to
determine
whether the licensees' programs are
consistent with the industry guidance in NEI 99-04, and that regulatory
commitments are being
effectively
implemented.
defines a "regulatory
commitment" as an explicit statement to take a
specific action agreed to, or
volunteered by, a licensee and submitted in writing on the
docket to the NRC. NRR guidelines direct the NRR Project
Manager to audit the
licensee's
commitment
management program by
assessing
the adequacy of the licensee's
implementation of a sample
of commitments made to the NRC in past licensing actions (amendments, reliefs, exemptions, etc.) and
activities (bulletins, generic letters, etc.).
2.0 AUDIT PROCEDURE
AND RESULTS An audit of the
commitment
management program for Limerick
Generating Station (LGS), Units 1 and 2 was performed during the period of May 11 through May 15, 2009. The audit was performed at LGS using
documentation provided by Exelon
Generating Company, LLC (Exelon) personnel, as requested by the NRC staff.
Enclosure
-2The NRC staff reviewed
commitments made during the period
approximately 3 years prior to the audit. The audit consisted of two major parts: (1) verification of the
licensee's
implementation
of NRC commitments that have been completed and (2) verification of the
licensee's program for managing changes to NRC commitments. Verification of
Licensee's
Implementation
of NRC Commitments The primary focus of this part of the audit is to confirm that the
licensee has implemented commitments made to the NRC as part of past licensing
actions/activities.
For commitments
not yet implemented, the NRC
staff determines
whether they have been captured in an
effective program for future
implementation. Audit Scope The audit addressed a sample of
commitments made during the review period. The audit focused on regulatory
commitments (as defined above) made in writing to the NRC as a result of past licensing actions (amendments, exemptions, etc.) or licensing
activities (bulletins, generic letters, etc.). Before the audit, the NRC staff searched ADAMS for
licensee commitments associated with LGS for
verification. The review included licensing actions and licensing activities with NRC
issuance dates in 2006, 2007, 2008 and portions of 2009. The
commitments included in the review are shown in Table 1. The audit excluded the following types of commitments that are internal to
licensee processes: Commitments made on the
licensee's own initiative among internal
organizational
components. Commitments that pertain to
milestones of licensing
actions/activities (e.g., respond to an NRC request for additional information by a certain date).
Fulfillment of these commitments was indicated by the fact that the subject licensing
action/activity
was completed. Commitments made as an internal reminder to take actions to comply with existing
regulatory
requirements such as regulations, Technical
Specifications (TSs), and
Updated Final Safety Analysis Reports (UFSARs).
Fulfillment
of these commitments
was indicated by the
licensee having taken timely action in
accordance with the subject
requirements. Audit Results Table 1 provides the
specific details and results of the audit for
verification of the licensee's implementation of
commitments.
All commitments associated with licensing actions or licensing activities were verified to be
completed
or adequately tracked by the
licensee for future completion at an
appropriate
date. Verification of the
Licensee's Program for Managing NRC
Commitment
Changes The primary focus of this part of the audit is to verify that the licensee has established administrative controls for modifying or deleting
commitments made to the NRC. The NRC staff
-compared the
licensee's
process for controlling
regulatory
commitments to the guidelines
in NEI 99-04, which the NRC has found to be an
acceptable guide for
licensees
to follow for managing and changing commitments.
The process used at LGS is
contained
in licensee procedure LS-AA-11 0, Revision 6, "Commitment
Management." The audit reviewed a
sample of commitment
changes as shown in Table 2, that
included changes that were or will be reported to the NRC, and
changes that were not or will not be reported to the NRC. The
audit also verifies that the
licensee's
commitment
management
system includes a mechanism to ensure
traceability
of commitments following initial
implementation.
This ensures that licensee
personnel are able to
recognize that future
proposed changes to the affected design features or operating
practices
require evaluation
in accordance with the commitment change control process.
2.2.1 Audit Results The NRC staff reviewed the
licensee's
procedure LS-AA-11 0, Revision 6, against NEI 99-04.
Section 6.1 of the
procedure lists NEI 99-04 as a reference. The NRC
staff found that
generally follows the
guidance of NEI 99-04 and
provides detailed instructions
for making regulatory
commitments, tracking regulatory
commitments, annotating
documents
to provide traceability
of commitments, and for making
changes to commitments. The NRC staff concludes that the procedure used by the
licensee to manage
commitments
provides the necessary
attributes for an effective
commitment
management
program. Table 2 provides the specific details and results of the audit of
commitment
changes for LGS. Areas warranting
further discussion
are described
below. Attachment 2 to procedure LS-AA-11 0
contains a flowchart that is intended to match up with Figure A-1 of NEI 99-04. It was noted during the
audit that the two
flowcharts
differ slightly downstream of the "Yes" answer in decision step 3, "Original
Commitment
Necessary
for Compliance." None of the
commitments reviewed in this audit would have come to a
different
conclusion based on the
discrepancy, so it was not
judged to detract from the commitment
program's
effectiveness. No readily
apparent reason for the
discrepancy
was immediately available, so the licensee entered the issue into the
corrective action program for
evaluation (Issue Report AR
00918829). It was also noted that
commitment
change evaluation
forms sometimes contain multiple
commitments in the original
commitment
description. The NRC staff noted that this could allow
a decision block to be skipped for such a "sub-commitment." For example, commitment
tracking number T04090 evaluates the deletion of four
sub-commitments all relating to an NRC Safety
Evaluation
Report (SER) dated June 28, 1994. Since
question number 2 on the change form only contained three
answers it appeared that one of the
sub-commitments may not have been fully evaluated.
Subsequent to the site review of the
commitment program, the licensee
determined that one of the
answers applied to two
different
sub-commitments, though this was not clearly identified on the form. Since this
commitment change was reported to the NRC as part of the annual report, this
example is not consequential
or safety significant, however, the licensee agreed to
evaluate the generic implications of the potential to not fully
evaluate a commitment (Issue Report AR
00919845).
-Two commitment
change forms (T02935, T02462) did not have strong
supporting reasons for the question "Is the
changed commitment necessary to
minimize recurrence of the adverse condition." The
licensee stated that the reason for
answering
this question "No" was that the
station's
procedure
change process would ensure no recurrence. By deleting the commitment, however, no
annotation to the previous events (in this case
Licensee Event Reports (LERs>> would be retained in the
procedure, inhibiting such a review within the
procedure
change process. Thus, as written, it
appears that a "Yes" answer would have been
appropriate.
It is probable that there may be
other valid reasons not listed on the form to
answer "No" to this question in both cases. For example, commitment
change T02662 evaluates
the frequency of a High Pressure
Coolant Injection (HPCI) Turbine Stop Valve Balance
Chamber adjustment
which is done by
procedure
M-C-756-014. During the site review, licensee personnel stated that the
preventative
maintenance program would
systematically
evaluate any surveillance
frequency changes. This rationale was not listed on the form. In the second
example, commitment
change number T02462, multiple actions from a past LER were
evaluated as not necessary
to prevent recurrence
because "No changes will be made to the
process without complete review." This justification
is superficial and could be
strengthened
by specifying what step in the
procedure
change process will provide this depth of review
considering the loss of the annotation to the deleted
commitment. Alternatively, the
rationale could be changed to specify
another applicable reason that
recurrence is prevented. The
licensee wrote Issue Report
AR 00919868 to evaluate this concern, both generically and in these specific cases. 3.0 CONCLUSION As discussed above, the
licensee's
procedure used to manage commitments
provides the necessary
attributes for an effective
commitment
management program. Several
suggestions for program
improvement were made that the licensee entered into the
corrective
action program for
evaluation. The NRC staff agrees that this is the
proper response to the issues
identified.
4.0 LICENSEE PERSONNEL
CONTACTED FOR THIS AUDIT S. Gamble Principal Contributor: P.
Bamford Date: June
15, 2009
Table Written Commitments
-
LGS Submittal
Date NRC TAC No. NRC Issuance Summary of Commitment
and Licensee Tracking Number (if applicable)
Licensee Implementation
Status 07/27/2007
MD5937, MD5938 Amendment Nos. 191/152
dated OS/29/2008 Update UFSAR to
explicitly
specify Technical
Requirements
Manual information is treated at the same level as information presented in the UFSAR for the purpose of 10 CFR 50.59
evaluations. Complete -verified
incorporation
into UFSAR Rev. 14, September
2008. 10/19/2007
MD7048, MD7049 Amendment Nos. 195/156
dated 10/28/2008 Update UFSAR to specify doubling of Local Power Range Monitor
uncertainty when using increased
surveillance interval. Licensee
tracking No. T04666.
In progress -UFSAR update not due until 2010, tracking
documentation
for inclusion into next update was verified.
Procedure
changes effective
with amendment implementation, procedure NF-AB-120.
04/21/2008
MD8630, MD8631 Amendment Nos. 198/159
dated 03/23/2009
Implement new working hours
requirements specified in 10 CFR 26, subpart I, concurrently
with implementation of TS amendment to delete
references to Generic Letter (GL) 82-12. Licensee
tracking No. AR A1657834.
In progress-implementation scheduled for
10/01/2009.
04/11/2008
MD7841,
MD7842 Generic Letter 2008-01, dated
01/11/2008
Complete walkdowns of Unit 2
inaccessible piping systems during spring 2009 refueling outage (RFO).
Complete evaluations
of subject systems within 60 days following startup from 2009 RFO. Licensee
tracking No. AR A1659520
Submit supplemental response to NRC with results
of completed
evaluations within 90 days of startup from spring 2009 RFO. Licensee tracking No. AR A1659520
Complete -verified by work orders during site
audit. In-process -due 06/15/2009 In-process -due
07/12/2009'
10/14/2008
MD7841, MD7842 Generic Letter 2008-01, dated
01/11/2008 Install new vents on
HPCI/Core
Spray/Residual Heat Removal systems during 2009 RFO Complete -verified sample of completed w/o's documenting new vent additions during audit
Table Changed
Tracking Number Source Justification
for change/deletion
NRC Notification
T00713 Response to Notice of Violation (NOV)
90-13/90-12 Original GET module
superseded by fleet wide lesson plans and
computer based training.
Current Exelon procedures
ensure continued compliance.
Yes T01992 NRC Inspection Report (IR)
92-80 Motor Operated Valve program
commitments are covered by
Exelon procedures
that superseded original
procedure with the contained frequencies.
Current Exelon procedures ensure continued compliance.
Yes T04090 * I NRC SER dated June 28, 1994, Amendment Nos. 71/34 1. Drift analysis determined that drift program is covered by current corrective action program 2. Technical
specifications
have been revised to specify the 18
month surveillance
frequency 3. All refueling floor
ventilation radiation monitor
recorders
have been replaced. 4. Analysis shows no need for 3 millisecond additional margin.
Yes T02578 GL 93-01 Recommended testing from GL is not a regulatory requirement. Required testing per 10 CFR 50 Appendix E, section VI, paragraph 1 is still required by
procedure EP-AA-124, which is
subject to 10 CFR 50.54(q) evaluation.
No T03877 LER 1-95-08 Suction strainer testing is no longer required. NRC was notified and approved
cessation of suction strainer testing via safety evaluation dated
August 10, 1998.
No T03645 LER 1-95-08 Only a portion of this
commitment, which had multiple entries was deleted. The deleted portion was identical to T03877.
The commitment remains open for safety relief valve tailpipe monitoring program, which remains in place.
No
Table Changed
Tracking Source Justification
for NRC Number change/deletion
Notification
T03950 LER 2-96-003 TS have been changed to delete
No requirement
for emergency
diesel generator failure reports, thus the
procedure
references to this I trackinq are no lonqer needed.
T02289 LER 90-11 Match marking is a
standard maintenance
practice and is No I called for in
procedures 500-128 throuqh
PMQ-500-131.
T02462* LER 1-87-015 HPCI turbine stop valve balance
No chamber adjustment
is performed by procedure
M-C-756-014. Procedure review
process will ensure no recurrence.
T02935* LER 87-061
Commitment
reflects procedure
No changes made as a result of 1988
exit interview
examiner concerns.
Commitment
tracking no longer required because
procedure
review process will ensure no recurrence of condition.
T03891 Letter to NRC dated
August This commitment had two parts.
No 19, 1996. One part was a
duplicate of a separate tracked, open
commitment (T03941).
The second part reflects a UFSAR change made in the past that is no longer
applicable
after completion of the spent fuel pool
rerack. T02950 NRC IR 87-08
& 87-07 The procedure created to resolve
No this observation (not a finding or violation) from IR 87-07 response, OT-117, still exists and the
procedure/plant
change process will ensure proper actions are taken in response to
Reactor Protection System failures. A
second commitment on this form, review NUREG-0899
to ensure Procedure
Generation
Package incorporates
latest recommendations, was a completed
one-time action. * Issue Report written, see report for
description
June 15, 2009 Mr. Charles G. Pardee
President
and Chief Nuclear Officer Exelon Nuclear Exelon Generation
Company, LLC 4300 Winfield Road Warrenville, IL 60555
LIMERICK GENERATING STATION, UNITS 1 AND 2 -
AUDIT OF EXELON
GENERATION COMPANY, LLC'S
MANAGEMENT
OF REGULATORY
COMMITMENTS (TAC NOS.
ME1086AND
ME1087) Dear Mr. Pardee: In Regulatory Issue
Summary 2000-17, "Managing Regulatory
Commitments Made by Power
Reactor Licensees to the NRC Staff," dated
September
21,2000, the Nuclear Regulatory
Commission (NRC) informed licensees that the Nuclear Energy Institute (NEI) document NEI 99-04, "Guidelines
for Managing NRC Commitment
Changes," contains acceptable
guidance for controlling
regulatory
commitments
and encouraged
licensees to use the NEI
guidance or similar administrative controls to ensure that
regulatory
commitments
are implemented and that changes to the regulatory
commitments
are evaluated and, when appropriate, reported to the NRC. The NRC Office of
Nuclear Reactor Regulation (NRR) has
instructed
its staff to perform an audit
of licensees'
commitment
management programs once every 3 years to
determine
whether the licensees'
programs are consistent with the industry
guidance in NEI 99-04, and that regulatory
commitments are being
effectively
implemented. An audit of the
commitment
management program for
Limerick Generating Station (LGS), Units 1 and 2 was
performed during the period of May 11 through May 15, 2009. Based on the audit, the NRC
staff concludes that: (1) LGS had
implemented
NRC commitments on a timely basis; and (2) LGS had
implemented
an effective program for
managing NRC commitment changes. Details of the audit are set forth in the enclosed audit report.
Sincerely, Ira! Peter Bamford, Project Manager Plant Licensing Branch
1-2 Division of
Operating
Reactor Licensing Office of
Nuclear Reactor Regulation Docket Nos. 50-352 and
50-353 Enclosure: Audit Report cc w/encl: Distribution via
Listserv DISTRIBUTION:
PUBLIC RidsNrrLAABaxter
RidsNrrPMPBamford
RidsRgn1 MailCenter
Resource RidsOgcRp Resource LPL 1-2 R/F
RidsAcrsAcnw_MailCTR
Resource RidsNrrDorlLpl1-2
Resource SMeighan, NRR Pkrohn, R1
ACCESSION
NUMBER' ML091540661
OFFICE LPL1-2/PM
LPL 1-2/LA LPL1-2/BC
NAME Pbamford Abaxter Hchernoff
DATE 6/4/09 6/10/09 6/15/09 OFFICIAL RECORD