Other: GO2-10-011, License Renewal Application, Applicants Environmental Report Operating License Renewal Stage, Appendix E, GO2-11-202, Response to NRC Audit Questions Regarding Their License Renewal Application, GO2-12-002, Response to Information Request, License Renewal Application, ML102160357, ML103630739, ML11250A015, ML11273A066, ML11348A014, ML12033A058
|
MONTHYEARGO2-10-011, License Renewal Application, Applicants Environmental Report Operating License Renewal Stage, Appendix E2010-01-19019 January 2010 License Renewal Application, Applicants Environmental Report Operating License Renewal Stage, Appendix E Project stage: Other ML1012503142010-05-10010 May 2010 Meeting Summary-CGS License Renewal Overview and Environmental Scoping Meetings Project stage: Meeting ML1012505192010-05-10010 May 2010 Summary of Public License Renewal Overview and Environmental Scoping Meetings Related to the Review of the Columbia Generating Station License Renewal Application Project stage: Meeting ML1024403422010-08-19019 August 2010 Response to Request for Additional Information License Renewal Application Project stage: Response to RAI ML1021603572010-08-19019 August 2010 Scoping and Screening Audit Report Regarding the Columbia Generating Station, License Renewal Application Project stage: Other ML1022203732010-08-26026 August 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application for Fatigue Monitoring Program, TLAA Exemptions, Metal Fatigue TLAA, Cumulative Fatigue Damage, CASS, and Structural Project stage: RAI ML1025200482010-09-0303 September 2010 Response to Requests for Additional Information on License Renewal Application Project stage: Response to RAI ML1024505712010-09-14014 September 2010 Summary of Telephone Conference Call Held on August 10, 2010, Between the U.S. NRC and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1024506212010-09-14014 September 2010 Summary of Telephone Conference Call Held on August 26, 2010, Between the U.S. NRC and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1024507562010-09-16016 September 2010 8/12/10, Summary of Telephone Conference Call Held on Between NRC and Energy Northwest, Concerning the RAI Pertaining to the Columbia Generating Station, LRA Project stage: RAI ML1024507272010-09-16016 September 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI ML1025306452010-09-21021 September 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI ML1027004332010-10-0404 October 2010 Summary of Telephone Conference Call Held on September 13, 2010, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License R Project stage: RAI ML1028004262010-10-14014 October 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application (TAC No. 3058) Project stage: RAI ML1027303552010-10-20020 October 2010 Letter Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application, Concerning Structures (Tac No. ME3058) Project stage: RAI ML1028507352010-10-20020 October 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application (TAC ME3058) Concerning Structures Project stage: RAI ML1027902232010-10-25025 October 2010 Summary of Telephone Conference Call Held Between NRC and Energy Northwest, Concerning the Draft Rao Pertaining to the Columbia Generating Station, License Renewal Application Project stage: Draft Other ML1028701932010-10-25025 October 2010 9/22/10 Summary of Telephone Conference Call Held Between the USNRC and Energy Northwest Concerning the D-RAI Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1028702452010-10-25025 October 2010 October 13, 2010, Summary of Teleconference Held Between the U.S. NRC and Energy Northwest, Concerning the Draft Request for Additional Information Pertaining to the Columbia Generating Station License Renewal Application Project stage: Draft RAI ML1028501032010-10-27027 October 2010 Summary of Telephone Conference Calls Held on 9/20/10, Between Us NRC and Energy Northwest, Concerning the Response to RAI Pertaining to the Columbia Generating Station, LRA Project stage: RAI ML1029305932010-11-0101 November 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI ML1030100802010-11-0505 November 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI GO2-10-164, Response to Request for Additional Information License Renewal Application2010-11-11011 November 2010 Response to Request for Additional Information License Renewal Application Project stage: Response to RAI ML1030905662010-11-19019 November 2010 Summary of Teleconference Held on September 22, 2010, Between the U.S. NRC and Energy Northwest, Concerning the Responses to the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1031305482010-11-19019 November 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI ML1032003382010-11-19019 November 2010 Summary of Teleconference Held on November 8, 2010, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Responses to Request for Additional Information Pertaining to the Columbia Generating Station, LRA Project stage: RAI ML1030004792010-11-19019 November 2010 Summary of Telephone Conference Call Between the USNRC and Energy Northwest, Concerning the Draft Request for Additional Information Pertaining to the Columbia Generating Station, LRA Project stage: Draft RAI ML1035400222010-12-20020 December 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application Project stage: RAI ML1035506032010-12-27027 December 2010 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application (TAC No. Me3058) Project stage: RAI ML1100500182011-01-0606 January 2011 Summary of Telephone Conference Call Held on January 3, 2011, Between the NRC and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application (TAC Number ME3 Project stage: RAI ML1034305262011-01-10010 January 2011 Schedule Revision for the Review of the Columbia Generating Station License Renewal Application Project stage: Approval ML1036307392011-01-11011 January 2011 Safety Project Manager Change for the License Renewal of Columbia Generating Station (Tac No. ME3058) Project stage: Other ML1100604382011-01-13013 January 2011 Summary of Telephone Conference Call Held on 1/5/11, Between NRC and Energy Northwesy, Concerning the RAI Pertaining to the Columbia Generating Station License Renewal Application (Tac No. ME3058) Project stage: RAI ML1101405882011-01-31031 January 2011 Summary of Telephone Conference Call Held Between NRC and Energy Northwest, Concerning the Responses to RAI Pertaining to the Columbia Generating Station. License Renewal Application Project stage: RAI ML1102007102011-02-0303 February 2011 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Energy Northwest Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1102402022011-02-0303 February 2011 Summary of Telephone Conference with NRC and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1102404262011-02-0303 February 2011 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application for Metal Fatigue (Tac No. ME3058) Project stage: RAI ML1102603802011-02-16016 February 2011 January 24, 2011, Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station Project stage: RAI ML1104702152011-02-23023 February 2011 Summary of Telephone Conference Call Held on February 14, 2011, Btw the USNRC and Energy Northwest, Concerning the Responses to the Request for Additional Information Pertaining to the Columbia Generating Station, LRA Project stage: RAI ML1105401262011-02-28028 February 2011 2/17/11 Summary of Telephone Conference Call Held Between the USNRC and Energy Northwest, Concerning the Responses to the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: RAI ML1106107122011-03-0909 March 2011 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application for Buried Piping and Tanks Inspection Project stage: RAI ML1106909972011-03-15015 March 2011 Summary of Telephone Conference Call Held on 3/8/11 Btw the USNRC and Energy Northwest Concerning the Responses to the RAI Pertaining to the Columbia Generating Station, License Renewal Application (TAC Number ME3058) Project stage: RAI ML1106806702011-03-18018 March 2011 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application for Drywell Floor Peripheral Seal Assembly (TAC Number ME3058) Project stage: RAI ML1106303602011-03-23023 March 2011 Request for Additional Information for the Review of the Columbia Generating Station, License Renewal Application for Time-Limited Aging Analyses of Reactor Vessel Neutron Embrittlement (TAC Number ME3058) Project stage: RAI ML1108714952011-04-0505 April 2011 Summary of Telephone Conference Call Held on March 23, 2011, Between NRC and Energy Northwest, Concerning the RAI Pertaining to the Columbia Generating Station, LRA (Tac No. ME3058) Project stage: RAI GO2-11-085, CGS 2011-04 Licensee Post Exam Analysis2011-04-22022 April 2011 CGS 2011-04 Licensee Post Exam Analysis Project stage: Request ML11138A3232011-05-24024 May 2011 RAI for the Review of the Columbia Generating Station, License Renewal Application for Operating Experience Project stage: RAI ML11140A1612011-06-0202 June 2011 RAI for the Review of the Columbia Generating Station, License Renewal Application Regarding Core Plate Assembly Project stage: RAI ML11137A0442011-06-0808 June 2011 Summary of Telephone Conference Call Between the NRC and Energy Northwest, Concerning the Draft Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application Project stage: Draft RAI ML11165A2432011-06-22022 June 2011 Summary of Telephone Conference Call Held on June 1, 2011, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Request for Additional Information Pertaining to the Columbia Generating Station, LRA Project stage: RAI 2010-09-03
[Table View] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 November 8, 2011 Mr. Bradley J. Sawatzke, Vice President of Nuclear Generation and Chief Nuclear Officer Columbia Generating Station Energy Northwest MD PE08 P.O. Box 968 Richland, WA 99352 REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE COLUMBIA GENERATING STATION, LICENSE RENEWAL APPLICATION REGARDING FIRE WATER AND OPEN CYCLE COOLING AGING MANAGEMENT PROGRAMS (TAC NO. ME3058)
Dear Mr. Sawatzke:
By letter dated January 19, 2010, Energy Northwest submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew operating license NPF-21 for Columbia Generating Station, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future. The issue in the enclosure was discussed with Abbas Mostala and an expedited, mutually agreeable date for the response is within 10 days of the date of this letter. If you have any questions, please contact me at 301-415-3897 or bye-mail at arthur.cunanan@nrc.gov.
Sincerely, Arthur D. Cunanan, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
As stated cc w/encl: Listserv COLUMBIA GENERATING LICENSE RENEWAL REQUEST FOR ADDITIONAL RAI (Follow-up)
SAMA FL-OSR-1 Background The response to the request for additional information (RAI) severe accident mitigation alternative (SAMA) FL-06R, dated September 29, 2011, states that the piping segments that are under the scope of SAMA FL-06R include fire protection system piping which is age managed by the Fire Water aging management program (AMP), and plant service water and standby service water piping which are age managed by the Open Cycle Cooling Water AMP. The RAI response also states that the SAMA candidate uses risk importance measures to provide insights to identify in-scope piping sections in these three systems that are more important to reducing the core damage frequency (CDF) contribution.
The RAI response further states that both aging management programs include non-destructive examination methods to monitor for loss of material which, when performed, will reduce the frequency of pipe-break initiating events for these systems and thus reduce the CDF. The response states that, "Final determination of the AMP testing and inspection locations will use plant experience and engineering evaluations to identify the most susceptible piping sections, as well as risk importance for selection of the testing frequency and locations." Issue The staff reviewed LRA Section B.2.26 and SER Section 3.0.3.2.9 for the Fire Water program; and license renewal application (LRA) Section B.2.42 and safety evaluation report Section 3.0.3.2.17 for the Open Cycle Cooling Water program and found no evidence that risk insights will be utilized in addition to plant experience and engineering evaluations to identify the most susceptible piping sections for inspections.
Request Revise LRA Sections B.2.26 and B.2.42 to state that risk insights will be utilized in addition to plant experience and engineering evaluations to identify the most susceptible piping sections for inspections, or state the basis for how the staff can conclude that the programs, when implemented, will utilize risk insights as an input to selecting inspection locations, or state how (e.g., specific program(s) and dates of implementation) this SAMA has been implemented independently of reliance on either the Fire Water AMP or the Open Cycle Cooling Water AMP. If full implementation has not occurred, state a commitment to implement this change prior to the period of extended operations.
State whether this potential SAMA would have been screened out in Phase I as already implemented if it had been discovered with the current state of program implementation.
November 8, 2011 Mr. Bradley J. Sawatzke, Vice President of Nuclear Generation and Chief Nuclear Officer Columbia Generating Station Energy Northwest MD PE08 P.O. Box 968 Richland, WA 99352 REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE COLUMBIA GENERATING STATION, LICENSE RENEWAL APPLICATION REGARDING FIRE WATER AND OPEN CYCLE COOLING AGING MANAGEMENT PROGRAMS (TAC NO. ME3058)
Dear Mr. Sawatzke:
By letter dated January 19, 2010, Energy Northwest submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew operating license NPF-21 for Columbia Generating Station, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future. The issue in the enclosure was discussed with Abbas Mostala and an expedited, mutually agreeable date for the response is within 10 days of the date of this letter. If you have any questions, please contact me at 301-415-3897 or bye-mail at arthur.cunanan@nrc.gov.
Sincerely, IRA! Arthur D. Cunanan, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession No.: ML 11305A *concurrence via e-mail OFFICE LA:DLR/RPB1*
PM:DLR/RPB1 BC:DLR/RPB1 PM:DLR/RPB1 NAME SFigueroa ACunanan DMorey ACunanan DATE 11/1/2011 11/7/2011 11/8/2011 11/8/2011 OFFICIAL RECORD COpy Letter to Bradley J. Sawatzke from Arthur D. Cunanan dated November 8, 2011 REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE COLUMBIA GENERATING STATION, LICENSE RENEWAL APPLICATION REGARDING FIRE WATER AND OPEN CYCLE COOLING AGING MANAGEMENT PROGRAMS (TAC NO. ME3058) DISTRIBUTION:
HARD COPY: DLR R/F E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource ACunanan DDoyle DMorey MThadani WWalker, RIV RCohen, RIV LSubin,OGC BSingal JDaily