IR 05000382/2017006

From kanterella
Revision as of 00:14, 10 May 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Annual Assessment Letter for Waterford Steam Electric Station Unit 3, (Report 05000382/2017006)
ML18052A527
Person / Time
Site: Waterford Entergy icon.png
Issue date: 03/01/2018
From: Miller G B
NRC/RGN-IV/DRP/RPB-D
To: Dinelli J
Entergy Operations
Miller G B
References
IR 2017006
Download: ML18052A527 (6)


Text

March 1, 2018

Mr. John Dinelli, Site Vice President Entergy Operations, Inc. 17265 River Road Killona, LA 70057-0751

SUBJECT: ANNUAL ASSESSMENT LETTER FOR WATERFORD STEAM ELECTRIC STATION UNIT 3 (REPORT 05000382/2017006)

Dear Mr. Dinelli:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Waterford Steam Electric Station Unit 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2017 through December 31, 2017. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The NRC determined the performance at Waterford Steam Electric Station Unit 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRC's Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (817) 200-1173 with any questions you have regarding this letter.

Sincerely,/RA/ Geoffrey B. Miller, Branch Chief Projects Branch D Division of Reactor Projects Docket: 50-382 License: NPF-38

Enclosure:

Waterford Steam Electric Station Unit 3 Inspection Plan Waterford01/01/2018 - 12/31/2019UnitStartEndActivityCACTitleStaff CountMAT'L CONTROL & ACCOUNTING1301/22/201801/26/2018IP 71130.11000742Material Control and Accounting (MC&A)RAD SAFETY 1,32301/22/201801/26/2018IP 71124.01000725Radiological Hazard Assessment and Exposure Controls301/22/201801/26/2018IP 71124.03000727In-Plant Airborne Radioactivity Control and Mitigation301/22/201801/26/2018IP 71151000746Performance Indicator VerificationWAT 50.59 CHANGES, TESTS, EXPERIMENTS3304/02/201804/06/2018IP 71111.17T000709Evaluations of Changes, Tests, and ExperimentsSECURITY TEAM INSPECTION2306/04/201806/08/2018IP 71130.04000736Equipment Performance, Testing, and Maintenance306/04/201806/08/2018IP 71130.07000739Security TrainingTRIENNIAL FIRE PROTECTION INSPECTION6307/30/201808/03/2018IP 71111.05XT000697Fire Protection - NFPA 805 (Triennial)307/30/201808/03/2018IP 92702000238Followup On Corrective Actions For Violations And Deviations308/13/201808/17/2018IP 71111.05XT000697Fire Protection - NFPA 805 (Triennial)EP PROGRAM INSPECTION1308/06/201808/10/2018IP 71114.02000717Alert and Notification System Testing308/06/201808/10/2018IP 71114.03000718Emergency Response Organization Staffing and Augmentation System308/06/201808/10/2018IP 71114.05000720Correction of Emergency Preparedness Weaknesses and Deficiencies308/06/201808/10/2018IP 71151001397Performance Indicator Verification308/13/201808/17/2018IP 71114.04000719Emergency Action Level and Emergency Plan Changes308/13/201808/17/2018IP 71151001397Performance Indicator VerificationRAD SAFETY 2,42309/10/201809/14/2018IP 71124.02000726Occupational ALARA Planning and Controls309/10/201809/14/2018IP 71124.04000728Occupational Dose AssessmentBIENNIAL PI&R INSPECTION4309/17/201809/21/2018IP 71152B000747Problem Identification and Resolution310/01/201810/05/2018IP 71152B000747Problem Identification and Resolution2/23/2018 10:41:08 AMPage 1 of 3This report does not include INPO and OUTAGE activities.This report shows only on-site and announced inspection procedures.IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING & EXERCISE WEEK 7

3 09/24/2018 09/28/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 3

10/15/2018 10/19/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing INITIAL EXAM 4

3 09/30/2018 10/06/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

3 11/04/2018 11/10/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

CYBER SECURITY INSPECTION 5

3 11/05/2018 11/09/2018 IP 71130.10P 000741 Cyber Security 3

11/26/2018 11/30/2018 IP 71130.10P 000741 Cyber Security SECURITY SOLO 1

3 12/03/2018 12/07/2018 IP 71130.02 000734 Access Control 3

12/03/2018 12/07/2018 IP 71151 001338 Performance Indicator Verification WATERFORD INSERVICE INSPECTION 1

3 01/14/2019 01/25/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR RP INSPECTION 2

3 01/14/2019 01/18/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3

01/14/2019 01/18/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 3

01/14/2019 01/18/2019 IP 71151 000746 Performance Indicator Verification WATERFORD EQ PROGRAMS INSPECTION 3

3 04/01/2019 04/19/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

SECURITY SOLO INSPECTION 1

3 05/13/2019 05/17/2019 IP 71130.02 000734 Access Control 3

05/13/2019 05/17/2019 IP 71151 001338 Performance Indicator Verification BRQ 2

3 07/29/2019 08/03/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -

Biennial SECURITY TEAM INSPECTION 2

3 10/07/2019 10/11/2019 IP 71130.05 000737 Protective Strategy Evaluation 2/23/2018 10:41:08 AM Page 2

of 3

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count RP TEAM INSPECTION 5

3 11/04/2019 11/08/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 3

11/04/2019 11/08/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 3

11/04/2019 11/08/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 3

11/04/2019 11/08/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP EXERCISE AND PI INSPECTION 4

3 11/18/2019 11/22/2019 IP 71114.01 000716 Exercise Evaluation 3

11/18/2019 11/22/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3

11/18/2019 11/22/2019 IP 71151 001397 Performance Indicator Verification TI 2515/194 2

3 12/09/2019 12/13/2019 TI 2515/194 000512 Inspection of the Licensee

s Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

2/23/2018 10:41:08 AM Page 3

of 3

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

ML18052A527 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: NHT/rdr Yes No Publicly Available Sensitive NRC-002 OFFICE DRP/SPE:D DRS/C:PSB1 DRS/D DRP/C:D DRP/D NAME JDixon JGroom AVegel GMiller TPruett SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA RLantz for/ DATE 2/21/18 2/21/18 2/22/18 2/23/18 2/22/18