List of Changes Affecting the Cook Nuclear Plant Security Training and Qualification Plan, Revision 2 and Physical Security Plan, Revision 3
ML021420070
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/14/2002
From: Greenlee S
Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
AEP:NRC:2073-01
Download: ML021420070 (3)


Text

Indiana Michigan Power Company Cook Nudear Plant One Cook Place Bndgman, MI 49106 61 &465--5,%

Safeguards Information Withhold From Public Disclosure INDIANA MICHIGAN POWER May 14, 2002 AEP:NRC:2073-01 10 CFR 50.54(p)

Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-Pl-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 LIST OF CHANGES AFFECTING THE COOK NUCLEAR PLANT SAFEGUARDS CONTINGENCY PLAN, REVISION 1 SECURITY TRAINING AND QUALIFICATION PLAN, REVISION 2 AND PHYSICAL SECURITY PLAN, REVISION 3 Pursuant to the provisions of 10 CFR 50.54(p), Indiana Michigan Power Company is submitting Revision 1 to the "Donald C. Cook Nuclear Plant Safeguards Contingency Plan," Revision 2 to the "Donald C. Cook Nuclear Plant Security Training and Qualification Plan," and Revision 3 to the "Donald C. Cook Nuclear Plant Physical Security Plan." provides a list of changes affecting Donald C. Cook Nuclear Plant Safeguards Contingency Plan, Revision 1; Security Training and Qualification Plan, Revision 2; and Physical Security Plan, Revision 3. Attachment 2 contains the Safeguards Contingency Plan. Attachment 3 contains the Security Training and Qualification Plan, and Attachment 4 contains the Physical Security Plan.

The changes made in these revisions do not eliminate plan commitments to specific security measures stated in 10 CFR 73.55(b) through (h), 10 CFR 73 Appendix B, nor do the changes decrease the ability of the CNP physical protection system and security organization to protect with high assurance against a design basis threat as stated in 10 CFR 73.1(a). These changes do not decrease the overall effectiveness of the plan or the security program and therefore do not require Nuclear Regulatory Commission approval prior to implementation.

NOTICE: WHEN SEPARATED FROM ATTACHMENTS, THIS DOCUMENT IS DECONTROLLED Safeguards Information Withhold From Public Disclosure AEP.,t le, ica ' Energy Partner,

Safeguards Information Withhold From Public Disclosure AEP:NRC:2073-01 U. S. Nuclear Regulatory Commission Page 2 This letter contains no new commitments.

Should you have any questions, please contact Mr. Gordon P. Arent, Manager of Regulatory Affairs, at (616) 697-5553.

Sincerely, cotA.Greenlee Director of Design Engineering and Regulatory Affairs DB/dmb Attachment C:

K. D. Curry, w/o attachments J. E. Dyer MDEQ - DW & RPD, w/o attachments NRC Resident Inspector, w/o attachments R. Whale, w/o attachments NOTICE: WHEN SEPARATED FROM ATTACHMENTS, THIS DOCUMENT IS DECONTROLLED Safeguards Information Withhold From Public Disclosure

Safeguards Information Withhold From Public Disclosure U. S. Nuclear Regulatory Commission Page 3 AEP:NRC:2073-01 bc:

G. P. Arent, w/o attachments A. C. Bakken, w/o attachments P. B. Cowan, w/o attachments R. W. Gaston, w/o attachments S. A. Greenlee, w/o attachments S. B. Haggerty, w/o attachments D. W. Jenkins, w/o attachments J. A. Kobyra, w/o attachments E. A. Larson, w/o attachments J. E. Pollock, w/o attachments J. F. Stang, Jr., - NRC Washington, DC, w/o attachments T. R. Stephens, w/o attachments NOTICE: WHEN SEPARATED FROM ATTACHMENTS, THIS DOCUMENT IS DECONTROLLED Safeguards Information Withhold From Public Disclosure