EA-03-208 Ltr 01/07/05 Perry Re Acknowledgment Letter of Licensee Response to Notice of Violation (NRC Office of Investigations Report No. 3-2002-031)
ML050070306
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/07/2005
From: Pederson C
Division of Reactor Safety III
To: Richard Anderson
FirstEnergy Nuclear Operating Co
References
3-2002-031, EA-03-208
Download: ML050070306 (4)


Text

January 7, 2005 EA-03-208 Mr. R. Anderson Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, A290 10 Center Road Perry, OH 44081

SUBJECT:

ACKNOWLEDGMENT LETTER OF LICENSEE RESPONSE TO NOTICE OF VIOLATION [NRC OFFICE OF INVESTIGATIONS REPORT NO. 3-2002-031]

Dear Mr. Anderson:

This will acknowledge receipt of a letter from the FirstEnergy Nuclear Operating Company (FENOC), dated April 30, 2004, in response to our letter dated April 1, 2004, transmitting a Severity Level III Notice of Violation. The findings involved the failure to follow Technical Specification 5.2.2.e overtime guidelines in that individuals worked in excess of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in a 7-day period and the immediate supervisors failed to request deviations from the overtime guidelines in advance from the Plant Manager or authorized designee. We have reviewed your corrective actions and have no further questions at this time.

Sincerely,

/RA/

Cynthia D. Pederson, Director Division of Reactor Safety Docket No. 50-440 License No. NPF-58 See Attached Distribution

R. Anderson cc:

G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC F. von Ahn, Plant Manager, Nuclear Power Plant Department W. OMalley, Manager, Maintenance Department J. Lausberg, Manager, Regulatory Compliance J. Messina, Director, Performance Improvement T. Lentz, Director, Nuclear Engineering Department M. OReilly, Attorney, First Energy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health

January 7, 2005 EA-03-208 Mr. R. Anderson Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, A290 10 Center Road Perry, OH 44081

SUBJECT:

ACKNOWLEDGMENT LETTER OF LICENSEE RESPONSE TO NOTICE OF VIOLATION [NRC OFFICE OF INVESTIGATIONS REPORT NO. 3-2002-031]

Dear Mr. Anderson:

This will acknowledge receipt of a letter from the FirstEnergy Nuclear Operating Company (FENOC), dated April 30, 2004, in response to our letter dated April 1, 2004, transmitting a Severity Level III Notice of Violation. The findings involved the failure to follow Technical Specification 5.2.2.e overtime guidelines in that individuals worked in excess of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in a 7-day period and the immediate supervisors failed to request deviations from the overtime guidelines in advance from the Plant Manager or authorized designee. We have reviewed your corrective actions and have no further questions at this time.

Sincerely,

/RA/

Cynthia D. Pederson, Director Division of Reactor Safety Docket No. 50-440 License No. NPF-58 See Attached Distribution DOCUMENT NAME: E:\\Filenet\\ML050070306.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII NAME ADunlop:tr DHills KOBrien CPederson DATE 01/05/05 01/05/05 01/06/05 01/07/05 OFFICIAL RECORD COPY

R. Anderson cc:

G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC F. von Ahn, Plant Manager, Nuclear Power Plant Department W. OMalley, Manager, Maintenance Department J. Lausberg, Manager, Regulatory Compliance J. Messina, Director, Performance Improvement T. Lentz, Director, Nuclear Engineering Department M. OReilly, Attorney, First Energy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health ADAMS Distribution:

AJM SPS1 RidsNrrDipmIipb GEG HBC KGO RJP OEMAIL CHW1 DRPIII DRSIII PLB1 JRK1