NFPA 805 Pilot Observation Visit Trip Report - March, 2006 - Transmittal Memo
ML061520285
Person / Time
Site: Oconee, Harris  Duke Energy icon.png
Issue date: 08/23/2006
From: Lain P
NRC/NRR/ADRA/DRA
To: Lyons J
NRC/NRR/ADRA/DRA
Lain P 415-2346, Lavretta A 415-3285
Shared Package
ML061530462 List:
References
Download: ML061520285 (2)


Text

August 23, 2006 MEMORANDUM TO: James E. Lyons, Director Division of Risk Assessment Office of Nuclear Reactor Regulation THRU:

Sunil D. Weerakkody, Chief /RA/

Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation FROM:

Paul W. Lain, Team Leader NFPA 805 Transition Pilot Program Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

SUBJECT:

NFPA 805 SECOND PILOT OBSERVATION VISIT TRIP REPORT, MARCH, 2006 We have enclosed the trip report on the second observation visit of pilot plants transitioning to the risk-informed, performance-based fire protection licensing basis in Title 10 of the Code of Federal Regulations (10 CFR) 50.48(c), (the NFPA 805 Rule). The trip occurred March 27 to 30, 2006 at Progress Energy headquarters in Raleigh, NC. The two Utilities with transitioning pilot plants; Duke Power for Oconee Nuclear Station and Progress Energy for the Shearon Harris Nuclear Plant provided briefings. We have included the trip report, the agenda, parking lot issues, and Issue Summary Sheets as enclosures to this memo. The handouts from the meeting are available in a separate file. This trip report will be publically available to provide lessons learned to those non-pilot plants transitioning NFPA 805.

Enclosure:

As stated CONTACT:

Paul Lain, NRR/DRA/AFPB 301-415-2346

MEMORANDUM TO: James E. Lyons, Director Division of Risk Assessment Office of Nuclear Reactor Regulation THRU:

Sunil D. Weerakkody, Chief Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation FROM:

Paul W. Lain, Team Leader NFPA 805 Transition Pilot Program Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

SUBJECT:

NFPA 805 SECOND PILOT OBSERVATION VISIT TRIP REPORT, MARCH, 2006 We have enclosed the trip report on the second observation visit of pilot plants transitioning to the risk-informed, performance-based fire protection licensing basis in Title 10 of the Code of Federal Regulations (10 CFR) 50.48(c), (the NFPA 805 Rule). The trip occurred March 27 to 30, 2006 at Progress Energy headquarters in Raleigh, NC. The two Utilities with transitioning pilot plants; Duke Power for Oconee Nuclear Station and Progress Energy for the Shearon Harris Nuclear Plant provided briefings. We have included the trip report, the agenda, parking lot issues, and Issue Summary Sheets as enclosures to this memo. The handouts from the meeting are available in a separate file. This trip report will be publically available to provide lessons learned to those non-pilot plants transitioning NFPA 805.

Enclosure:

As stated DISTRIBUTION:

ADAMS RidsNrrAdra (GHolahan)

RidsNrrDra (JLyons)

TQuay MTschiltz RidsNrrDraAfpb RidsNrrDirsIrib AFPB R/F SDinsmore PKoltay DSolorio. OE DStarkey, OE MSalley, RES JS Hyslop, RES AFPB PFillon, RII JBradey, RII RidsRgn1MailCenter RidsRgn2MailCenter RidsRgn3MailCenter RidsRgn4MailCenter ADAMS Accession # (Package):

ML061530462 ADAMS Accession # (Memo):

ML061520285 ADAMS Accession # (Trip Report):

ML061500468 ADAMS Accession # (Handouts):

ML061530193 OFFICE DRA:AFPB C:DRA:AFPB NAME PLain SDinsmore SWeerakkody DATE 08/17/06 08/12/06 08 /23/06 OFFICIAL RECORD COPY