NRC 2007-0075, Calculation Project Schedule Change
| ML072280462 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 08/15/2007 |
| From: | Koehl D Nuclear Management Co |
| To: | Office of Nuclear Reactor Regulation, Region 3 Administrator |
| References | |
| NRC 2007-0075 | |
| Download: ML072280462 (1) | |
Text
Comrnilted to Nuclear Excellence Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC August 15, 2007 NRC 2007-0075 Regional Administrator Region Ill U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 21 0 Lisle, lL 60532-4352 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Calculation Proiect Schedule Chanae
References:
(1) Nuclear Management Company, LLC (NMC) Letter Dated July 28, 2006, Transmitting Commitment Status Update In Reference (1) NMC submitted an Engineering Design Control Commitment Status Update, which provided a revised completion schedule for the milestones associated with the safety-related calculation project.
These milestones involved the completion of electrical, mechanical and instrumentation and control (I&C) calculations, as well as performance of the final effectiveness review by the end of 2007.
Based on the complexity of some of the calculations and progress to date, NMC anticipates that the calculation reconstitution project will now complete in 2008, with an effectiveness review of the project to be conducted in 2008. NMC will continue to provide updates to this schedule until completion of the project.
Please contact me if there are any questions regarding the project.
Summary of Commitments There are no new commitments or revisions to existing commitments in this letter.
Dennis L. Koehl Site Vice-President, Point Beach Nuclear Plant Nuclear Management Company, LLC cc:
Document Control Desk NRR Project Manager, Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, Wisconsin 54241-9516 Telephone: 920.755.2321