| | Title | Significance | Cross cutting aspect |
|---|
| 05000259/FIN-2013011-01 | Failure to Perform Evaluation of Nonconforming Material during Commercial Grade Dedication of Safety-Related Bearings | Green | H.14 |
| 05000259/FIN-2013011-02 | Failure to Follow Procedure during Implementation of Plant Modifications to the Residual Heat Removal and Core Spray Systems | Green | H.5 |
| 05000259/FIN-2013011-03 | Failure to Perform 10 CFR 50.59 Evaluation Intergranular Stress Corrosion Cracking Examination on ASME Code Class 1 Piping Weld | Green | H.13 |
| 05000259/FIN-2013011-04 | Two BFN Assistant Unit Operators Closed and Danger Tagged the A1 RHRSW Pump Manual Discharge Valve Instead of the Required A2 RHRSW Pump Discharge Valve | Green | H.12 |
| 05000259/FIN-2013011-05 | Maintenance Personnel Not Following Clearance Procedure Violation | Green | H.7 |
| 05000259/FIN-2013011-06 | Conduct of Operations Procedure Violation | Green | H.5 |
| 05000259/FIN-2013011-07 | Failure to Adequately Implement Procedure 3-SR-3.3.8.2.1(B) | Green | H.8 |
| 05000259/FIN-2013011-08 | Failure to Manage Emergent Risk Condition during A1 and A2 RHRSW Inoperability | Green | H.5 |
| 05000259/FIN-2013011-09 | Failure to control a modification to the seismically mounted control room ceiling light diffusers | Green | H.8 |
| 05000259/FIN-2013011-10 | Requirements for Concurrent Verification, Independent Verification, and Peer Checks | Green | H.7 |
| 05000259/FIN-2013011-11 | Inadequate Corrective Actions to Address Programmatic Procedure Quality Issue | Green | P.2 |
| 05000259/FIN-2013011-12 | Deficient Acceptance Criteria for Main Battery Bank 1 | Green | H.7 |
| 05000259/FIN-2013011-13 | Failure To Translate The Design Into Procedure 3-SR-3.3.8.2.1(B) | Green | |
| 05000259/FIN-2013011-14 | Failure to Implement an Adequate Test Program for RHRSWS and EECS | Green | P.2 |
| 05000259/FIN-2013011-15 | Deficient Design Control for RHR Service Water Freeze Protection | Green | P.1 |
| 05000259/FIN-2013011-16 | Failure to Establish Qualified Ultrasonic Examination Procedures | Green | P.5 |