- 1 NbRs 3 R::GULTRY *FORMATION DISTRIBUTION SY*-M (RIDS)
~
ACCESSION NbR;8308310221 DOC.DATE: 83/08/29 NOTARIZED: NO DOCKET #
FACIC:50-361 San Onotre Nuclear Station, Unit 2, Southern Californ 05000361 50*362 San OnofreNucqlear Station, Unit 3, Sovthern Californ 05000362 AUTH.qNAME AUTHOR AFFILIATION BASKINK.P.
Southern California Edison Co, RECIPNAMt RECIPIENTLAFFILIATION
- DENJUNHR, Office of Nuclear Reactor Regulation, Director
SUBJECT:
Forwards "Plant Operations Personnel Review," detailing results of plant operations personnel review committee review & recommendations on how licensee mgt can assist i improving effeciiveness of operations personne, Sw DISTRIBUTIUN CODE: M003S COPIES RECEIVED:LT L
R. /
Ez TITLE: Operator Requalification Program NOTES:J Hanchett Icy PDR Documents, ELD Chandler icy, 05000361 J Hanchett Icy POR Documents. ELD Chandler icy.
05000362 RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL NRR L53 BC 1
ROODH.
1 4
INTERNAL: NRH/DHFS/OLB 01 2
REG)FILE 04 1
1 RGN5 1
1 EXTERNAL: ACRS 08 10 10 INPO4STARNES 1
LPDR 03 1
1 NRC PDR 02 1.
NSIC OS 1
NTIS 1
1 NOTES:
4 2
TOTAL NUMBER OF COPIES REWUIRED: IVTTR 23 ENCL whb
Southern California Edison Company P. 0.
BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD.
CALIFORNIA 91770 K. P. BASKIN Ags29183TELEPHONE MANAGER OF NUCLEAR ENGINEERING, August 29, 1983 572-1401 SAFETY, AND LICENSING Mr. Harold Denton Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:
Subject:
Docket No. 50-362 San Onofre Nuclear Generating Station Unit 3 By letter dated November 15, 1982, Southern California Edison Company (SCE) advised the NRC of its plans to establish a committee to review and evaluate the staffing and training of operations personnel at San Onofre, Unit 3. The enclosed report details the results of the Plant Operations Personnel Review Committee's (POPRC) review including conclusions and recommendations on how SCE management can assist in improving the overall effectiveness of the Unit 3 operations staff.
The POPRC was composed of five professionals, four of whom were independent of SCE's operating staff. Mr. Ben C. Rusche of Management Analysis Company was retained by SCE to actively participate in the POPRC's review. The services of appropriately qualified non-members were used as necessary to provide supplementary technical expertise.
The review was conducted by developing an action plan as described in SCE's submittal of December 28, 1982. The action plan provided a basis for evaluating the readiness of plant operations personnel in terms of certain defined parameters.
The POPRC recommended that six items receive management attention and further action.
They are:
- 1. Adherence to procedures should be continually emphasized. The POPRC felt that continual emphasis was appropriate to maintain the current high standard of care necessary to assure the safe operation of the plant.
- 2. The computer based surveillance program presently used in some station divisions for preventive maintenance and Technical Specification surveillance should be implemented for all station departments to improve adherence to surveillance schedules.
8308310221 830829 PDR ADOCK 05000361 P
Mr. Harold Denton August 29, 1983
- 3. The administrative training requirements in the senior reactor operator training program should include the delineation of job responsibilities for other operator classifications.
- 4. Stress management training for reactor operators should be upgraded to equal that for senior reactor operators.
- 5. A program to improve communications between the shift staff and station management should be instituted.
- 6. Additional supervisory skills training should be provided to operations supervisors.
SCE has taken the following steps to implement the POPRC recommendations:
- 1. Adherence to procedures has been emphasized by station directives.
Station division managers continually emphasize this point to their employees.
- 2. SCE has implemented the San Onofre Maintenance Management System (SOMMS) within the Maintenance and Instrumentation and Control Divisions. SOMMS will be made available to other divisions to assist in meeting surveillance schedules. This system combines the plant data base, surveillance plan, preventive maintenance planning, and the execution of surveillance activities into a single computer-based system.
- 3. Administrative training requirements in the senior reactor operator training program include the delineation of job responsibilities for other operator classifications.
- 4. Stress management training for reactor operators has been upgraded to the level of that for senior reactor operators.
5&6. To improve shift communications, the Operations Division has instituted an expanded thirty minute shift turnover session.
The incoming shift meets as a group first with the offgoing shift supervisor. Items discussed are:
- a. Events that have occurred since the time this shift was on duty;
- b. Particular problems encountered in Unit operations;
- c. New special orders or changes to procedures; and
- d. Other general information important to operators.
Following this meeting, the conventional "one on one" shift turnover operation is conducted in the Control Room.
Mr. Harold Denton August 29, 1983 Additional supervisory skills training'will be provided for Operations Supervisors.
Further, the Station Operations Division has instituted an organizational development program structured through the use of an outside consultant.
Initially, each shift is rotated through the program twice. Thereafter, shift supervision and station management will meet on a periodic basis to discuss any perceived dissatisfaction with shift working conditions and to recommend improvements to maintain a highly motivated nuclear work force.
SCE had originally intended to submit the POPRC report in March 1983.
However, submittal of the report was delayed to provide the POPRC an opportunity to review the results of a study conducted by Management Analysis Company (MAC) and documented in "Recommendations for Improvement of the Operation of San Onofre Nuclear Generating Station, Units 2 and 3", dated June 1983. The POPRC's comparison of their report with the MAC report is provided in the attached "San Onofre Nuclear Generating Station, Units 2 & 3, Supplement, Plant Operating Personnel Review, August 1983".
The conclusion of this supplement is that there are no conflicts between the two reports.
If you have any questions concerning this matter, please contact me.
Very truly yours, Enclosure cc:
Mr. H. Rood, Project Manager Licensing Branch No. 3