Letter Sequence Request |
|---|
EPID:L-2018-RNW-0023, Regarding Windblown Debris Caused Transformer Fault Resulting in Auto-Start of Emergency Diesel Generator (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML18297A045, ML18319A184, ML18319A252, ML18320A236, ML18340A266, ML18340A267, ML18345A244, ML18351A051, ML19015A243, ML19044A556, ML19044A659, ML19046A433, ML19098A810, ML19100A254, ML19106A416, ML19107A021, ML19128A079, ML19140A449, ML19169A329, ML19206A651, ML19248C228, ML19253C753, ML19270E741, ML19316A834, ML19360A020, NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent
|
MONTHYEARML18121A0342018-03-29029 March 2018 Possible Topics for the April 17, 2018 Public Meeting with Dominion on Its Surry SLRA Project stage: Request ML18102A5692018-04-17017 April 2018 Dominions Presentation on Surrys SLRA Safety Meeting-Final (for April 17, 2018) Project stage: Request ML18129A3142018-05-16016 May 2018 Summary of Pre-Application Meeting with Dominion Energy Regarding the Surry, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML18291A8362018-06-30030 June 2018 Enclosure 4, Attachment 1: ANP-3679NP, Revision 0, Topical Report Project stage: Request ML18291A8342018-10-15015 October 2018 Appendix E - Environmental Report Project stage: Request ML18291A8352018-10-15015 October 2018 Submittal of Application for Subsequent Renewed Operating Licenses Project stage: Request ML18297A0932018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Request ML18297A0452018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18319A2522018-11-16016 November 2018 Subsequent License Renewal Application Online Reference Portal Project stage: Other ML18319A1842018-11-26026 November 2018 Plan for the Operating Experience Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RWN-0023 and L-2018-RNW-0024 Project stage: Other ML18320A2352018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing FRN - v2 Project stage: Request ML18320A2362018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing Letter - v3 Project stage: Other 05000280/LER-2018-002, Regarding Windblown Debris Caused Transformer Fault Resulting in Auto-Start of Emergency Diesel Generator2018-12-10010 December 2018 Regarding Windblown Debris Caused Transformer Fault Resulting in Auto-Start of Emergency Diesel Generator Project stage: Request NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent2018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice Project stage: Other ML18345A2442018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Companys Application for Subsequent Licen Project stage: Other ML18340A2652018-12-17017 December 2018, 21 December 2018 Notice of Intent to Prepare an Enviromental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML18340A2672018-12-17017 December 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18351A0512018-12-18018 December 2018 Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Companys Application for Subsequent License Renewal Project stage: Other ML19046A0092018-12-20020 December 2018 Comment (10) from Bettina Rayfield on Surry Power Station, Unit Nos. 1 and 2 Relicensing Project stage: Request ML18351A2572018-12-20020 December 2018 U.S. Nuclear Regulatory Commission Approval of Virginia Electric and Power Companys Request for Withholding Information from Public Disclosure, Regarding the Application for Subsequent License Renewal of Surry Power Station, Unit Nos. 1 and Project stage: Withholding Request Acceptance ML18340A2662018-12-21021 December 2018 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML19024A1992019-01-0808 January 2019 Subsequent License Renewal Scoping Meeting Surry Power Station Units 1 and 2 Project stage: Meeting ML19016A0932019-01-12012 January 2019 Comment (1) of Erica Gray on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1542019-01-13013 January 2019 Comment (9) of W. Frank Adams on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0962019-01-14014 January 2019 Comment (3) of Kay Patrick on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0942019-01-14014 January 2019 Comment (2) of Scott Burger on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19017A0132019-01-16016 January 2019 Comment (4) of Anonymous Individual on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Units 1 and 2 Project stage: Request ML19025A1462019-01-20020 January 2019 Comment (5) of David Martin on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1492019-01-21021 January 2019 Comment (6) of Glen Besa on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19015A2432019-01-22022 January 2019 Plan for the In-Office Regulatory Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML19025A1502019-01-22022 January 2019 Comment (7) of Scott Price on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1522019-01-22022 January 2019 Comment (8) of Randal Owen on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19042A1372019-01-29029 January 2019 Submittal of Supplement to Subsequent License Renewal Operating Licenses Application for Sufficiency Review Change Notice 1 Project stage: Supplement NRC-2018-0280, Comment (11) of Amy Ewing on Surry Relicensing, Scoping Comments: NRC-2018-0280 (Esslog 38468)2019-02-14014 February 2019 Comment (11) of Amy Ewing on Surry Relicensing, Scoping Comments: NRC-2018-0280 (Esslog 38468) Project stage: Request ML19046A4332019-03-0404 March 2019 Report for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML19044A6592019-03-0404 March 2019 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Surry Power Station, Unit Nos. 1 and 2, Subsequent License Renewal Application Project stage: Other ML19044A5562019-03-0404 March 2019 License Renewal Environmental Site Audit Plan Regarding the Surry Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Other ML19095A5972019-04-0202 April 2019 Submittal of Supplement to Subsequent License Renewal Application Change Notice 2 Project stage: Supplement ML19095A6002019-04-0202 April 2019 Enclosure 1 - Topics That Require a SLRA Supplement Project stage: Request ML19095A6022019-04-0202 April 2019 Enclosure 2 - SLRA Mark-Ups Change Notice 2 Project stage: Request ML19114A4352019-04-11011 April 2019 RAIs 4-4-19 r3 Project stage: RAI ML19106A4022019-04-11011 April 2019 Request for Additional Information Set 1 - Surry SLRA Environmental Review Project stage: RAI ML19107A0202019-04-16016 April 2019 Audit Need Update Tracking Spreadsheet Project stage: Request ML19107A0192019-04-16016 April 2019, 29 April 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Request ML19098A8102019-04-17017 April 2019 On-Site Regulatory Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML19106A4162019-04-25025 April 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19100A2542019-04-29029 April 2019 Schedule Revision for the Subsequent License Renewal Application Review Project stage: Other ML19107A0212019-04-29029 April 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Other ML19148A4412019-05-10010 May 2019 Response to Requests for Additional Information Set 1 - Regarding Environmental Review Project stage: Request ML19128A0792019-05-30030 May 2019 Report for the in Office Regulatory Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024 Project stage: Other 2019-01-13
[Table View] |
Similar Documents at Surry |
|---|
|
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-280 and 50-281; NRC-2018-0280]
Virginia Electric and Power Company; Dominion Energy Virginia:
Surry Power Station, Unit Nos. 1 and 2 AGENCY: Nuclear Regulatory Commission.
ACTION: Draft supplemental environmental impact statement; request for comment.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment draft plant-specific Supplement 6, Second Renewal, to the Generic Environmental Impact Statement (GEIS) for License Renewal of Nuclear Plants, NUREG-1437, regarding the subsequent renewal of Facility Operating License Nos.
DPR-32 and DPR-37 for an additional 20 years of operation for Surry Power Station, Unit Nos. 1 and 2 (Surry). The Surry facility is located in Surry County, Virginia.
Possible alternatives to the proposed action (subsequent license renewal) include no action and reasonable replacement power alternatives.
DATES: The staff will hold a webinar on the draft Environmental Impact Statement in November, including a presentation on the preliminary findings and a transcribed public comment session. The webinar details will be announced in the near future. Submit either electronic or written comments by December 10, 2019. Comments received after this date will be considered, if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.
ADDRESSES: You may submit comments by any of the following methods:
Federal Rulemaking Web Site: Go to https://www.regulations.gov/ and search for Docket ID NRC-2018-0280. Address questions about NRC docket IDs to
2 Anne Frost; telephone: 301-287-9232; e-mail: Anne.Frost@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
Mail comments to: Office of Administration, Mail Stop: TWFN-7-A60M, ATTN: Program Management, Announcements and Editing Staff, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
For additional direction on obtaining information and submitting comments, see Obtaining Information and Submitting Comments in the SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Tam Tran, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3617; e-mail: Tam.Tran@nrc.gov.
SUPPLEMENTARY INFORMATION:
I.
Obtaining Information and Submitting Comments A. Obtaining Information Please refer to Docket ID NRC-2018-0280 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document by any of the following methods:
Federal Rulemaking Web Site: Go to https://www.regulations.gov/ and search for Docket ID NRC-2018-0280.
3 NRCs Agencywide Documents Access and Management System (ADAMS): You may access publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that the document is referenced here. Draft plant-specific Supplement 6, Second Renewal, to the GEIS for License Renewal of Nuclear Plants, NUREG-1437, is available in ADAMS under Accession No. ML19274C676.
NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
Library: A copy of draft plant-specific Supplement 6, Second Renewal, to the GEIS for License Renewal of Nuclear Plants, NUREG-1437, is available at the following location: Williamsburg Regional Library, 515 Scotland St., Williamsburg, VA 23185.
B. Submitting Comments Please include Docket ID NRC-2018-0280 in the subject line of your comment submission, in order to ensure that the NRC is able to make your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact information in comment submissions that you do not want to be publicly disclosed. The NRC will post all comment submissions at https://www.regulations.gov/ as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to
4 remove identifying or contact information.
If you are requesting or aggregating comments from other persons for submission to the NRC, you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS.
II.
Discussion The NRC is issuing for public comment draft plant-specific Supplement 6, Second Renewal, to the GEIS for License Renewal of Nuclear Plants, NUREG-1437, regarding the subsequent renewal of Facility Operating License Nos. DPR-32 and DPR-37 for an additional 20 years of operation for Surry, Unit Nos. 1 and 2. Draft plant-specific Supplement 6, Second Renewal, to the GEIS includes the preliminary analysis that evaluates the environmental impacts of the proposed action and alternatives to the proposed action. The NRCs preliminary recommendation is that the adverse environmental impacts of subsequent license renewal for Surry are not so great that preserving the option of subsequent license renewal for energy-planning decisionmakers would be unreasonable.
Dated at Rockville, Maryland, this 17th day of October, 2019.
For the Nuclear Regulatory Commission.
/RA/
John Tappert, Director, Division of Rulemaking, Environmental, and Financial Support, Office of Nuclear Material Safety and Safeguards.