Schedule Revision for the Subsequent License Renewal Application Review
ML19316A834
Person / Time
Site: Surry  Dominion icon.png
Issue date: 11/27/2019
From: Eric Oesterle
NRC/NRR/DNRL/NLRP
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
Gibson L, NRR-DNRL 415-1056
References
EPID L-2018-RNW-0024
Download: ML19316A834 (4)


Text

November 27, 2019 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Blvd Glen Allen, VA 29060

SUBJECT:

SURRY POWER STATION, UNIT NOS. 1 AND 2 - SCHEDULE REVISION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NO.

L-2018-RNW-0024)

Dear Mr. Stoddard:

By letter dated October 15, 2018 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML18291A842), as supplemented by letters dated January 29, 2019 (ADAMS Accession No. ML19042A137), and April 2, 2019 (ADAMS Accession No. ML19095A666), Virginia Electric and Power Company (Dominion) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-32 and DPR-37 for the Surry Power Station, Unit Nos. 1 and 2, respectively (Surry). Dominion submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

The purpose of this letter is to inform you that, while the overall review schedule for the Surry subsequent license renewal application remains June 2020, the safety review schedule will be slightly modified. The scheduled date for Issue Safety Evaluation Report (SER) is being revised from November 2019 to December 2019 to support closure of the final review aspects.

This change to an interim milestone will not affect the February 2020 schedule for the ACRS Subcommittee on Plant License Renewal. The NRC staff understands, through discussions with your staff, that Dominion has no objection to this safety review schedule change. The enclosure of this letter provides the staffs revised review schedule for the Surry subsequent license renewal application.

If you have any questions related to this safety review schedule, please contact Angela Wu at 301-415-2995 or Angela.Wu@nrc.gov or Lauren Gibson at 301-415-1056 or Lauren.Gibson@nc.gov.

Sincerely,

/RA/

Eric. R. Oesterle, Chief License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281

Enclosure:

Surry SLRA Revised Review Schedule cc w/encl: Listserv

ML19316A834

  • concurred by email OFFICE PM:NLRP:DNRL LA:NLRP:DNRL PM:NLRP:DNRL D:DNRL NAME LGibson SLent AWu(LGibson for)

ABradford DATE 11/19/19 11/19/19 11/19/19 11/27/19 OFFICE BC:NLRP:DNRL NAME EOesterle DATE 11/27/19

Enclosure SURRY POWER STATION, UNIT NOS. 1 AND 2 Revised Subsequent License Renewal Application Review Schedule Milestone Schedule Actual Receive Subsequent License Renewal Application (SLRA) 10/2018 10/15/2018 Publish Federal Register Notice (FRN) - LRA Availability 11/2018 11/01/2018 Publish FRN - Docketing Acceptance/Rejection and Opportunity for Hearing 12/2018 12/10/2018 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 12/2018 12/20/2018 Public Meeting - Overview of Subsequent License Renewal Process and Environmental Scoping 1/2019 1/8/2019 Environmental Scoping Period Ends 2/2019 1/22/2019 Deadline for Filing Hearing Requests and Petitions for Intervention 2/2019 2/15/2019 Issue Draft Supplemental Environmental Impact Statement (DSEIS) 10/2019 10/17/2019 Public Meeting - Draft SEIS Meeting (webinar) 11/2019 11/7/2019 End of DSEIS Comment Period 12/2019 Issue Safety Evaluation Report (SER) 12/2019 Advisory Committee on Reactor Safeguards (ACRS)

Subcommittee Meeting 2/2020 Issue Final SEIS 4/2020 U.S. Environmental Protection Agency FRN Published

- Availability of Final SEIS 4/2020 ACRS Full Committee Meeting 4/2020 Decision - Director, NRR 6/2020