RIS 2015-05, Withdrawn NRC Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations

From kanterella
Revision as of 21:44, 5 March 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Withdrawn NRC Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations
ML15062A568
Person / Time
Issue date: 04/20/2015
From: Cheok M C, Kokajko L E
Division of Construction Inspection and Operational Programs, Division of Policy and Rulemaking
To:
Revelle C R
References
RIS-15-005
Download: ML15062A568 (6)


Withdrawn NRC Regulatory Issue Summary (RIS) 2015-05, "Preparation and Scheduling of Operator Licensing Examinations," dated April 20, 2015 (ADAMS Accession No. ML15062A568), has been withdrawn and superseded by RIS 2016-09 (ADAMS Accession No. ML16116A275).

ML15062A568 April 20, 2015 NRC REGULATORY ISSUE SUMMARY 2015-05 PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS

ADDRESSEES

All holders of, or applicants for, a power reactor operating license or construction permit under Title 10 of the Code of Federal Regulations (10 CFR) Part 50, "Domestic Licensing of Production and Utilization Facilities," except those that have certified that they have permanently ceased operations and fuel has been permanently removed from the reactor vesse All holders of, or applicants for, a power reactor early site permit or a combined license under 10 CFR Part 52, "Licenses, Certifications, and Approvals for Nuclear Power Plants."

INTENT

The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS) to inform addressees of NRC staff's need for updated information on projected site-specific operator licensing examination schedules, as well as on the estimated number of applicants planning to take operator licensing examinations and the NRC's generic fundamentals examinations (GFEs). This information will help the NRC to plan its resources more effectively. This RIS requires no action or written response on the part of addressee Addressee actions to collect and transmit the information requested are strictly voluntar

BACKGROUND INFORMATION

Subpart E, "Written Examinations and Operating Tests," of 10 CFR Part 55, "Operators' Licenses," contains the relevant NRC regulation In particular, 10 CFR 55.40, "Implementation," permits nuclear power reactor facility licensees to prepare, proctor, and grade the written examinations required by 10 CFR 55.41, "Written examination: Operators," and 10 CFR 55.43, "Written examination: Senior operators," subject to certain condition Under 10 CFR 55.40, facility licensees may also prepare the NRC-administered operating tests required by 10 CFR 55.45, "Operating tests." Under 10 CFR 55.40(c), facility licensees that choose not to prepare their own examinations and operating tests must request in writing that the NRC prepare the examinations and operating test In RIS 2014-05, "Preparation and Scheduling of Operator Licensing Examinations," dated April 29, 2014, the NRC asked power reactor licensees to voluntarily submit proposed schedules of examinations they intended to prepare and to estimate the number of applicants to be tested for on-site examinations and GFEs in calendar years (CYs) 2016 through 201 This RIS requests that licensees voluntarily update examination schedules and applicant estimates for CYs 2017 through 202

SUMMARY OF THE ISSUE

The NRC uses nearly twice as many resources to prepare an examination as to review, approve, administer, and document a licensee-prepared examinatio The number of examinations administered by licensees fluctuates annuall Consequently, the NRC has found it helpful to request an annual update of the operator licensing examination needs of power reactor facility licensee Moreover, with the anticipated number of new operator positions that will need to be filled for new plants, the differences in upcoming years could be significan Therefore, the NRC requests that licensees evaluate their responses to this RIS in this light, particularly for the later year The update should estimate the number of applicants to be examined and should indicate if the licensee or the NRC will prepare the exa In their responses, those utilities not planning to construct a new plant should consider the effect of licensed operators moving between utilities to fill the anticipated openings in the futur This information will help the NRC budget its resource The NRC regional offices will continue to coordinate specific examination dates with the training managers of affected facility licensee The NRC requests that each licensee provide the following information using NRC Form 536, "Operator Licensing Examination Data." (NRC Form 536 is available on the NRC Web site at http://www.nrc.gov/reading-rm/doc-collections/forms/.)

A. Proposed Examination Preparation Schedule Licensees should estimate the number of examinations they intend to prepare, and the number of examinations they will request the NRC to prepare during CYs 2017 through 202 For examinations that facility licensees will prepare, the NRC will assume that each examination includes the required outline, the written examination, and the operating test, unless the licensee specifies otherwis Joint NRC and licensee examination development is permitted and should be coordinated with the NRC regional offic Licensees should notify the applicable NRC regional office, by letter, of any required schedule changes that arise after submission of the RIS response for agreement to, and coordination of, changes to examination administratio B. Initial Operator License Examinations For each desired examination, estimate the number of applicants to be tested and enter the proposed primary and alternate dates of the examinatio If requesting more than one examination per calendar year, fill in the applicable columns as appropriate through CY 202 C. Proposed Generic Fundamentals Examination Schedule Estimate by month the number of applicants planned to take the GFE in CYs 2017 and 201 As requested by industry, the NRC administers the GFE four times per yea

VOLUNTARY RESPONSE

The NRC asks addressees choosing to submit the information requested in NRC Form 536 to do so within 30 days of receiving this RI Direct responses to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, and send a copy of the response to the applicable regional offic Responses may be submitted electronicall BACKFITTING AND ISSUE FINALITY This RIS requests the addressees to inform the NRC of the dates and number of operator-licensing examinations and the NRC's generic fundamentals examinations in CY 2017-2020 and whether the licensee or the NRC will prepare the exam The RIS requires no action or written respons Any action on the part of addressees to collect and transmit operator-licensing examination data in accordance with the request contained in this RIS is strictly voluntar Therefore, this RIS does not represent backfitting as defined in 10 CFR 50 109(a)(1), nor is it otherwise inconsistent with any issue finality provision in 10 CFR Part 5 Consequently, the NRC staff did not perform a backfit analysis for this RIS or further address the issue finality criteria in Part 5

FEDERAL REGISTER NOTIFICATION

The NRC did not publish in the Federal Register a notice of opportunity for public comment on this RIS because it concerns an administrative aspect of the regulatory process that involves the voluntary submission of information on the part of addressee

CONGRESSIONAL REVIEW ACT

This RIS is not a rule as defined in the Congressional Review Act (5 U.S.C. §§ 801-808).

PAPERWORK REDUCTION ACT STATEMENT

This RIS contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB) approved these information collections, approval number 3150-013 The burden to the public for these information collections is estimated to average 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collectio Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control numbe /RA/ /RA/ Michael C. Cheok, Director Lawrence E. Kokajko, Director Division of Construction Inspection Division of Policy and Rulemaking Operational Programs Office of Nuclear Reactor Regulation Office of New Reactors

CONTACT

Please direct any questions about this matter to the technical contacts listed belo Technical Contacts: Scott Sloan, NRR Michael Junge, NRO 301-415-3254 301-415-7745 E-mail: scott.sloan@nrc.gov E-mail: michael.junge@nrc.gov Donald Jackson, RI Gerald McCoy, RII 610-337-5306 404-997-4551 E-mail: donald.jackson@nrc.gov E-mail: gerald.mccoy.@nrc.gov Hironori Peterson, RIII Eugene Guthrie, RII 630-829-9707 404-997-4662 E-mail: hironori.peterson@nrc.gov E-mail: eugene.guthrie@nrc.gov Vincent Gaddy, RIV 817-200-1159 E-mail: vincent.gaddy@nrc.gov

CONTACT

Please direct any questions about this matter to the technical contacts listed belo Technical Contacts: Scott Sloan, NRR Michael Junge, NRO 301-415-3254 301-415-7745 E-mail: scott.sloan@nrc.gov E-mail: michael.junge@nrc.gov Donald Jackson, RI Gerald McCoy, RII 610-337-5306 404-997-4551 E-mail: donald.jackson@nrc.gov E-mail: gerald . mccoy.@nrc.gov Hironori Peterson, RIII Eugene Guthrie, RII 630-829-9707 404-997-4662 E-mail: hironori.peterson@nrc.gov E-mail: eugene.guthrie@nrc.gov Vincent Gaddy, RIV 817-200-1159 E-mail: vincent.gaddy@nrc.gov

ADAMS Accession No.: ML15062A568 TAC No. MF5807 OFFICE OLA:IOLB:DIRS Tech Editor C:IOLB:DIRS C:COLB:DCIP: NRO DD:DIRS:NRR D:DORL:NRR NAME CRevelle QTE SSloan MJunge AHowe MEvans DATE 03/06/2015 03/10/2015 03/12/2015 03/11/2015 03/12/2015 03/25/2015 OFFICE MA:PMDA:NRR OIS OGC LA:PGCB:DPR PM:PGCB:DPR C:PGCB:DPR NAME LHill TDonnell HBenowitz ELee AMarkley SStuchell DATE 03/16/2015 03/18/2015 04 /01/2015 04/07/2015 04/08 /2015 04/08/2015 OFFICE D:DCIP:NRO D:DPR:NRR NAME MCheok LKokajko DATE 04/17/2015 04/20/2015 OFFICIAL RECORD COPY