Monthly Operating Rept for Jul 1982
ML20071M056
Person / Time
Site: Ginna Constellation icon.png
Issue date: 08/06/1982
From: Mcnamara A
ROCHESTER GAS & ELECTRIC CORP.
To:
Shared Package
ML20071M040 List:
References
NUDOCS 8209240237
Download: ML20071M056 (5)


Text

.

A

. OPERATING DATA REPORP D0uurr NO.

50-244 DATE Augu_st,6, 1982 COMPLE*IED BY (m 3m_y* J,M---f_%

Andrew E. McNamara L

'IELEPIKNE 1 (315) 524-4446

~

OPERATING STA'IUS Ext. 293 or 501 at Ginna.

1. Unit Name: GINNA STATION, UNIT #1 Notes: %e reactor power level
2. Reporting Period: July, 1982 averaged 100% for the majority of the
3. Licensed hermal Power (PWt):

1520 report nonth, the exceptions being

4. Nameplate Rating (Gross MWe):

490 detailed on page 4.

5. Design Electrical Rating (Net MWe): 470
6. Maximum Dependable Capacity (Gross PMe): 490
7. Maximm Dependable Capacity (Net MWe):

470

8. If Changes Occur in Capacity Ratings (Items Ntaber 3 through 7) Since Last Repor.t, Give Reasons:
9. Power Level to Wich Restricted, If Any (Net PMe):
10. Reasons Ibr Restrictions, If Any:

h is Month Yr.-to-Date Ctmuulative

11. Ilours In Reporting Period 744 5,087 111,143.00
12. Ntaber of ikx1rs Reactor Was Critical 744 2,214.00 83,856.62
13. Reactor Reserve Shutdown flours 0

0 1,631.32*

14. Ilours Generator On-Line 744 2,145.00 81,9723T
15. Unit Reserve Shutdown flours 0

0

8. D
16. Gross h ermal Energy Generated (MMI) 1,118,424 3,165,480 112,071,034
17. Gross Electrical Energy Generated (MWil) 368,647 1,045,668 36,480,633
18. Net Electrical Energy Generated (MNEI) 350,580 994,363 34,572,436
19. Unit Service Factor 100%

42.17%

73.75%

20. Unit Availability Factor 100%

42.17%

73.76%

21. Unit Capacity Factor (Using POC Net) 100.3%

41.59%

68.80%

22. Unit Capacity Factor (Using DER Net) 100.3%

41.59%

68.80%

23. Unit Forced Gutage Rate 0%

23.60%

8.85%

24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

Steam Generator Inspection - 9/25/82. Duration - 3 weeks.

25. If Shutdown At Fnd Of Report Period, Estimated Date Of Startup:
26. Units In 'Ibst Status (Prior to Ccmuercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY C09ERCIAL OPFEATICN

  • Ctunulative 'Ibtal Commencing January 1,1975.

h 0

p R

/

' AVERAGE DAILY UNIT POWER LEVEL D00ET NO.

50-244 UNIT #1 Ginna Station IRTE Auoust_6, 1982 C01PIRIED BY diem 2_e 2. W F _ w Andrew E. McNamara

'IELEPHNE 1 (315) 524-4446 Ext. 293 or 501 at Ginna.

MONDI July, 1982 DAY AVERPGE DAILY POWER LEVEL DAY AVERAGE IRILY POWER LEVEL (MWe-Net)

(PWe-Net) 1.

481 17.

474 2.

479 18.

471

3.,

480 19.

469 4.

480 20.

470 5.

480 21.

471 6.

481 22.

469 7.

481 23.

468 8.

479 24.

469 9.

480 25.

385 10.

477 26.

467 11.

479 27.

467 12.

477 28.

470 13.

475 29.

468 14.

475 30.

469 15.

475 31.

470 16.

474 INSTRUCTIW S On this format, list the average daily unit power level in PMe-Net for each day in the reporting month. Capute to the nearest whole megawatt.

- s D00ET NO.

50-244 LNIT NAME il Ginna Station

[ NIT SIUTD01@i MD POWER REDUCTI(NS DME August 6, 1982 ONPLETED BY W E. A c 4.,__ _

Ardrew E. M$amara N REPORT MNIH July, 1982

'IELEPHONE 1 (315) 524-4446 Ext. 293 or 501 Ginna Method of Duration Reason Shutting Licensee System (baponent Cause & Corrective No.

Date Type 1 (Ikxirs) 2 Down Event Code 4 Code 5 Action to Reactor 3 Seport #

Prevent Recurrence P/R 07/25/82 S

7 B

('Ibrbin)

Reactor power level reduction to approximately 47% to perform a series of turbine valve and trip tests.

1 2

3 4

F: Forced Reason:

Method:

Exhibit G - Instructions S: Scheduled A-BNipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram.

Entry Sheets for Licensee C-Refueling 3-Automatic Scram.

Event Report (LER) File D-Regulatory Restriction 4-Other (Explain)

(10 REG-0161)

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain) 5 8

H-Other (Explain)

Exhibit 1 - Same Sour

e

- NARRATIVE SIDGERY OF OPERATING EXPERIDICE DOCET NO.

50-244 UNIT Ginna Station, Unit #1 IRTE August; 6, 1982 COMPLETED BY k-M W -j Andrew E. Mdiamara

'IELeffDfE 1 (315) 524-4446 Ext 293 or 501 Ginna.

M[Nni July, 1982 he reactor power level was maintained at 100% level for the majority of the report month.

We major exception was a power reduction to approximately 47% to perform a series of nonthly turbine valve and trip tests.

l l

l l

l l

l l

1 1

. GIftpL STATIQi Maintenance kport July, 1982 During July, routine maintenance and inspections were performed.

Major safety related maintenance incitded:

1.

Replacement of a leaking mechanical seal on one of the Residual Heat Removal Pumps.

2.

Venting twice of the reference leg of the pressurizer level instrtmentation after one channel drifted away from the other channels.

l l

[

i l

l L.

.