Forwards Plant ISI Exam Summary Rept for 1994 Refueling Outage
ML20080F668
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 01/20/1995
From: Hill W
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20080F673 List:
References
NUDOCS 9501300133
Download: ML20080F668 (3)


Text

,.

-,~

e Northem States Power Company Monticello Nuclear Generating Plant 2007 West Hwy 75 Montice:lo. Minnesota 55362-9637 January 20,1995 i

US Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 Inservice inspection (ISI) Examination Summary Report - Refuelino Outaae No.17 Enclosed for your information are four copies of the Inservice inspection (ISI) examination summary report for the 1994 Monticello refueling outage (Refueling Outage No.17). The 1994 outage represented the second inspection conducted for first period of Monticello's third 10-year ISI interval.

The enclosed report identifies components examined, the examination methods used, the examination number, and summarizes the results. The examination plan focused on: 1) the pressure retaining components and their supports associated with the reactor coolant system and associated syste,ns classified as ASME Classes 1 and 2,2) reactor vessel examination,

3) systein pressure testing, and 4) snubber inservice testing. All anomalies were either corrected or an engineering evaluation was performed to accept "as-is" conditions.

This letter contains no new NRC commitments, nor does it modify any prior commitments.

Please contact Mary Engen, Sr Licensing Engineer, at (612) 295-1291 if you require additional information.

jf)Il

/

't w'

William J Hill Manager Monticello Nuclear Generating Plant c: See next page l,

1/18/95 HsP H:OATA\\NRCCoRRRFo171S!

/[

t

}fl p

9501300133 950120

\\

s DR ADDCK 05000263 PDR

USNRC NORTHERN STATES POWER COMPANY January 20,1995 Page 2 c:

Regional Administrator-Ill, NRC (2 copies of attachment)

NRR Project Manager, NRC (w/o attachment)

Resident inspector, NRC (1 copy of attachment)

J Silberg (w/o attachment)

B Kubitshek, Chief Boiler inspector, State of MN (1 copy of attachment)

Paul Fisher, Hartford Ins. (1 copy of attachment) l Enclosure l

l i

TRANSMITTAL MANIFEST NORTHERN STATES POWER COMPANY NUCLEAR LICENSING DEPARTMENT MONTICELLO NUCLEAR GENERATING PLANT Inservice Inspection (ISI) Examination Summary Report - Refuelina Outaae No.17 Correspondence Date:

January 20,1995 Monticello Intemal Site Distribution Special Instructions Kaleen Hilsenhoff..... USAR File......

..Yes No x St:ve Ludders......... NRC Commitment....Yes No x Lila Imholt............. Monti OC Sec.........Yes No x - 10, No dist to OC members below if YES M:l Opstad............. Monti SAC Sec........Yes No x

-6

  1. Mail Room.......... Monti Posting........Yes__ No_x_ - 7 Monticello Intemal Site Distribution:
    • Monti Document Control File J C Grubb, NGSS, OC W J Hill, Plant MGR, SAC, OC L L Nolan, GSSA, OC C A Schibonski, GSE, OC B D Day, MGR MTC, OC M F Hammer, GSM, OC Operating Experience Coord J E Windschill, GSRS, OC W A Shamla, NQD M W Onnen, GSO, OC "Monti Site Lic File Alan Wojchouski

" Steve Ray, SR Res insp, NRC

" Dean Carstens NSP Intemal Distribution E L Watzl R O Anderson, Dir LMI, SAC "J L Ricker Communications Dept Yes_x_ No "M M Vik Extemal NSP Distribution

'W** Doc Control Desk NRC.-4 copies.of Encli Kris Sanda, State of Minn

" Regional Admin-lli,NRC - 2 copies of Enci J E Silberg, Beth Wetzel, NRR-PM, NRC "Minn State Boiler inspector

" Paul Fisher (Hartford Ins)

" Includes copies of the summary report, advance Distribution made by Site Licensing.

Manifest Date:

January 20,1995