Monthly Operating Repts for Dec 1995 for Vogtle Electric Generating Plant,Units 1 & 2
ML20096C305
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/31/1995
From: Hooper G, Mccoy C
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LCV-0564-L, LCV-564-L, NUDOCS 9601170223
Download: ML20096C305 (12)


Text

.. _.

Georga Power Company

)

40 invernew Center Park Aay Post ot'.ce 0o4 1295 frrg'ngtlam A!atama 35201 Tefedhone 205 877-7122

]

Georgia Power C.K.McCo)

Vce Prewlent. Nuclear VOQt\\Q pro ltKt Ut' Southern glCClfc SySlem j

January 8, 1996 LCV-0564-L Docket Nos. 50-424 j

S0-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT MONTHLY OPERATING REPORT Enclosed are the Decenber 1995, monthly operating reports for Vogtle Electric Generating Plant (VEGP) Units 1 and 2. These reports are submitted in accordance with i

Technical Specification 6.8.1.5.

Sincerely, C. K. McCoy CKM/JLL Enclosures cc:

Georgia Power Company Mr. J. B. Beasley, Jr.

Mr. M. Sheibani NORMS U. S. Nuclear Regulatory Commission Mr. S. D. Ebneter, Regional Administrator

- Mr. L. L. Wheeler, Licensing Project Manager, NRR Mr. C. R. Ogle, Senior Resident Inspector, Vogtle 9601170223 951231 PDR ADOCK 05000424 R

PDR

.17004g jp 4

ENCLOSURE 1 VOGTLE ELECTRIC GENERATING PLANT - UNIT I MONTHLY OPERATING REPORT FOR DECEMBER 1995 TABLE OF CONTENTS NARRATIVE REPORT Page VI-l OPERATING DATA REPORT Page VI-2 AVERAGE DAILY POWER LEVEL Page VI-3 UNIT SHUTDOWNS AND POWER REDUCTIONS Page VI-4 i

i I

NARRATIVE REPORT DOCKET NO. 50-424 UNIT 1 DATE:

JANUARY 2,1996 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 DECEMBER 01 00:00 UNIT 1 AT 100% POWER WITH NO OPERATIONAL PROBLEMS.

DECEMBER 31 23:59 UNIT 1 AT 100% POWER WITH NO OPERATIONAL PROBLEMS.

(

V1-1

OPERATING DATA REPORT DOCKET NO. 50-424 DATE:

JANUARY 2,1996 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706)8264104 OPERATING STATUS

1. UNIT NAME:

VEGP UNIT 1

2. REPORT PERIOD:

DECEMBER 1995

3. LICENSED THEF. MAL POWER (MWt):

3565

4. NAMEPLATE RATING (GROSS MWe):

1215

5. DESIGl.' ELECTRICAL RATING (NET MWe):

1169

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

1216

7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):

1162

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

NO RES * > 7TIONS

10. REASONS FOR RESTRICTION,IF ANY:

NA THIS MONTH YR. TO DATE CUMULATIVE

11. HO JRS IN REPORTING PERIOD:

744 8760 75265

12. NUMBER OF HOURS REACTOR WAS CRITICAL:

744.0 8701.6 66466.2

13. REACTOR RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

14. HOURS GENERATOR ON-LINE:

744.0 8621.6 65342.4

15. UNIT RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

16. GROSS THERMAL ENERGY GENERAT ED (MWH):

2650729 30608433 221401734

17. GROSS ELEC. ENERGY GENERATED (MWH):

917302 10445840 74672527

18. NET ELEC. ENERGY GENERATED (MWH):

878122 9983960 71042407

19. REACTOR SERVICE FACTOR 100.0 %

99.3 %

88.3 %

20. REACTOR AVAILABILITY FACTOR 100.0w 99.3 %

88.3 %

21. UNIT SERVICE FACTOR:

100.0 %

98.4 %

86.8%

22. UN8T AVAILABILITY FACTOR:

100.0 %

98.4 %

86.8 %

23. UNIT CAPACITY FACTOR (USING MDC NET):

101.6 %

98.1 %

84.8 %

24. UNIT CAPACITY FACTOR (USING DER NET):

101.0 %

97.5 %

84.2 %

25. UNIT FORCED OUTAGE RATE:

0.0%

0.S%

4.4%

26. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

REFUELING,03/03/96,31 DAYS

27. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

NA V1-2

~

UNIT 1 AVERAGE DAILY DOCKET NO. 50-424 l

1 POWER LEVEL DATE:

JANUARY 2,1996 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826 4 104 DAY Net MW 1...............

1178

  • 2....

1178

  • 3..

1177

  • 4..

1175

  • 5.

1176

  • 6...

1179

  • 7.............

1181

  • 8..................

1185

  • 9...

1184

  • 10.

1186 *

11...

1185

  • 12...........

1182

  • 13..

1181

  • 14.

i ic '

  • 15..

16......

1167

  • 17................

1179

  • 18.........

1182

  • 19....

1175

  • 20..............

1183

  • 21...............

1185

  • 22..._......

1186

  • 23.

1186

  • 24................

1186

  • 25.

1184

  • 2 6..........

1183

  • 27...

1183

  • 28.

1184

  • 2 9........

1183

  • 30...

1180

  • 31......

1178 *

  • MDC CAN BE EXCEEDED UNDER OPTIMAL CONDITIONS V1-3

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-424 DATE:

JANUARY 2,1996 i

UNIT NAME:

VEGP UNIT 1 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 4

REPORT MONTH DECEMBER 1995 R

M S

E E

Y T

A T

LICENSEE SC Y

S H

EVENT TO COMPONENY CAUSE & CORP.CCTIVE P

DURATION O

O REPORT ED CODE ACTION TO I

NO.

DATE E

(HOURS)

N D

NUMBER ME (SUBCODE)

PREVENT RECURRENCE NA NA NA N/.

NA NA NA NA NA NA l

F: FORCED REASON:

METHOD:

EVENTS REPORTED INVOLVE S: SCHEDULED A-EQU!PMENT FAILURE (EXPLA)N) 1 - MANUAL A GREATER THAN 20%

B-MAINTENANCE OR TEST 2 - MANUAL SCRAM REDUCTION IN AVERAGE C-REFUELING 3 - AUTO. SCRAM DAILY POWER LEVEL FOR D-REGULATORY RESTRICTION 4 - CONTINUATIONS THE PRECEDING 24 HOURS.

E-OPERATOR TRAINING & LICENSE 5 - LOAD REDUCTION F-ADMINISTRATIVE 9 - OTHER (EXPLAIN)

G-OPERATIONAL ERROR (EXPLAIN)

H-OTHER (EXPLAIN) l V1-4

i

{

ENCLOSURE 2 VOGTLE ELECTRIC GENERATING PLANT - UNIT 2 MONTHLY OPERATING REPORT FOR DECEMBER 1995 TABLE OF CONTENTS NARRATIVE REPORT Page V2-1 OPERATING DATA REPORT Page V2-2 i

AVERAGE DAILY POWER LEVEL Page V2-3 UNIT SHUTDOWNS AND POWER REDUCTIONS Page V2-4

NARRATIVE REPORT DOCKET NO. 50-425 UNIT 2 DATE:

JANUARY 2,1996 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 DECEMBER 01 00:00 UNIT 2 AT 100% POWER WITH NO OPERATIONAL PROBLEMS.

DECEMBER 02 04:00 UNIT 2 BEGAN DERATE TO 60% POWER TO REPAIR LEAK ON ISOPHASE BUS DUCT COOLER.

DECEMBER 02 18:44 UNIT 2 RETURNED TO 100% POWER.

DECEMBER 31 23:59 UNIT 2 AT 100% POWER WITH NO OPERATIONAL PROBLEMS.

V2-1 1

I i

OPERATING DATA REPORT DOCKET NO. 50-425 DATE:

JANUARY 2,1996 4

COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 OPERATING STATUS

1. UNIT NAME:

VEGP UNIT 2

2. REPORT PERIOD:

DECEMBER 1995

3. LICENSED THERMAL POWER (MWt):

3565

4. NAMEPLATE RATING (GROSS MWe):

1215

5. DESIGN ELECTRICAL RATING (NET MWe):

1169

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

1216 1

7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):

1162

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

NO RESTRICTIONS

10. REASONS FOR RESTRICTION, IF ANY:

NA THIS MONTH YR. TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD:

744 8760 58009

12. NUMBER OF HOURS REACTOR WAS CRITICAL:

744.0 7968.8 52116.5

13. REACTOR RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

14. HOURS GENERATOR ON-LINE:

744.0 7909.3 51499.5

15. UNIT RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

16. GROSS THERMAL ENERGY GENERATED (MWH):

2624729 21895487 173454115

17. GROSS ELEC. ENERGY GENERATED (MWH):

913303 9574606 59023302

18. NET ELEC. ENERGY GENERATED (MWH):

875683 9159186 56238262

19. REACTOR SERVICE FACTOR 100.0 %

91.0 %

89.8 %

20. REACTOR AVAILABILITY FACTOR 100.0 %

91.0 %

89.8 %

)

21. UNIT SERVICE FACTOR:

100.0 %

90.3 %

88.8 %

22. UNIT AVAILABILITY FACTOR:

100.0 %

90.3 %

88.8 %

23. UNIT CAPACITY FACTOR (USING MDC NET):

101.3 %

90.0 %

86.1 %

24. UNIT CAPACITY FACTOR (USING DER NET):

100.7 %

89.4 %

86.1 %

25. UNIT FORCED OUTAGE RATE:

0.0%

0.5%

1.9%

26. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

NONE

27. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP :

NA V2-2

_ _ _. = _. _. _ _.. _ _

. _ _ _.. ~ _..... _ _ _ _ _ _.

l' *

~

l UNIT 2 AVERAGE DAILY DOCKET NO. 50-425 1

POWER LEVEL DATE:

JANUARY 2,1996 1

4.

COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 A

DAY Net MW 1.

1191

  • 4 2..

839 i

3.............

1128 1

4.....

1183

  • 1 j

5............

1183

  • 1 6..............

1186

  • 7......

1187

  • 8..........

1192

  • 9........

1191

  • a 10....

1194

  • 1 1............

1194

  • l 12...

1195

  • 13..................

1187

  • 14..

1188

  • l j

15..

1182

  • 16.

1181

  • i 17..

1191

  • 18.

1190

  • 19......

1182

  • 20.........

1192

  • 1 21.

1193

  • 4 l

22.......

1194

  • 4 23...

1194 *

)

24.......

1194

  • 25.

1192

  • 26....

1195

  • 27..........

1196

  • 28.

1196

  • 29.

1195

  • 30.

1193

  • 31.

1191 *

  • MDC CAN BE EXCEEDED UNDER OPTIMAL CONDITIONS V2-3

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-425 DATE:

JANUARY 2,1996 UNIT NAME:

VEGP UNIT 2 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 REPORT MONTH DECEMBER 1995 R

M S

E E

Y T

A T

LICENSEE SC Y

S H

EVENT TO COMPONENT CAUSE & CORRECTIVE P

DURATION O

O REPORT ED CODE ACTION TO NO.

DATE E

(HOURS)

N D

NUMBER ME (SUBCODE)

PREVENT RECURRENCE 95-5 12-2 S

0 B

5 NA KG HX SEE BELOW F: FORCED REASON:

METHOD:

EVENTS REPORTED INVOLVE S: SCHEDULED A EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL A GREATER THAN 20%

B-MAINTENANCE OR TEST 2 - MANUAL SCRAM REDUCTION IN AVERAGE C-REFUELING 3 - AUTO. SCRAM DAILY POWER LEVEL FOR D-REGULATORY RESTRICTION 4 - CONTINUATIONS THE PRECEDING 24 HOURS.

E-OPERATOR TRAINING & LICENSE 5 - LOAD REDUCTION F-ADMINISTRATIVE 9 - OTHER (EXPLAIN)

G OPERATIONAL ERROR (EXPLAIN)

H-OTHER (EXPLAIN)

EVENT 95-5 CAUEEL. UNIT DERATED TO REPAIR LEAK ON ISOPHASE BUS DUCT COOLER CORRECTIVE ACTION: LEAK WAS REPAIRED AND UNIT WAS RETURNiiD TO 100% POWER.

V2-4 1

i l

ENCLOSURE 3 VOGTLE ELECTRIC GENERATING PLANT-UNITS 1 AND 2 CHALLENGES TO PORV OR SAFETY VALVES 1

l DOCKET NOS, 50-424,504 25 DATE:

JANUARY 2,1996 COMPLETED BY: G. L. HOOPER TELEPHONE:

(706) 826-4104 l

EVENT DATE TAG NO.

TYPE DESCRIPTION NA NA NA NA

-__