ML20129F425

From kanterella
Revision as of 11:25, 12 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Insp Repts 50-321/85-12 & 50-366/85-12 on 850429-0503. Violations Noted:Noncompliance W/Unit 1 Tech Spec Surveillance Test Frequencies & Inadequate Calibr Procedures in Maint Tool Shop
ML20129F425
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/23/1985
From: Runyan M, Upright C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20129F352 List:
References
50-321-85-12, 50-366-85-12, NUDOCS 8507170333
Download: ML20129F425 (11)


See also: IR 05000321/1985012

Text

.+pp-

. . .

.

~

,

,

l.

.

pLtzg

UNITED STATES

g

fo

NUCLEAR REGULATORY COMMISSION

p

REGloN 11

p

g

j-

101 MARIETTA STREET.N.W.

ATLANTA, GEORGI A 30323

$g

,/

+...+

Report Nos.: 50-321/85-12 and 50-366/85-12

'

Licensee: Georgia Power Company

P. O. Box 4545

Atlanta, GA 30302

Docket Nos.: 50-321 and 50-366

License Nos.: DPR-57 and NPF-5

Facility Name: Hatch I and 2

Inspection Conducted: April 29 - May 3, 1985

Inspector: [1AWNw

522186

M. F. Runyah

\\

Date Signed

Approved by: M //w

/[

C

.3"

~

C. M. Uprigh~t/Jecti.

Chief

()dteS(gned

Division of Riacto -' afety

SUMMARY

Scope: This routine, unannounced inspection involved 32 inspector-hours on site

in the areas of licensee action on previous enforcement matters, surveillance

testing and calibration control program, measuring and test equipment program,

and licensee action on previously identified inspection items.

Results: Two violations were identified - Noncompliance with Unit 1 Technical

Specification Surveillance Test Frequencies and Inadequate Calibration Procedures

in the Maintenance Tool Shop.

.

I

4

8507170333 850531

PDR

ADOCK 05000321

0

PDR

_ - _ _ _ _ _

.

-

3

e

-

=

.-

REPORT DETAILS

i

h

1.

Persons Contacted

Licensee Employees

_

J. Beck, Maintenance Foreman

E. Burkett, Engineer, Reactor Systems

T. Elton, Engineer and Supervisor, Regulatory Compliance

  • P. Fornel, QA Site Manager

--

D. Griffin, Performance Engineer

  • C. Jones, Engineering Manager

7

8. Keck, Engineering Supervisor, Reactor Systems

_

  • H. Nix, General Manager

J. Payne, Engineer. Regulatory Compliance

_-

T. Powers, Superintendent, I&C

7

J. Purvis, I&C Foreman

4

  • T. Seitz, Maintenance Manager

i

H. Scarborough, Maintenance Supervisor

o

'

  • C. Stancil, Engineer, Regulatory Compliance

f

'

  • L. Sumner, Operations Manager

3

  • S. Tipps, Superintendent, Regulatory Compliance

"

?

Other licensee employees contacted included technicians and office

-

personnel.

j

NRC Resident Inspector

  • P. Holmes-Ray, Senior Resident Inspector

i-

  • Attended exit interview

f

2.

Exit Interview

@

The inspection scope and findings were summarized on May 3, 1985, with those

persons indicated in paragraph I above. The inspector described the areas

inspected and discussed in detail the inspection findings Itsted below,

f

.

I

Violation:

Inadequate Calibration Procedures in the Maintenance Tool

_'

Shop, paragraph 5.a.

i

-9

Violation: Noncompliance with Unit 1 Technical Specification Surveil-

2

lance Test Frequencies, paragraph 4.

The licensee denied the violation

.!

-

on the basis that their interpretation of the Technical Specification

!

was consistent with the wording provided.

-

y

Inspector Followup Item: Promptness of Evaluations of Out of-Tolerance

_

Measuring and Test Equipment, paragraph 5.b.

i

$

l

5

t

L

P

__r

v

Y

_ B

_ _ _ _ _

.

.

.

a

2

h

Inspector Followup Item: Method of Verifying Validity of Previous Test

Results for Out of-Tolerance Measuring and Test Equipment, paragraph

5.c.

.

The licensee did not identify as proprietary any of the material provided to

or reviewed by the inspector during this inspection.

3.

Licensee Action on Previous Enforcement Matters

(Closed) Severity Level IV Violation 321, 366/84-33-01:

Failure to Issue

Audits Within TS Required Timeframes.

The licensee response dated November 5,1984, was considered acceptable by

Region II. The post audit conference is now considered the completion of

the audit as prescribed by the ANSI Standard.

The QA Site Manager is

required to ensure the timely issuance of the audit and uses a checklist to

this end. Procedure QA-05-01 was revised to clearly define the Technical

'

Specification requirement to issue audits within 30 days of completion.

From a review of six audits since the citation, all were issued within

30 days of completion.

The inspector concluded that the licensee had

determined the full extent of the violation, taken action to correct current

conditions, and developed corrective actions needed to preclude recurrence

of similar problems.

Corrective actions stated in the licensee response

have been implemented.

4.

Surveillance Testing and Calibration Control (61725)

References:

(a)

10 CFR 50, Appendix B, Quality Assurance Criteria for

Nuclear Power Plants and Fuel Reprocessing Plants

(b) Regulatory Guide 1.33,

Quality Assurance Program

Requirements (0perations), Revision I

(c) ANSI N18.7-1976, Administrative Controls and Quality

Assurance for the Operational Phase of Nuclear Power

Plants

(d) Technical Specifications, Section 4

The inspector reviewed the licensee surveillance testing and calibration

control program required by references (a) through (d) to verify that the

program had been established in accordance with regulatory requirements,

industry guides and standards, and Technical Specifications. The following

criteria were used during this review to determine the overall acceptability

of the established program:

A master schedule for surveillance testing and calibration delineates

-

test frequency, current status, and responsibilities for performance.

The master schedule reflects the latest revisions of the Technical

4

-

Specifications and operating license.

If

[

s ,

- - --

_ --

.

.

3

Responsibilities are assigned to maintain the master schedule up-to-

-

date and to ensure that required tests are performed.

Detailed procedures with appropriate acceptance criteria have been

-

approved for all surveillance testing requirements.

The program defines responsibilities for the evaluation of surveillance

-

test data as well as the method of reporting deficiencies and

malfunctions.

The inspector also verified that similar controls have been established for

calibration of instruments used to verify safety functions but not spect-

fically identified in the Technical Specifications. The documents listed

below were reviewed to verify that these criteria had been incorporated into

the surveillance testing and calibration control program:

QAM, Section 5, Instructions, Procedures, and Drawings, Revision 36

QAM, Section 16, Corrective Action, Revision 36

QAM, Appendix B, Safety Related Items

"Q" List, Revision 36

40AC-REG 01-0, Technical Specifications Surveillance Program,

,

Revision 0

40AC-ENG01-0, Inservice Inspection Program, Revision 0

10AC-MGR03-0, Preparation and Control of Procedures, Revision 2

SIGM-CALO3-0, Calibration Program for LCO/B0P Instrumentation,

Revision 0

The master schedule for Technical Specification (TS) surveillance testing

and inservice inspection of pumps and valves consists of a computer data

base for each unit. This data base lists the procedure number, responsible

group, test type, required frequency, grace period, TS requirement, due

date, and ten previous performance dates for each required test. The data

base was recently audited by an outside consultant after several errors were

found.

The licensee submitted licensee event reports (LER) to document

problems such as failing to revise the data base correctly for a TS amend-

ment. The independent audit and intensive efforts by the licensee provide

reasonable assurance that the data base is now consistent with the TS.

Additional problems were identified with implementation of the program. In

one case, the licensee waited until the last permissible date to perform a

test, then incurred problems with badging personnel essential for its

performance, and thus exceeded the limit.

In another case, an inadvertent

sign-off of a tracking sheet was lined out inconspicuously such that

personnel missed the fact that it had not been performed.

LERs were

submitted for these and similar problems.

Several NRC violations were

submitted for both licensee-identified and NRC-identified deficiencies.

_._m

_ ,, __

__

_

_,

._

.

.

4

Other areas of program deficiencies were recently identified in the

following site QA audits:

QA-84-539, QA Audit of the Surveillance Program, December 13, 1984

QA-85-66, QA Audit of the Site Chemistry Program, February 21, 1985

QA-85-069, QA Audit of Reactor Physics, March 5, 1985

QA-85-146, QA Audit of Test Equipment, April 8, 1985

^

Among the problems identified by these audits were procedures not fully

implementing the TS, failure to review test data, and errors in testing

frequency.

The licensee is aggressively pursuing the closing of these

items.

,

The following surveillance test work packages were reviewed to check program

implementation:

HNP-1-3117-M, Reactor Water Level Loop Calibration, 1/8/85

HNP-1-3966-1, Air Test on Torus Headers and Nozzles, 6/5/84

HNP-1-3006-1, Main Steam Valves Closure Test, 4/6/85

These work packages appeared complete, met acceptance criteria, were

properly reviewed, and were performed on the dates specified by the data

base.

The licensee's program of inservice inspection (ISI) of pumps and valves as

required by ASME Code Section XI, Subsections IWP and IWV, is pending

approval from the Division of Licensing, NRC.

The following ISI work

packages were verified complete and found to meet procedural acceptance

criteria.

HNP-1-3405-1, RCIC Pump Operability, 1/10/85

HNP-1-3303-1,2,3, HPCI Pump Operability, 2/22/85

HNP-1-3201-1,2, Core Spray Pump Operability, 3/14/85

The licensee is required to establish a calibration program for in plant

process instrumentation associated with safety-related systems or functions.

A master calibration schedule addresses both safety-related and balance-of-

j

plant instrumentation and provides information similar to the surveillance

test schedule. The following plant instruments were chosen at random from

>

several ISI and surveillance test procedures to verify their inclusion in

the calibration program:

t

IE41-R601

HPCI Pump Discharge Pressure

.

.

.

.

.

5

1E41-R613

HPCI Pump Flow Rate

E21-R600

Core Spray Pump Discharge Pressure

E21-R601

Core Spray Pump Flow Rate

B21-R607

Vessel Shell and Flange Temperature Recorder

E11-N015A-B

RHR Loop Flow Transmitter

C41-N003

Standby Liquid Control Tank Temperature

The above instruments were included in the program. Calibration frequencies

appeared consistent with instrument type and good engineering practice.

Within this area, one violation was identified. Unit 1 TS 1.0-II states,

" Periodic surveillance tests, checks, calibrations, and examinations shall

be performed within the specified surveillance intervals.

These intervals

may be adjusted plus or minus 25%."

The licensee disagreed with this

violation on the basis that their program to control surveillance test

frequency was developed to assure consistency with the specific TS wording.

Region II management discussed this issue with NRC headquarters and deter-

mined that this TS is intended to limit the time between any two tests to

125 percent of the specified interval.

The licensee interpreted that the

plus or minus 25 percent could be applied independently to fixed scheduled

intervals in such a manner that a test performed 25 percent early, then 25

percent late the next time, could result in 150 percent of the TS interval

between two tests. Other Region II facilities having similar TS wording are

testing in compliance with the NRC intent stated above.

The following

examples are monthly tests which exceeded the maximum performance interval

of 38.75 days required by TS 1.0-II:

Residual Heat Removal Pump Flow (LPCI Flow Switch) Test required by TS

Table 4.2-5(7) performed 1/7/85 and 2/20/85 or 44 days between tests.

Main Steam Isolation Valve Closure Test required by TS Table 4.1-1 (10)

performed 7/26/84 and 9/5/84 or 41 days between tests.

High Drywell Pressure Instrument Test required by TS Table 4.1-1(5)

performed 1/3/85 and 2/12/85 or 40 days between tests.

The performance of these tests were not affected by plant condition or

operating mode. These examples are not all inclusive. Failure to comply

with Unit 1 TS surveillance test frequencies is identified as violation

321/85-12-01.

5.

- Measuring and Test Equipment Program (61724)

References:

(a) 10 CFR 50, Appendix B, Quality Assurance Criteria for

Nuclear Power Plants and Fuel Reprocessing Plants

.

._-

. _ . _

.

._

-

._

.

__

- . .

-

.. .

..

-

.-

.

.

6

(b) Regulatory Guide 1.33,

Quality Assurance Program

Requirements (Operations), Revision 2

x

(c) ANSI N18.7-1976, Administrative Controls and Quality

Assurance of the Operational Phase of Nuclear Power

Plants

(d) Regulatory Guide 1.30, Quality Assurance Requirements

,

for the Installation, Inspection, and Testing of

Instrumentation and Electric Equipment, August 11, 1972

' '

(e) ANSI _ N45.2.4-1972,'

IEEE

Standard,

Installation,

Inspection, and Testing Requirements for Instrumentation

>-

'

and Electric Equipment During the Construction of

Nuclear Power Generating Stations

The inspector reviewed the licensee measuring and test equipment (M&TE)

program required by references (a) through (e) to verify that the program

4

had been established in accordance with regulatory requirements and industry

]

guides and standards. The followf ag criteria were used during this review

i

to determine the overall acceptability of the established program:

}

Responsibility is_ delegated and criteria established to assign and

-

adjust calibration frequency for each type of M&TE.

i

An equipment inventory list identifies all M&TE used on safety-related

-

i,

components, the calibration frequency and standard, and the calibration

'

procedure.

Formal requirements exist for marking -the latest calibration date on

~

-

each piece of equipment.

'

The program assures that each piece of equipment is calibrated on or

-

'

before the date required or stored in a location separate from in-

service M&TE.

'

~

Written requirements - prohibit the use of M&TE which has not been

-

'

calibrated within the prescribed frequency.

i

_ When M&TE is found out of calibration, the program requires documented

-~

[

^

evaluations to determine the cause of the out of-calibration condition

and the acceptability of items previously tested.

,

The program . assures that new M&TE is added to_ the inventory list and

4

--

calibrated prior to use.

,

,

.

.

_

_

,

- The documents ' listed below were reviewed to : verify that these criteria had

been incorporated-into the M&TE program:

.FSAR, Section 17.2.12, Control of Measuring and Test. Equipment-

1

.-

-r

..

l:

,

,

3 e

.

,

_

,r

-,m-,

.

m

y.,,

,

-..

,

- . ,

.

.

,

.

.

7

QAM, Section 12, Control of Measuring and Test Equipment, Revision 31

QAM, Section 16, Corrective Action, Revision 36

50AC-MNT02-0, Control of Measuring and Test Equipment, Revision 0

51GM-CAL 01-0, Control of Test Shop Instrumentation, Revision 0

51GM-MNT02-0, Maintenance Housekeeping and Tool Control, Revision 0

51GM-CALO2-0, Maintenance Shop Measuring and Test Equipment, Revision 0

The inspector reviewed QA-85-146, QA Audit of Test Equipment, April

8~, 1985.

The response date for the audited groups is May 8,

1985.

This audit

identified deficiencies addressed as inspector followup items below.

The I&C shop is the control and issue point for the bulk of the plant's

M&TE. Most equipment is sent off site for calibration. The exceptions are

pressure gages, thermometers, and stop watches.

This equipment is

calibrated according to the following procedures:

HNP-0-5936, Fluke 2160A Digital Thermometer Calibration

HNP-0-5913, Stop Watch Calibration Check

HNP-0-5901, Bourdon Tube Style Test Gauge

The above procedures provided appropriate guidance for performing the

calibration and included specified acceptance criteria.

As a check of control and accountability, the following items of M&TE were

selected from the master equipment index:

MPL No.

Description

L51-E802

Oscilloscope

L51-E827

Ammeter

L51-E840

High Resistance Meter

L51-E864

Tachometer

L51-F888

Digital Multimeter

L51-F892

Digital Multimeter

L51-F900:

Digital Multimeter

L51-F921

Digital Thermometer

L51-G506

Digital Pressure Indicator

L51-P813

Wheatstone Bridge

L51-W805

Deadweight Tester

The above equipment was properly stored, tagged, and documented or could be

accounted for with the exception of the digital thermometer. Apparently, it

had been checked out without documentation on the maintenance history card.

This appeared to be an isolated occurrence.

1

e

.

.-

_

_

o

.

8

The licensee .is required to evaluate previous tests performed with M&TE

found out-of-tolerance during calibration. The following evaluations were

reviewed:

Date Found

Date of

MPL No.

Instrument Type

Out-of-Tolerance

Review

L51-F895

Digital.Multimeter

10/11/84

11/29/84

L51-F911

Digital Multimeter

11/15/84

1/4/85

!

L51-F912

Digital Multimeter

2/5/85

2/21/85

j

Both the timeliness and the method of conducting these reviews are addressed

as inspector followup items below.

The calibration and issuance of mechanical test equipment is conducted in

the maintenance shop. The following tools were selected from the equipment

index to check control and accountability:

MPL No.

Description

L51M-0186

24" Vernier Caliper

L51M-0727

Micrometer 1-2"

L51M-1027

Micrometer 5-6"

L51M-1159

Amp Crimping Tool

L51M-1314

Test Stand Dial Indicator

L51M-1348

Torque Wrench

L51M-2002

Hydraulic Torque Wrench

L51M-4317

Dial Indicator 0-2"

The above tools were either properly stored or checked out. Calibration

stickers agreed with information provided on the master index.

Within this area, -one violation and two inspector followup items were

identified and are discussed in the following paragraphs.

a.

Inadequate-Calibration Procedures in the Maintenance Tool Shop

10 CFR 50, Appendix B, Criterion XII,- requires that measures shall be

.

established to assure that measuring and testing -devices are properly

calibrated. 10 CFR 50, Appendix B, Criterion V, states that activities

affecting quality shall be prescribed by procedures appropriate to. the

l

circumstances which include quantitive or qualitative acceptance

criteria.

Procedures for the calibration of test equipment in the

maintenance tool shop were reviewed.

Major.-deficiencies .were found

with procedure HNP-6943, Calibration Check on Precision Measuring

Equipment,. Revision 1.

This procedure, which addresses calibration of

, micrometers, vernier calipers, depth gauges, and dial indicators, does

not provide. 'prerequi sites such as environmental controls for. the

calibration, step-by-step instructions explaining how to perform the-

-

,

,

a

.

9

calibration, or criteria by which to determine the acceptable tolerance

of the device. Neither vendor manuals nor other manufacturer's data

were availcble to provide this information. Calibration of precision

measuring equipment is sensitive to tn erature, rates of temperature

f

change, and possibly other factors so n as humidity, dust, and vibration.

This can best be controlled by esttalishing environmental conditions

satisfactory for all calibration activities conducted in the shop.

Step-by-step instructions are necessary for quality control of any

activity directly affecting safety. Acceptance criteria must establish

tolerance bands within which the device will be considered acceptable.

Though the calibration procedure for precision measuring equipment has

been specifically discussed above, all calibration procedures in the

shop should be reviewed as a generic issue.

Failure to provide

adequate calibration procedures in the maintenance tool shop is

identified as violation 321, 366/85-12-02.

b.

Promptness of Evaluations of Out-of-Tolerance Measuring and Test

Equipment

The . licensee is committed to ANSI N18.7-1976, Section 5.2.16, which

states, "When calibration, testing, or other measuring devices are

found to be out of calibration, an evaluation shall be made and

documented concerning the validity of previous tests and the accept-

ability of devices previously tested from the time of the previous

calibration." Though the standard does not mention the timeliness of

these evaluations, this is an important consideration because invalid

settings, test data, or calibrations could invoke limiting conditions

of operation. In both the I&C and maintenance shops, many evaluations

had taken from one to three months to complete. Lengthy delays are due

in part to procedures which do not provide a.necessary time constraint.

-Site QA identified this problem in a recent audit and is awaiting

initial responses.

Until the timeliness of out-of-tolerance evalua-

tions is procedurally and effectively controlled, this is identified as

inspector followup item 321, 366/85-12-03.

c.

Method of Verifying Validity of Previous Test Results for

Out-of-Tolerance Measuring and Test Equipment

51GM-CAL 01-0, Control of Test Shop Instrumentation (I&C), Revision 0,

states'that when M&TE is found out of calibration and a review reveals

that previous tests are in question, plant instrumentation will be

retested, beginning with the most recent calibrations, until three

consecutive instruments have been checked to ensure the quality of the

remaining calibrations.

However, an item of M&TE may be out of

calibration' on several scales.

The last three tests may have been

affected by a scale only slightly out of tolerance while previous tests

may have been affected by another scale greatly out of tolerance. In

this case, the assumption that previous test are acceptable may be

erroneous.

In the maintenance shop, only the last affected test is

1

-1

-

I]

-

..

..

10

rechecked though this policy is not written.

These problems were

recently identified by site QA and corrective action is in progress.

Until the program is revised to ensure that evaluations of out-of-

tolerance M&TE address the issue of multiple scales and a uniform

policy on previous usage, this item is identified as inspector followup

item 321, 366/85-12-04.

6.

Licensee Action on Previously Identified Inspection Findings (92701)

(Closed) Inspector Followup Item 321, 366/84-33-02: Management Attention to

Oetail

The QA site manager is now required to ensure that a response date is

specified in the transmittal letter to all affected groups. A sample of six

recent audits confirmed compliance with this requirement.

Procedure

QA-05-01 was revised to state TS requirements for issuing audits and to

clarify the QA escalation process.