IR 05000237/2020004

From kanterella
Revision as of 11:08, 29 November 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Integrated Inspection Report 05000237/2020004 and 05000249/2020004
ML21041A483
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/10/2021
From: Kenneth Riemer
NRC/RGN-III/DRP/B1
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
References
IR 2020004
Download: ML21041A483 (23)


Text

February 10, 2021

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - INTEGRATED INSPECTION REPORT 05000237/2020004 AND 05000249/2020004

Dear Mr. Rhoades:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3. On January 21, 2021, the NRC inspectors discussed the results of this inspection with Mr. P. Boyle, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects

Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000237 and 05000249

License Numbers:

DPR-19 and DPR-25

Report Numbers:

05000237/2020004 and 05000249/2020004

Enterprise Identifier: I-2020-004-0061

Licensee:

Exelon Generation Company, LLC

Facility:

Dresden Nuclear Power Station, Units 2 and 3

Location:

Morris, IL

Inspection Dates:

October 1, 2020 to December 31, 2020

Inspectors:

J. Cassidy, Senior Health Physicist

G. Edwards, Health Physicist

R. Elliott, Resident Inspector

M. Garza, Emergency Preparedness Inspector

V. Meghani, Reactor Inspector

A. Nguyen, Senior Resident Inspector

C. Phillips, Project Engineer

M. Porfirio, Illinois Emergency Management Agency

Approved By:

Kenneth R. Riemer, Chief

Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 began the inspection period at full power. On December 5, 2020, the unit was down powered to 66 percent for routine control rod drive scram time testing, a control rod sequence exchange, main turbine surveillances, and feedwater regulating valve maintenance. The unit returned to full power on December 6, 2020. The unit remained at or near full power for the remainder of the inspection period.

Unit 3 began the inspection period in coast down to prepare for refueling outage D3R26. On October 26, 2020, the unit was shut down to commence D3R26. The unit synchronized to the grid on November 7, 2020, and ascended to full power shortly thereafter. The unit was down powered to 65 percent power on November 14, 2020, for beginning-of-life control rod sequence exchanges and returned to full power on November 15, 2020. An additional down power was performed on November 21, 2020, to 70 percent power for additional control rod sequence exchanges. The unit returned to full power on November 22, 2020, and operated at or near full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19),resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 3 shutdown cooling system during D3R26 on October 26, 2020
(2) Electrical alignment during D3R26: 4kV crossties on October 29, 2020, and November 2, 2020
(3) Unit 3 alternate delay heat removal and fuel pool cooling system alignment during D3R26 on November 2, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone (FZ) 8.2.5D and FZ 8.2.6D, Unit 3 low pressure heater bays on October 27,2020
(2) FZ 8.2.2B, Unit 3 containment cooling service water pump floor, elevation 495', and comp measures for out of service fire hose stations on October 30, 2020
(3) FZ 1.1.1.3, Unit 3 reactor building general area, elevation 545' on November 2, 2020
(4) FZ 1.2.1, Unit 3 drywell primary containment on November 3, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Cable tunnel on December 18, 2020

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 3 'A' low pressure coolant injection heat exchanger

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary were appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing documents for the following activities from October 26, 2020, to November 5, 2020:

03.01.a - Nondestructive Examination and Welding Activities

1. Nondestructive Examinations

  • Ultrasonic (UT) Examination, core bore hole drywell steel liner surface, 112.5.1.1A and 112.5.1.1B
  • Visual VT-1 Examination, RPV head vent piping flange bolting 3/1/0215-2/HV2-18-FLG
  • Visual VT-3 Examination, rigid support, M-3410-09, containment
  • Visual VT-3 Examination, spring hanger, M-3411-04, containment
  • Visual VT-3 Examination, supports 01 /02/06, torus ring girder - support columns/inner support column base plates/ outer support column base plates
  • In-Vessel Visual Inspection (IVVI) of RPV Internals, component IDs CSS 1 S3 a, b 008-080 (Core Spray Sparger) and JP 09 WD-1 (Jet Pump), part of the boiling water reactor vessel and internals project (VIP)

2. Examination records with relevant indications accepted for continued service

  • Recordable UT Indications, D3R25, Weld 3/2/02A-12/12-8, isolation condenser shell to nozzle weld (AR 04190585)

3. Pressure boundary welds

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during reactor shutdown/cool down on October 26, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 3 C circulating water pump bearing identified as failed during Unit 3 refueling outage on October 17, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) High-pressure coolant injection rupture disc maintenance and quality control, failures during installation during D3R26

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Division 1 and 2 low pressure coolant injection and core spray work windows during the week of October 19 - 23, 2020
(2) Unit 3 transfer of AC feed to and from 4kV crossties during D3R26 on October 29, 2020, and November 2, 2020
(3) Unit 3 Yellow shutdown risk during lowered inventory conditions on October 27, 2020, and November 4, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)2A reactor feedwater pump lost indication

(2) Cardox tank level low causing CO2 to be inoperable to emergency diesel generator rooms
(3) Many partially blocked containment spray nozzles identified during Unit 3 testing
(4) Unit 3 isolation condenser 3-1301-3 valve over-torqueing during testing
(5) Emergency core cooling system valve issues identified during D3R26
(6) Local leak rate test leakage identified during D3R26

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Adjustable speed drive NXG circuit card obsolescence and cooling upgrades

[Permanent]

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) DOS 0201-01, Unit 3 reactor pressure vessel ASME B&PV (American Society of Mechanical Engineers Boiler and Pressure Vessel) Code 1000 psi system leakage test, after work that affected the reactor coolant system and boundaries during D3R26 on November 5, 2020
(2) Unit 3 control rod drive exercising and timing after repairs during D3R26 on November 5 and 6, 2020
(3) DOS 0040-07, Unit 3 verification of remote position indication for valves in the inservice testing program, after troubleshooting and repair of the 3-0220-44 and 3-0220-46 valves per WOs 5096172 and 5092566 during D3R26
(4) Division 1 core spray post-maintenance tests (PMTs) D3R26
(5) Unit 3 low pressure coolant injection and containment cooling service water PMTs D3R26
(6) DOS 2300-03, Unit 3 high-pressure coolant injection system operability and quarterly IST (inservice testing) verification test, after system maintenance completed during D3R26 on November 7, 2020
(7) Troubleshoot and repair Unit 3 rod select matrix per WO 5086646

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the Unit 3 refueling outage, D3R26, activities from October 26, 2020, through November 7, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) DOS 6600-03, Unit 3 Division 1 undervoltage test on October 27 and 28, 2020
(2) DIP 0260-01, Refuel outage reactor vessel level and cavity instrumentation on October 26 and November 5, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) DOS 7100-06, Unit 3 seat leakage testing of valve 3-2301-7, high-pressure coolant injection check valve, on October 30, 2020

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Local leak rate testing of Unit 3 main steam isolation valves and feedwater check valves during D3R26 on October 27-29, 2020

FLEX Testing (IP Section 03.02) (1 Sample)

(1) WO 4718444, FLEX SAWA pump run on November 10, 2020

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors completed an evaluation of submitted emergency action level and emergency plan changes on December 2, 2020. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) EP Drill on December 3,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated radiological protection-related instructions to plant workers

Contamination and Radioactive Material Control (IP Section 03.03) (1 Sample)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed licensee surveys of potentially contaminated material leaving the Radiologically Controlled Area (RCA) and workers exiting the RCA at Unit 3 during a refueling outage.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (1 Sample)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) Initial entry into reactor cavity and decontamination after refueling during D3R26 under radiation work permit (RWP) DR-03-20-00906

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 2 (October 1, 2019 through September 30, 2020)
(2) Unit 3 (October 1, 2019 through September 30, 2020)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 2 (July 1, 2019 through June 30, 2020)
(2) Unit 3 (July 1, 2019 through June 30, 2020)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 2 (July 1, 2019 through June 30, 2020)
(2) Unit 3 (July 1, 2019 through June 30, 2020)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 2 (July 1, 2019 through June 30, 2020)
(2) Unit 3 (July 1, 2019 through June 30, 2020)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 2 (October 2019 through September 2020)
(2) Unit 3 (October 2019 through September 2020)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 2 (October 1, 2019 through September 30, 2020)
(2) Unit 3 (October 1, 2019 through September 30, 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

(June 2019 through September 2020)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1)

(April 2019 through September 2020)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends during D3R26, specifically focused on Human Performance events that could be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Safety-related valve degradation issues identified during D3R26, the Unit 3 refueling outage, from October 26 through November 7, 2020
(2) Multiple failures of the FLEX SAWA pumps during surveillance runs

INSPECTION RESULTS

Observation: Potential Negative Trend in Human Performance Events 71152 The inspectors performed a semiannual review of issues entered into the corrective action program (CAP) and a cognitive review of observations conducted over the period of July 1, 2020, to December 31, 2020, to identify any potential trends that might indicate the existence of a more significant safety issue. Based on these reviews, the inspectors concluded that there was a potential negative trend in the area of Human Performance.

Specifically, there were a number of issues where the implementation of human performance tools was not adequate to prevent errors, emergent work scheduling changes led to unintended challenges for completing (or in some cases missing) work activities, and general attention to detail and appropriate focus on work activities was not demonstrated to ensure proper engagement by plant personnel to prevent errors. Examples of these human performance issues, and their associated CAP documents, are listed below:

  • IR 4381193, D3R26, Fuel Handling Error during Fuel Shuffle 2
  • IR 4381800, Reseat of Fuel Support Casting Location 18-23
  • IR 4383120, 2 Valves Still Need Required Surveillance Testing
  • IR 4385543, D3R26, Hydro Preps Conflict with IM Logic Testing
  • IR 4390417, Entered DOA 4450-03 for Loss of Lift Station and
  • IR 4384354, Ops Crew Clock Reset, Quarterly Valve Timing

The residents discussed these observations with the licensee. The licensee created corrective actions to address some of these items for the specific issue in the CAP system.

However, the licensee, at the time of this report, had not performed a holistic review of the issues to determine if there were more widespread actions that could be taken to improve performance. The licensee will convene a group to review the data and determine any actions going forward.

Observation: Safety-Related Valves Found Degraded during D3R26, Unit 3 Refueling Outage 71152 During the refueling outage on Unit 3, several safety-related valves were identified as being degraded and documented in the corrective action program. The inspectors reviewed the current corrective actions associated with ensuring these valves remained in compliance with licensing and design basis requirements. No issues were identified that would challenge the safety function or operability of these valves. The corrective actions taken were determined to be timely and appropriate for the conditions identified.

The inspectors also reviewed previous condition reports and corrective actions for prior degradation issues identified with a select number of these valves. The inspectors found that a few of the valves had repetitive degradation issues identified in the CAP and reviewed the prior evaluation of these issues to determine if the issues were addressed appropriately. The inspectors determined that previous evaluations were appropriate for the conditions identified at the time and that the corrective actions taken were adequate. Some of the degradation mechanisms were different over time, and/or maintenance frequencies were appropriately changed to identify potential issues sooner.

Observation: Multiple Failures of the FLEX SAWA Pumps during Surveillance Runs.

71152 The inspectors reviewed multiple issue reports associated with the licensee's attempts to operate the FLEX SAWA pumps per the required monthly test runs which were unsuccessful.

The degraded conditions were documented adequately in the CAP in a timely manner. The inspectors reviewed the current corrective actions associated with ensuring FLEX SAWA pumps remained in compliance with licensing and design basis requirements. No issues were identified that would challenge or pose a threat to the licensee's FLEX strategy or implementation. The corrective actions taken were determined to be timely and appropriate for the conditions identified.

The inspectors also reviewed previous condition reports and corrective actions for previous FLEX pump issues identified during surveillance runs. The inspectors found repetitive degradation issues identified during the surveillances that were entered in the CAP and reviewed the prior evaluation of these issues to determine if the issues were addressed appropriately. The inspectors determined that previous evaluations were appropriate for the conditions identified at the time and that the corrective actions taken were adequate. The licensee also identified and entered the trend of FLEX issues into their CAP program IR 4374740, Trend IR FLEX Equipment.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 21, 2021, the inspectors presented the integrated inspection results to Mr. P. Boyle, Plant Manager, and other members of the licensee staff.
  • On November 5, 2020, the inspectors presented the Inservice Inspection Exit D3R26 inspection results to Mr. P. Karaba, Site Vice President, and other members of the licensee staff.
  • On December 2, 2020, the inspectors presented the IP 71114.04 exit meeting inspection results to Mr. D. Moore, Senior Manager Emergency Preparedness, and other members of the licensee staff.
  • On December 10, 2020, the inspectors presented the radiation protection inspection results to Mr. T. Casagrande, Radiation Protection Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

4380442

3-1001-4A Valve Stem Corrosion

10/27/2020

Corrective Action

Documents

Resulting from

Inspection

4379748

D3R26 3-1999-325 Packing Leak

10/26/2020

Engineering

Evaluations

2343

D3R26 Spent Fuel Pool Cooling Evaluation During

Transition to ADHR

Procedures

DOP 1000-M1/E1 Unit 3 Shutdown Cooling Checklist

DOP 1900-E1

Fuel Pool Cooling Electrical

DOP 1900-M1

Unit 3 Fuel Pool Cooling System Checklist

DOP 6500-30

E: Bus Crosstie Amps

DOS 1000-02

Alternate Decay Heat Removal Using Shutdown Cooling

and Fuel Pool Cooling Systems

71111.05

Corrective Action

Documents

4380385

Transient Combustibles Located Under Stairwell

10/28/2020

Engineering

Evaluations

Various Transient Combustible Permits for D3R26, Unit 3

Refueling Outage, Work Activities

Fire Plans

21 URB-23A

Dresden Generating Station Pre-Fire Plan

FZ 8.2.2B

Unit 3 CCSW Pumps, Elevation 495'

FZ 8.2.5D

Unit 3 Low Pressure Heater Bay, Elevation 517'

FZ 8.2.6D

Unit 3 Low Pressure Heater Bays, Elevation 538'

Miscellaneous

Hot Work Permits for Welding in Unit 3 Low Pressure and

High-Pressure Heater Bays during D3R26

Procedures

OP-AA-201-007

Fire Protection System Impairment Control

71111.06

Miscellaneous

DR-PSA-012

Internal Flood Evaluation Summary and Notebook

71111.07A

Corrective Action

Documents

4380814

3A LPCI Tubes Stuck Cleaning Scrapers

10/30/2020

4381431

3-1599-112, CCSW Heat Exchanger Sample Line Flush

Valve, Failed Inspection

11/01/2020

4381473

D3R26 3A LPCI Heat Exchanger Coating Repairs

11/01/2020

4383193

3A LPCI Heat Exchanger D3R26 Coatings Repairs

Lessons Learned

10/31/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NDE Reports

20-10

Eddy Current Examination Final Report for Exelon Nuclear

Dresden, Unit 3, 3A LPCI Heat Exchanger

(3-1503-A)

11/02/2020

Work Orders

4590891

D3R26 Clean/Inspect/Eddy Current 'A' LPCI Heat

Exchanger

11/02/2020

71111.08G

Calculations

1801382.301

Dresden Iso Condenser Flaw Evaluation

Corrective Action

Documents

00949941

Corrosion on Unit 3 Torus Baseplate Anchor

08/03/2009

04013601

Degraded Unit 3 CCSW Piping Identified

05/22/2017

04379976

D3R26 Drywell Basement Moisture Barrier Relevant

Conditions

10/27/2020

04380663

D3R26 FAC, Area on 3D2 Heater found Below Min Wall

10/29/2020

04381396

D3R26 Nonrelevant Condition on Support M-3410-09

10/31/2020

Drawings

3-CISI-1000 SHT

2B

IWE Component Detail, Drywell Floor Core Hole Locations

and Details

A

M-3410-09 SHT

Vacuum Relief 3-16040 18 IN LX

B

M-3410-09 SHT

Vacuum Relief 3-16040 18 IN LX

E

M-3411-04 SHT

Support Drawing

D

Engineering

Evaluations

EC 626262

ASME Code Case N-586-1 Evaluation for Unit 3 Isolation

Condenser 3/2/1302A-12/12-8 Nozzle to Shell Weld

NDE Reports20-375

VT-3 Report for License Renewal Supports 1, 2, 6

10/31/2020

20-393

VT-3 - Component No. M-3410-09

11/02/2020

20-403

VT-3 for Component No. M-3411-04

11/02/2020

20-427

UT Thickness Measurements of the Drywell Basement

Floor Liner in 22 Core Hole Locations

11/02/2020

D3R26-VT-001

VT-1 for 3/1/0215-2/HV2-18-FLG

10/31/2020

D3R26-VT-002

3/1/0215-4/4A-1(A)-FLG

10/31/2020

Procedures

ER-AA-335-004

Ultrasonic (UT) Measurement of Material Thickness and

Interfering Conditions

ER-AA-335-014

VT-1 Visual Examination

ER-AA-335-016

VT-3 Visual Examination of Component Supports,

Attachments and Interiors of Reactor Vessels

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-AA-335-018

Visual Examination of ASME IWE Class MC and MET

ALLIC Liners of Class CC Components

GEH-VT-203

Procedure for In-Vessel Visual Inspection (IVVI) of BWR 3

RPV Internals

Work Orders

04678175-01

CM Replace CCSW Pump 3-1501-44-D, Degraded

Discharge Elbow

11/02/2018

04615093-11

Through Wall Pipe Leak on CCSW Line 3-1514-16

03/23/2017

71111.12

Corrective Action

Documents

4382882

D3R26 - Steam Leak from HPCI Rupture Disc

11/07/2020

4377284

3C Circulating Water Pump Bearing High Temperature

10/17/2020

Engineering

Changes

2912

HPCI Steam Rupture Disc - Allow Use of 140 psig Rated

Set

Engineering

Evaluations

448508

Evaluate Torque Value for HPCI Rupture Discs with Fully

Lubricated Flange Bolts

448508

Evaluate Torque for HPCI Rupture Disc Based on

Lubricated Stud Bolts

Procedures

DMP 2300-14

HPCI Rupture Disc Maintenance

and 09

Work Orders

25035

IST Replace Both Unit 3 HPCI Turbine Steam Exhaust

Rupture Discs

11/03/2020

71111.13

Corrective Action

Documents

Resulting from

Inspection

4379974

NRC Questions During D3R26

10/27/2020

4380495

NRC Concern on Protected Pathway

10/29/2020

4382296

Protected Pathway Concerns

11/04/2020

4382308

NRC ID: 2/3 RBCCW Oiler Empty

11/04/2020

4382310

NRC ID: 3A CCSW Pump Seal Leakage

11/04/2020

Miscellaneous

D3R26 Shutdown Safety Contingency Plans,

Compensatory Action Plans and Related Work Evaluation

10/13/2020

D3R26 Protected Equipment Summary

10/23/2020

Protected Equipment Schemes for Various Plant

Configurations Reviewed this Quarter

Procedures

DOP 6400-13

Electrical Yard Switching

DOP 6400-14

Transformer 86 Load Tap Changer Operation

DOP 6500-08

Bus 24-1 to Bus 34-1 Tie Breaker Operation

DOP 6500-30

Bus 23-1 to Bus 33-1 Tie Breaker Operation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DOS 1100-04

Standby Liquid Control System Quarterly/Comprehensive

Pump Test for the Inservice Testing (IST) Program

DOS 5750-04

Control Room Train B HVAC and Air Filtration Unit

Surveillance

OP-AA-108-117

Protected Equipment Program

71111.15

Corrective Action

Documents

4379382

LLRT Results Above Alarm Limit for Penetration X-138

10/25/2020

4379385

LLRT Results Above Warning Limit for Penetration

X-149B

10/25/2020

4379698

LLRT Results Above Warning Limit for AOV 3-2001-6

10/26/2020

4379747

Cardox Tank Low

4379969

3-1501-26A Leakage During LPCI Single Loop Test

10/27/2020

4380023

High Resistance Contacts - Control Switches for HPCI

Valves

10/27/2020

4380323

Unable to Close Breaker for 3-1501-21A

10/28/2020

4380764

LLRT Results Above Warning Limit for MOV 3-1501-19A

10/30/2020

4380783

Open Contacts on Torque Switch

10/30/2020

4381583

D3R26 Results of U3 LPCI Containment Spray Testing

4382613

3-1501-25B Failed to Indicate Full Open during Testing

11/05/2020

4389199

2A Reactor Feedwater Pump Indicating Light Out

2/09/2020

Drawings

2E-2349

Schematic Diagram: 480V Bus 29 Main Feed and Bus

28-29 Crosstie Breakers

AH

Engineering

Changes

2250

Blocked Drywell Spray Nozzle Evaluation for AST Dose

Analyses

Procedures

DOS 0040-07

Verification of Remote Position Indication for Valves

Included in Inservice Testing (IST) Program

Work Orders

4855292

Primary Containment Type B&C Leakage Rate Test

Summation

11/11/2020

71111.18

Engineering

Changes

25677

ASD Obsolescence and Cooling Upgrades

28647

ASD NXG Circuit Card on ASD Digital Card Rack

Procedures

DOS 0202-25

ASD Testing in Open Loop Test Mode

71111.19

Corrective Action

Documents

4379710

Failed Recirculation Sample Valve, 3-0220-44; Did Not

Open with Control Switch

10/26/2020

4380424

Rupture Disc Failure During Install

10/29/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4381583

D3R26 Results of U3 LPCI Containment Spray Testing

4382189

Unit 3 HPCI MGU/MSC PMTs

11/04/2020

4382306

D3R26 Flowscan Testing of the 3-0220-44 Recirculation

Sample Valve

11/04/2020

4382356

AOV 3-0220-44 Showing Dual Indication on Position

11/05/2020

4382501

D3R26 System Leakage Test: 84 dpm Leak from

HCU 14-11

11/05/2020

4382541

D3R26 RCPB Class 1 System Leakage Test Results

11/05/2020

4382602

AO 3-0220-45 Valve will Not Open from Main Control

Room during PMT

11/05/2020

4382606

3-0220-46, Reactor Head Vent Valve, will Not Operate

11/05/2020

4382650

LLRT Results above Warning Limit for AOV 3-0220-44

(As-Left)

11/06/2020

4382911

Entered DOA 0700-02 for IRM 13 Not Withdrawn

11/07/2020

4383070

Unit 3 Rod Select Matrix Issues

11/08/2020

4386073

D3R26 Unit 3 Rod Select Matrix Troubleshooting

11/18/2020

Engineering

Evaluations

395859

Evaluation of Leakage at Mechanical Connections for

Class 1 and 2 System Leakage Test

448626

IRM 13 Fuses Replaced with 2 Amp due to 1 Amp Fuses

Blowing when Attempting to Withdraw IRM During Startup

2929

Evaluation of Leakage at Mechanical Connection for LPCI

Valve 3-1501-26A

Procedures

DIS 1500-20

Division 1 and II Low Pressure Coolant Injection Pumps

Suction and Injection Valves Circuitry Logic System

Functional Test

DOS 0040-07

Verification of Remote Position Indication for Valves

Included in Inservice Testing Program

DOS 0201-02

Unit 3 RPV ASME B and PV Code 1000 PSI System

Leakage Test

DOS 0300-08

CRD Exercising with Mode Switch in Refuel

DOS 0300-15

Control Rod Drive SCRAM Timing Test during Hydro

DOS 2300-03

High-Pressure Coolant Injection System Operability and

Quarterly IST Verification Test

117

DTS 1500-03

LPCI Containment Spray Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

01784322

D3 4Y TS LPCI Containment Spray Test of D/W Spray

Nozzle

1610562

Replace Regulator and Diaphragm and Repack

3-0220-44 Valve

11/06/2020

4570360

D3 24M TS Division 1 and 2 LPCI Suction and Injection

Valves LSFT

4852964

Replace ASCO Solenoid for Valve 3-0220-44

11/06/2020

4872264

Unit 3 Refuel Outage ISI 1000 PSI Reactor Vessel

Leakage Test (Hydrostatic Test)

11/05/2020

5068912

Inspect and Replace MSC and MGU Limit Switches

10/30/2020

5092566-02

(PMT) Perform Logic Testing of Valve 3-0220-44

11/06/2020

5096172

3-0220-46, Reactor Head Vent Valve, will Not Operate,

Troubleshoot and Repair

11/06/2020

71111.20

Corrective Action

Documents

4382043

D3R26: FME ECCS Suction Strainer Inspection Results

11/03/2020

4382206

Deviation to Implementation of the Work Hour Rule

4382403

Deviation to Implementation of the Work Hour Rule

4382946

203-5 Instrument Rack Leak

11/07/2020

4382985

3C Reactor Feedwater Pump Auxiliary Oil Pump Did Not

Automatically Shut Off

11/08/2020

4382993

3A Reactor Feedwater Pump Discharge Valve Binding

11/08/2020

4382994

MFDLRX Mismatch during D3R26 Power Ascension

11/07/2020

Engineering

Changes

2956

MR-90 Jumpers to Support D3R26 Hydro Test Prior to

Startup

Miscellaneous

D3R26 Refuel Outage Key Safety Function Review

10/23/2020

Tagout 03-03-

SDVWEST-001

D3R26: Unit 3 West SCRAM Discharge Volume Work

10/27/2020

Tagout 03-15-

CCSW+HX-001

D3R26: Division I CCSW Loop and 3A LPCI Heat

Exchanger

10/26/2020

Tagout 03-83-

250VDC-001

D3R26: 250V Battery Modified Performance Test

11/02/2020

Operability

Evaluations

OP-AA-108-108

Unit Restart Review

Procedures

DFP 0800-07

Fuel Movements during Refueling Operations

DGP 01-S1

Startup Checklist

103

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DGP 04-01

Fuel Moves and Refueling

DOP 0201-04

Reactor Pressure Vessel Water Inventory Control

DOP 1000-09

Bypassing Shutdown Cooling Isolation

DOP 1900-03

Reactor Cavity, Dryer/Separator Storage Pit and Fuel Pool

Level Control

DOS 1600-10

Drywell Closeout Inspection Plan

LS-AA-119

Fatigue Management and Work Hour Limits

OU-DR-104

Shutdown Safety Management Program

71111.22

Corrective Action

Documents

4380835

D3R26 3-2301-7 Excessive Leakage

10/30/2020

Procedures

DIP 0260-01

Refuel Outage Reactor Vessel and Cavity Level

Instrumentation

DOS 6600-03

Bus Undervoltage and ECCS Integrated Functional Test

for Unit 3 Diesel Generator

DOS 7000-26

Local Leak Rate Testing of Unit 2(3) Feedwater System

Valves

DOS 7100-06

Seat Leakage Testing of Valve 3-2301-7

Work Orders

4596470

Unit 3 Refueling Cycle Bus 33-1 Undervoltage and ECCS

Integrated Functional Test

10/28/2020

4852650

Local Leak Rate Test for Valves 3-0220-57B and

3-0220-62B, Feedwater Outboard Check Valves

10/29/2020

4852651

Local Leak Rate Testing of Valves 3-0220-57B and

3-0220-58B, Feedwater Inboard Check Valves

10/29/2020

4855824

Unit 3 Refueling Reactor Vessel and Cavity Level

Instrumentation

11/05/2020

4881509

Unit 3 IST Seat Leak Test for HPCI Inlet to Feedwater

Check Valve

11/06/2020

71114.04

Corrective Action

Documents

25295

Perform Impact Review of EAL Revisions from

EOP/SAMG, Rev. 4

03/10/2020

Miscellaneous

19-29

Exelon Nuclear Standardized Radiological Emergency

Plan

09/04/2020

19-65

Exelon Nuclear Standardized Radiological Emergency

Plan

09/06/2019

19-79

Various Station Emergency Preparedness Annexes

11/08/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

19-80

On-Shift Staffing Assessments

11/08/2019

20-05

EALs for Dresden Station; Dresden PAR Flowchart

2/07/2020

20-36

EALs for Dresden Station

06/09/2020

71124.01

ALARA Plans

DR-03-20-00512

D2R26 Drywell Control Rod Drive Exchange / CRD

Support Activities

10/13/2020

DR-03-20-00513

D2R26 Drywell Control Rod Drive Exchange / CRD

Support Activities

10/13/2020

DR-03-20-00906

D3R26 Cavity Decon

10/13/2020

Corrective Action

Documents

014383624

D3R26 RP Lessons Learned

11/11/2020

Miscellaneous

Reactor Cavity Decontamination Plan

N/A

Radiation

Surveys

20-084355

Reactor Cavity - Post Decon Survey

11/04/2020

20-084374

Reactor Cavity - Post Decon Survey

11/04/2020

20-084435

Reactor Cavity - Initial Survey

11/04/2020

71151

Corrective Action

Documents

04367428

NRC Request Follow-Up on ED Alarm

09/04/2020

Miscellaneous

CY-AA-130-

3010-F-03

Dose Equivalent Iodine Determination - Unit 2

October

2019 -

September

20

CY-AA-130-

3010-F-03

Dose Equivalent Iodine Determination - Unit 3

October

2019 -

September

20

LS-AA-2090

Monthly Data Elements for NRC Reactor Coolant System

(RCS) Specific Activity

October

2019 -

September

20

LS-AA-2140

Monthly Data Elements for NRC ROP Indicator -

Occupational Exposure Control Effectiveness

June 2019 -

September

20

LS-AA-2150

NRC RETS/ODCM Radiological Effluent Occurrences and

Supporting Information

April 2019 -

September

20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radiation

Surveys

2019-056188

2/3 Radwaste 507' Barrel Area

10/22/2019

71152

Corrective Action

Documents

1138794

D3R21 LLRT 3-1501-19A Exceeded Admin Alarm Limit

11/11/2010

1441994

D3R22 LLRT on 3-1501-19A Exceeded Admin Limit

11/19/2012

2737436

LLRT Exceeds Warning Limit

11/05/2016

4372663

Temporary Loss of Required Fire Watch

09/28/2020

4378033

Security Response to Turnstile Alarm

10/20/2020

4381193

D3R26: Fuel Handling Error During Fuel Shuffle 2

10/31/2020

4381227

Level 1 Fuel Move Error

10/31/2020

4381800

Reseat of Fuel Support Casting Location 18-23 Required

11/02/2020

4383120

Valves Still Need Required Surveillance Testing

11/09/2020

4385280

D3R26 Lessons Learned - Near Miss of PMT Required

Prior to Mode 2

11/06/2020

4385543

D3R26 Lessons Learned: Hydro Preps Conflict with IM

Logic Testing

11/05/2020

4385550

D3R26 Lessons Learned: Near Miss with PMT - Partial

Procedure and New Conditions

11/06/2020

4387354

Ops Crew Clock Reset: Quarterly Valve Timing

11/22/2020

4390417

Entered DOA 4450-03 for Loss of Lift Station

2/15/2020

Corrective Action

Documents

Resulting from

Inspection

4379644

NRC Questioned PPE Requirements for Racking Breakers

10/26/2020

4379684

Issues Identified During NRC Walkdown

10/26/2020

4379958

NRC Concern

10/26/2020

Work Orders

1386628

Repair 3-1501-19A Valve

11/28/2012