ML20129D863

From kanterella
Revision as of 14:57, 21 August 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Forwards Appraisal Team Insp Rept on 850219-0301 & 0311-22. Deficiencies Noted Indicate Const Program Weaknesses Exist. Executive Summary of Results of Insp Encl
ML20129D863
Person / Time
Site: Millstone Dominion icon.png
Issue date: 05/21/1985
From: Taylor J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Opeka J
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML20129D868 List:
References
NUDOCS 8506060249
Download: ML20129D863 (10)


See also: IR 05000219/2003001

Text

m ,

. .

'

" , E,) k:g' -

-

UMTED STATES

. NUCLEAR REGULATORY COMMISSION

.,,

  • , -l , ,

WASHING TON, D. C. 20555

-....... May 21, 1985

-Docket No. 50-423

~

LNortheas'tfNuclearEnergyCompany

ATTN: -Mr.' John F.-Opeka

-

Senior Vice President - Nuclear

. Engineering and Operations Group

P.O.' Box 270 .'

' Hartford,'CT - 06141-0270

-Gentlemen:

, -

. SUBJECT:

CONSTRUCTION APPRAISAL TEAM INSPECTION 50-423/85-04

Enclosed is the report of the Construction Appraisal Team (CAT) inspection

conducted by the Office of Inspection and Enforcement on February 19-March 1

and March 11-22 1985'at-the Millstone Unit 3 site.

Team was compose,d of members of IE, NRC Region I and a number of consulta

The inspection cevered construction activities authorized by NRC Construction

Permit CPPR-113.

This inspection is .the eleventh of a planned series of construction appraisal

'  : inspections by the Office of Inspection and Enforcement. The results of these

inspections are being used to evaluate the management control of construction

activities and the quality of construction at nuclear plants.

The enclosed report identifies the areas examined during the inspection.

Within these areas, the effort consisted primarily of detailed inspection of

selected hardware subsequent to quality control inspections, a review of

selected portions of your Quality Assurance Program, examination of procedures

and records, and observation of work activities.

Appendix A to this letter is an Executive Summary of the results of this

inspection and of conclusions reached by this office. The NRC CAT noted no

pervasive breakdown in meeting construction requirements in the samples of

installed hardware inspected by the team or in the licensee's project

p construction controls for managing the Millstone Unit 3 project.

,

I

However, deficiencies noted by the NRC CAT indicate that a number of construc--

tion program weaknesses exist which warrant additional management attention.

,

The major areas of concern to the NRC CAT are: (1) ineffective implementation

and contro1~of work on systems ~and components subsequent to turnover from

! construction to the testing organization and (2) need to improve interface

actions and communications among the design, construction, and inspection

! organizations.

IE01

s Copy to RCPBt1E

>

<

w -

..

. Northeast Nuclear Energy Company -2- May 21, 1985

o

Appendix'B to this letter contains a list of potential enforcement actions

based on the.NRC CAT inspection observations. These are being reviewed by the

Office of Inspection and Enforcement and the NRC Region I Office for

appropriate action. In addition, Region I will be following your corrective

action for deficiencies identified during this inspection.

In accordance with.10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room. No reply to this letter is

required at this time. You will be required to respond to these findings

after a decision is made regarding appropriate enforcement action.

Should you have any questions concerning this inspection, please contact us or

the Region I Office.

Sincerely, ,

/3/

James M. Taylor, Director

Office of Inspection and Enforcement

Enclosures:

1. Appendix A - Executive Summary

2. Appendix B - Potential Enforcement Actions

'3. Inspection Report

cc w/ enclosures: See next page

MN IE\

IE:RCPB IE:RCPB IE:D W DI IE:D/DIR

HWong RHeishman JGPartlow RHVollmer JMi a lor

05/7 /85 05/ /85 05/ /85 05/ /85 05 p /85

.

p -

,

Northeast Nuclear Energy Company -3- May 21, 1985

cc w/ enclosures:

Northeast Utilities Service Company Robert W. Bishop, Esq.

ATTN: Mr. V. Papadopoli, Supervisor Corporate Secretary

Construction Quality Assurance Northeast Utilities

Millstone Unit 3 P. O. Box 170

P. O. Box 328 Hartford, CT 06141

Waterford, CT 06385

Northeast Utilities Service Company Mr. Kevin McCarthy

ATTN: Mr. Edward J. Mroczka, Director

Vice President, Nuclear Operations Radiation Control Unit

P. O. Box 270 Department of Environmental

He.rtford, CT 06141 Protection

State Office Building

Northeast Utilities Service Company 165 Capital Avenue

ATTN: Mr. E. R. Foster, Director Hartford, CT 06106

Generation Construction

P. O. Box 270 Mr. T. Rebelowski

Hartford, CT 06141 Senior Resident Inspector Office

U.S. Nuclear Regulatory Commission

Northeast Utilities Service Company Millstone III

ATTN: Mr. R. T. Laudenat, Manager . P. O. Box 615

Generation Facilities Licensing Waterford, CT 06385

P. O. Box 270

Hartford, CT 06141

Northeast Nuclear Energy Company

ATTN: Mr. D. O. Nordquist, Manager of

Quality Assurance

P. O. Box 270

Hartford, CT 06141

Mr. Michael L. Jones, Manager

ProjectManagementDepartment

Massachusetts Municipal Wholesale

  • Electric Company

Post Office Box 425

Ludlow, Massachusetts 01056

Gerald Garfield, Esq.

Day, Berry & Howard

City Place

Hartford, CT 06103-3499

Mr. Maurice R. Scully, Executive Director

Connecticut Municipal Electric

Energy Cooperative

268 Thomas Road

I Groton, CT 06340

i

I

L.

., - _ ,. _- -_ _ _

~

.

t ,

~

, .' Northeast Nuclear Energy Company -4. May 21, 1985

_

DISTRIBUTION:

.~DCS.(Docket No. 50-443)

"-

~NRC PDR

Local-PDR

JMTaylor

RHVollmer-

JGPa~rtlow

BKGrimes>

-RFHeishman-_

HThompson

TMNovak

BDoolittle

MRushbrook~

BJYoungbloodl

AE00>

-

. g. OELD

~

NMSS: .

.RES

ACRS (10)

NSIC'

NTIS

Regional Administrators

R8ernero

-JPKnight

WRussell

TSpeis

ELJordan

~ CAT Team Members..

JAxelrad

Regional Division Directors

HBoulden, 01A

SECY.

-OPE

OCA-(3)

WDircks

HRDenton

Resident Inspector

_ _ _ - _ _ . _ _ _ _ _ _ - _ _ _ . . _ - _ _ - _ .___-___--_-___ _ ___- - ______-__ _ _ _ _ _ _ _ . _ __ _ __ _ -

APPENDIX A

EXECUTIVE SUMMARY

An announced NRC Construction Appraisal Team (CAT) inspection was conducted

at Northeast Nuclear Energy Company's Millstone Unit 3 during the period

February 19-March 1 and March 11-22, 1985.

Overall Conclusions

Hardware and documentation for construction activities were generally in

accordance with requirements and licensee commitments. However, the NRC

CAT did identify a number of construction program weaknesses that require

additional management attention. These include:

1. Control of work on systems and components subsequent to turnover from

Construction to the testing organization requires improvement. This is

indicated by the deficiencies found in the control of wiring changes, and

preventive maintenance deficiencies found in the mechanical and electrical

areas subsequent to turnover to the startup organization. Additional

attention is needed to ensure that missed maintenance activities are

evaluated as to the potential damaging effects on the components. These

findings indicate the need to reevaluate the controls applied to activi-

ties subsequent to system turnover from Construction to Operations.

2. A number of hardware deficiencies were identified which appear to have

been caused by a lack of effective communications between the design,

construction, and inspection groups. Design parameters were in some

cases not properly translated into inspection criteria. For example, pipe

supports had been installed and accepted by QC with dimensional tolerances

not in accordance with the design calculations. In addition, a lack of

thoroughness on the part of the design organization was identified.

Examples identified include: omission of the Residual Heat Removal System

from the pipe support " lugs-in-contact" review; wiring termination changes

made to drawings without the issuance of the necessary documents to

control the actual construction work; inadequate technical justification

for the acceptance of unmarked fasteners in certain motor control centers;

and conflicting details for a structural steel end connection.

3. A significant number of document control errors were found at both the

Quality Control and Construction drawings stations. This is of particular

concern in that the deficiencies in document control had been identified

previously, and the number of audits increased to monitor the situation.

In fact, a 100% audit of all drawing stations had been performed just

prior to the start of the NRC CAT inspection. The corrective actions

taken had not been effective, however.

!

l

,

A-1

_

I

.

4. A number of findings indicate that the effectiveness of Quality Control

inspection activities needs to be improved. These findings include the

area of piping as-built drawings, mechanical equipment foundation anchorage,

i structural steel connections (welded and bolted), piping support welding

(pipe straps and skewed fillet welds), and pipe support miscellaneous

i hardware (lock nut tightness, cotter pin installations, etc.). Also,

vendor deficiencies were identified in the areas of tank and heat

exchanger fillet welds (pressure boundary and supports), performance

of load indicating washers, and marking of fasteners.

The foregoing identified weaknesses require additional management attention

to assure that completed installations meet design requirements.

AREAS INSPECTED AND RESULTS

Electrical and Instrumentation Construction

The electrical and instrumentation samples inspected generally met the applicable

design requirements and installation specifications. Several discrepancies

were identified including some that will require additional management attention.

Numerous electrical separation discrepancies were identified in the Main

Control Board wiring installed by the vendor and as modified by design and

(

'

construction activities. Several areas were noted in which redundant electrical

division wires were in contact with each other.

Electrical separaticn criteria detailed in the Millstone Unit 3 FSAR had not

been met in many raceway and cable installations. However, lesser separation

may be acceptable based on recent tests. This matter is considered open

pending NRR review and evaluation.

During examination of Class IE cable ends, a number of terminations were

identified that were not in accordance with current design drawings. One

group of discrepancies pertains to incomplete implementation of design changes.

The second group relates to inadequate documentation of post-turnover wiring

changes.

Mechanical Construction

HVAC restraints, concrete expansion anchor installations, pipe wall thickness

and piping hydrostatic test records were found to be in general conformance

to design and procedural requirements.

Numerous discrepancies were identified in pipe support / restraints and mechani-

cal equipment foundation installations. A number of discrepancies were

observed between as-built drawings and piping configurations. Greater atten-

tion to detail during QC inspections appears necessary.

A need for more thorough engineering review activities, and additional

reinspection and/or reanalysis was observed. This need was indicated by:

unclear inspection criteria and inadequate engineering interface for pipe

support / restraint attachment locations; inadequate review of attachment lug

contact criteria; and a number of drafting errors.

A-2

l - . _ _ _ _ _ _ _ _ _ _ _ _ _ - _

r

The NNEC0 maintenance program and maintenance activities performed after

equipment turnover from Construction were considered to be inadequate. This

item had been previously identified, but corrective actions taken had not been

effective or timely.

Welding and Nondestructive Examination

Welding and nondestructive examination activities were gerorally found to be

conducted in accordance with the governing codes and specifi 3tions. However,

a number of examples were identified where completed structural telds in pipe

supports involving skewed welded connections did not have the weld sizes

specified by the Architect-Engineer. These undersized welds in skewed

connections should have been identified during the weld inspection process,

and their existence indicates a program weakness. The licensee has performed

an engineering evaluation concerning this problem and concluded that most of

these welds are adequate for the intended application. In the area of vendor

supplied tanks and heat exchangers a number of tanks were found to heve

undersized weld reinforcements in nozzle and manway welded jointt. In addition,

some tank supports were found to have deficient welds.

Civil and Structural Construction

In general, concrete quality, cadwelding and concrete material certification

were found to be acceptable. Rebar appeared to be placed in accordance with

the design drawings. However, the NRC CAT inspectors identified unauthorized

material in the building isolation joints (rattle spaces).

Structural steel member size and configuration were generally found to be

acceptable. A nember of steel connections in the Main Steam Valve Building

were found to be not in accordance with the design drawings. Based on testing

by the NRC CAT, problems were identified in the performance of load indicating

washers.

Material Traceability and Control ,

The licensee's material traceability and control program was found to be

acceptable, except for certain fastener hardware. Significant lack of

traceability was found for vendor fastener materials, including bolts for

mounting large pump motors, bolts for battery racks and bolts for inter-

connecting adjacent motor control center cabinets.

Design Change Control

Design change control was determined to be in accordance with site procedures

with the exception of timely updating of design documents with the latest

change information. A number of drawings were found to be overdue for updating

to include the latest design change requirements. In the area of design

document control, a significant number of document control errors were found at

site drawing stations used for construction work and QC acceptance. Weaknesses

were also identified in the use of yellow drawings and document control audits.

In addition, four cases of apparent inadequate corrective actions were noted

in both the document control and design change control areas.

A-3

7-.

.

Corrective Action Systems-

A weakness was:found in the corrective actions taken to control preventive

maintenance after components had been turned over for testing / operation. In'

addition, corrective actions applied to design change controls and document

control deficiencies had not been effective. Also, an-increasing number of

unresolved nonconformances was-found after turnover of system packages for.

. testing / operation. These matters require additional management attention.

m

I

t

t

l-

i

I

! A-4

l

[.

m

.

L. .

,

APPENDIX B

,-

POTENTIAL ENFORCEMENT ACTIONS-

.

'

As' a _ result of' the NRC CAT inspection of February 19 - March 1 and March 11-22,

'1985 at the Millstone Unit 3: site, the following items are being referred to

Region Itas-Potential Enforcement Actions! Section references are to the detailed

portion of the inspection report.

1. 10 CFR 50, Appendix B, Criterion III, as implemented by Northeast Utili-

ties Quality Assurance Program (NVQAP), QAP 3.0, requires that measures'

shall be established to assure that applicable' regulatory requirements are

correctly translated into specifications, drawings, procedures and -

' instructions.

Contrary to the above, at the time of this inspection, the licensee's =

! program for design control has not been adequate to assure that Class IE '

wiring configurations are in accordance with applicable design. As a

result of incomplete control'of electrical ' termination changes, a number

of existing installations may'not perfonn their intended function (Section

II.B.2.b.(6)).

2. 10 CFR 50, Appendix B, Criterion V, as implemented by NVQAP, QAP 5.0,

requires that activities affecting quality shall be prescribed by

documented instructions, procedures or drawings which include appropriate

quantitative or qualitative acceptance criteria.

Contrary to the above, the NRC CAT inspectors found, at the time of this

inspection, that the licensee's programs were not effectively implemented

-in that they:

a. Failed to adequately implement their post-turnover test and

l

inspection program

accordance to assure

with applicable that wiringSection

procedures. (changes were documented in

II.B.2.b.(6)).

b. Failed to identify conflicting allowable acceptance criteria between

the design organization and the inspection organization for pipe

supports / restraints (Section III.B.2).

3. 10 CFR 50, Appendix B, Criterion VI, as implemented by NUQAP, QAP 6.0,

requires in part that measures be established to control issue and

distribution of document changes to the prescribed locations.

Contrary to the above, during this inspection, the SWEC design document

control procedures were not adequately implemented in that numerous errors

in distribution, filing and updating of document record cards, design

change documents, drawings and specifications were found to exist in site

drawing stations used for plant construction and Quality Control inspec-

L tion (SectionVII.B.1).

(

4. 10 CFR 50, Appendix B, Criterion VII, as implemented by NUQAP, QAP 7.0,

. requires that measures be established to assure that purchased material,

equipment and services confonn to the procurement documents.

B-1

c

Contrary to the above, at the time of this inspection, the implementation

of SWEC's procedures were found to be ineffective in that vendor procured

tanks and heat exchangers were accepted and installed with deficient

welds (Section IV.B.1).

5. 10 CFR 50, Appendix B, Criterion VIII, as implemented by ?!UQAP, QAP 8.0,

requires that measures be established for the control of materials, parts

and components to prevent the use of incorrect or defective items.

Contrary to the above, at the time of this i.nspection the material

traceability and control of some fasteners., includirg busts for mounting

large pump motors, have not been adequate u essure the us9 of currect

material s.

6. .10 CFR 50, Appendix B, Criterion X, as implemented by NUQAP, QAP 10.0,

requires tnat a program for inspection of activities affecting quality be

established and executed to verify conformance with design documents.

Contrary to the above, at the time of this inspection, it was found that

the licensee's programs were not effectively implemented in that they:

a. Failed to ensure that safety-related pipe supports / restraints were

constructed in accordance with design requirements in that support

attachment locations were not installed as shown on design drawings

(Section III.B.2),

b. Did not assure that equipment foundation bolting connections were

installed in accordance with specified acceptance criteria and

requirements (Section III.B.5).

c. Have not assured that the specified weld sizes in skewed structural

pipesupportconnectionshavetherequiredweldsizes(Section

IV.B.1).

7. 10 CFR 50, Appendix B, Criterion XVI, as implemented by NUQAP, QAP 16.0,

requires that measures be established to assure that conditions adverse

to quality are promptly identified and corrected, including action to

avoid repetition.

Contrary to the above, at the time of this inspection, the licensee's

program of Quality Control Inspection had not provided adequate

procedural controls in that there was:

a. Failure to promptly identify and correct numerous separation

deficiencies in vendor or modified vendor wiring installations

withinthemaincontrolboards(SectionII.B.2.b(2)).

b. Failure to promptly perform effective corrective action to prevent

recurrence of nonconformances (Section VIII.B.1.b(1)).

c. Inadequate control of preventive maintenance after turnover for

testing / operating (SectionVIII.B.1.b.(2)).

d. Failure to apply effective corrective actions for document control

deficiencies (SectionVIII.B.1.b.(4)).

B-2