ML20199G559
| ML20199G559 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 10/31/1997 |
| From: | Todd F Public Service Enterprise Group |
| To: | |
| Shared Package | |
| ML20199G546 | List: |
| References | |
| NUDOCS 9711250209 | |
| Download: ML20199G559 (5) | |
Text
. . ,- .- ~ . . . . -. - _ . - . - . - -- . - - . -
DOCKET NO.: 50-354L ,
-UNIT: Hope Creek DATE: 11/06/97
-COMPLETED BY: F.-Todd
~ TELEPHONE: (609) 339-1316-OPERATING DATA REPORT-
- OPERATING STATUS 1 Reporting-Period October 1997: Hours in_ Report 745 Period 2: Currently _ Authorized 'ower Level _ (MWt) 3293
. Max l Dependable Capacity (MWe-Net) 1031 Design Electrical-Rating (MWe-Net) 1067 3 Power' level to which restricted (if any) _.(MWe Net)
None
,4 Reason For Restriction (if any)
This Month Yr To Cumulative Date 5 No..of hours reactor was critical 0 6058 79781 6 Reactor reserve shutdown hours 0.0 0.0 0.0 7 l Hours generator-on line 0 6058 78618 8 Unit reserve shutdown hours 0.0 0.0 0.0 9 Gross thermal-energy generated (MWH) C 18833746 250701993 10 Gross _ electrical energy generated (MWH) 0 6285370 83179583 11 Net electrical energy generated (MWH) 0 6008693 79488089 ,
12 Reactor Service f actor 0.0% 83.0% 83.7%
13 Reactor availability factor 0.0% 83.0% 83.7%
14 Unit Service Factor 0.0% 83.0% 82.5%
15 Unit Availability Factor 0.0% 83.0% 82.5%
'16 : Unit Capacity Factor (MDC) 0.0% 79.9% 80.9%
17 Unit Capacity _ Factor (DER) 0.0% 77.2% 78.2%
18 - Unit: Forced Outage Rate 0.0% 1.0% 4.1%
'19 Shutdowns scheduled over next 6 months (type,-date, du ra ti" .1)::
_20 [If shutdown atl end of report- period, estimated date of Startup: -11/25/97-9711250209 971117 PDR ADOCK 05000354 - '
c- R- PDR l 1
DOCKET NO., 50_-354 UNIT: Hope Creek DATE: 11/06/97 COMPLETED BY: F. Todd TELEPHCNE: (609) 339-1316 OPERATING DATA REPORT UNIT SHUTDOWNS AND POWER REDUCTIONS MONTH OCTOBER 1997 METHOD OF SHUTTIN G
DOWN THE TYPE REACTOR OR F= FORCED DURATIO REASON REDUCIN CORRECTIVE N G NO. DATE S= SCHEDULE (HOURS) (1) POWER ACTION / COMMENT s D (2) 1 10/1 S 745 Hrs C 2 Refuel Outage 10/31 A: F,quipment 11 Manual Eatlure 2: Mariu a l B: Maint or Test Scram C: Refueltr.g 3:
D: Regulatory Automatic Restrict!cn Scram L: Operator 4: Other Traintrig and Licensee Exam F: Administrative G: Operational Error H: Other in f.' ;
b
DOCKET NO. 50-354 UNIT: Hope Creek .
DATE: 11/06797 COMPLETED BY: F. Todd TELEPilONE: (609) 339-1316 !
AVERAGE DAILY UNIT POWER LEVEL MONTH OCTOBER 1997 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 0_ 17 0, 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 f, 22 0 7 0 23 0 0 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 9 28 0 13 0 29 0
.4 0 30 0 15 0 31 0 16 0
DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 11/06/97 COMPLETED BY: R. Ritzman TELEPHONE: (609) 339-1445 REFUELING INFORMATION MONTH OCTOBER 1997
- 1. Refueling information has changed from last month:
Yes X No
- 2. Scheduled date for next refueling (RF07): currently in refueling outage
- 3. Scheduled date for restart following refueling:
11/25/97 4A Will Technical Specification changes or other license amendments be required?
Yes __
No X B. Has the Safety Evaluation covering the COLR been reviewed by the Station Operating Review Committee (SORCi ?
Yes No X If no, when is it scheduled? 10/22/97
- 5. Scheduled date(s) for submitting proposed licensing action:
N/A
- 6. Important licensing considerations associated with refueling:
None
- 7. Number of Fuel Assemblies:
A. Incore 764 B. In Spent Fuel Storage 1708
- 8. Present lir ;nsed spent fuel storage capacity: 4006 Future spen'. fuel storage capacity: 4006
- 9. Date of last refueling that can be discharged to spent fuel pool assuming the present licensed capacity: 5/3/2006(EOC13)
(Doea allow for full-core 3ff-load)
(Assumes 244 bundle reload. every 18 months until then)
(Does not allow for smaller reloads due to improved fuel)
DOCKET NO.: 50-354 UNIT: llope Creek DATE: 11/06/97 COMPLETED BY: F. Todd TELEPilONE: (609) 339-1316 MONTHLY OPERATING
SUMMARY
HONTH OCTOBER 1997
- For the month of October, the Hope Creek Generating Station continued the seventh refueling outage.
!