Text
- - - _ -
. .. .. . .
> -
,. . .
' '
_ , s; -
e 2
.
15 JtJL 1988
I
Docket No. 50-333
Power Authority of the State of New York
James A. FitzPatrick Nuclear Power Plant
ATTN: Mr. Radford J. Converse
Resident Manager
P.O. Box 41
Lycoming, New York 13093
Subject: Inspection Report No. 50-333/88-11
This letter transmits the results of the routine inspection conducted by
Messrs. A. Luptak and R. Plasse of this office on May 1,1988 - June 17,
1988, at the J. A. FitzPatrick Nuclear Power Plant, Scriba, New York. Mr.
Luptak discussed the inspection findings with you and other members of your
staff at the conclusion of the inspection.
'In addition, we have reviewed your letter dated May 31, 1988, in response
to our letter dated April 29, 1988, referring to Inspection Report no.
'
88-04. Thank you for informing us of the corrective and preventive actions
documented in your letter. These actions will be examined during a future
.insrection of your Inservice Testing Program.
,
'
This letter requires no reply. We appreciate your cooperation.
Sincerely,
wet &y
Edward C. Wenzinger, Chief
Projects Branch No. 2
Division of Reactor Projects
Enclosure:
1. NRC Region I Inspection Report Number 50-333/88-11
-
0FFICIAL RECORD COPY IR FITZ 88-11 - 0001.0.0
8807250255 000715 07/12/88
PDR ADOCK 05000333 ik
Q PNU EOI
,
.
_ _ _ - _ - _ _ _ _ _ _ _
L ,
-
... . .
'
.. ..
, . Power' Authority of the-State
'
of New York 2
ggg
cc w/encls:
J.P. Bayne,- President
J.C. Brons, Executive Vice President-Nuclear Generation-
R.E. Beedle, Vice President Nuclear Support
-
S.S. Zulla, Vice President Nuclear Engineering
.R. Burns, Vice President Nuclear Operations
A. Klausmann,' Senior Vice President-Appraisal and Compliance
Services
R.L. Patch, Quality Assurance Superintendent-
G.H. Wilverding, Manager, Nuclear Safety Evaluation
.
Gerald C. Goldstein, Assistant General Counsel
,
- Department of Public Service, State of New York
State of New York, Department of Law
Public Document Room (PDR)
local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector
State of New York-
'
bec w/ encl:
Region I Docket Room (with concurrences)
~ Management Assistant, DRMA (w/o encls)
Section Chief, DRP
Robert J. Bores, DRSS
TI Coordinator, DRP
State Liaison Officer (SLO)
-H. Abelson, LPM, NRR
B. Clayton, EDO, Region I Coordinator
W. Cook, SRI, NMP1/2
P. Koltay, SRI, IP3
J. Strosnider, DRS
R: I: RP
JoMnson/rbl )henzinger
i
7/l1/88 7/]i/88
0FFICIAL RECORD COPY IR FITZ 88-11 - 0002.0.0
07/12/88
L