Correction to Request for Additional Information Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors (EPID-2020-LLA-0017)
ML20253A342
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/17/2020
From: Bhalchandra Vaidya
Plant Licensing Branch III
To: Bryan Hanson
Exelon Nuclear
Vaidya B
References
EPID L-2020-LLA-0017
Download: ML20253A342 (3)


Text

September 17, 2020 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear LaSalle County Station 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

LASALLE COUNTY STATION, UNITS 1 AND 2 CORRECTION TO REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO RENEWED FACILITY OPERATING LICENSES TO ADOPT 10 CFR 50.69, RISK-INFORMED CATEGORIZATION AND TREATMENT OF STRUCTURES, SYSTEMS, AND COMPONENTS FOR NUCLEAR POWER REACTORS (EPID L-2020-LLA-0017)

Dear Mr. Hanson:

By letter dated September 3, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20240A218), the U.S. Nuclear Regulatory Commission (NRC) staff issued the request for additional information (RAI) regarding your license amendment request dated January 31, 2020 (ADAMS Accession No. ML20031E699). The amendment would revise the renewed facility operating licenses to adopt 10 CFR [Title 10 of the Code of Federal Regulations] 50.69, Risk-informed categorization and treatment of structures, systems, and components for nuclear power reactors.

The NRC staff has identified that due to inadvertent error, the third paragraph in the NRCs letter stated that The draft request for additional information (RAI) is enclosed. It should read The request for additional information (RAI) is enclosed.

Additionally, the last sentence in the fourth paragraph stated that By email dated August 26, 2020, you committed to provide the responses to this request no later than September 30, 2020, for Question Nos. 1, 2, 8, 11, and 12, and October 22, 2020, for Question Nos. 3, 4, 5, 6, 7, 9, and 10. It should read, By email dated August 26, 2020, you committed to provide the responses to this request no later than 30 calendar days from the date of this letter for Question Nos. 1, 2, 8, 11, and 12, and no later than 45 calendar days from the date of this letter for Question Nos. 3, 4, 5, 6, 7, 9, and 10.

The correction does not change any of the RAIs. Based on the above change, the response dates for the RAIs would be October 3, 2020, for Question Nos. 1, 2, 8, 11, and 12, and October 18, 2020, for Question Nos. 3, 4, 5, 6, 7, 9, and 10.

B. Hanson If you have any questions, please contact me at 301-415-3308 or via e-mail at Bhalchandra.Vaidya@nrc.gov.

Sincerely,

/RA/

Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374 cc: Listserv

ML20253A342 *via e-mail OFFICE NRR/DORL/LPL3/PM* NRR/DORL/LPL3/LA* NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*

NAME BVaidya SRohrer (JBurkhardt for) NSalgado BVaidya DATE 09/14/2020 09/11/2020 09/16/2020 09/17/2020