Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company January 14, 2003
Davis-Besse Oversight Panel - Public Meeting January 2003 Purposes of This Meeting
- Inform the Public of the NRCs Oversight Panel Activities
- Discuss Licensees Progress on Implementing the Return to Service Plan 2
Davis-Besse Oversight Panel - Public Meeting January 2003 AGENDA
- Introduction and Opening Remarks
- Summary of Dec. 10th & Dec. 23rd Public Meetings
- Discussion of NRCs Restart Checklist and Status of NRC Inspections
- Licensee Presentation on the Status of Their Return to Service Plan
- Adjourn NRC meeting with FENOC
<break>
- Public Comments and Questions of NRC
- Adjourn Meeting 3
Davis-Besse Oversight Panel - Public Meeting January 2003
SUMMARY
OF DEC. 10, 2002 PUBLIC MEETING
- Topics Discussed
- Management & Human Performance Excellence Plan
- Operations Root Cause
- Restart Preparations
- Containment Health Plan
- System Health Assurance
- Plant Program Reviews
- 0350 Action Progress
- FENOC Alignment for Sustained Operations
- QA Oversight of FENOC Alignment
- Transcripts of the Dec. 10, 2002, meetings will be available on our web site. http://www.nrc.gov/
4
Davis-Besse Oversight Panel - Public Meeting January 2003
SUMMARY
OF DEC. 23, 2002 PUBLIC MEETING
- Topics Discussed
- System Health Assurance
- Open Design Questions
- Transcripts of the Dec. 23, 2002, meeting will be available on our web site. http://www.nrc.gov/
5
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Adequacy of Root Cause Determination
- Penetration cracking and reactor pressure vessel corrosion
- Organizational, programmatic and human performance issues 6
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Adequacy of Safety Significant Structures Systems and Components
- Reactor pressure vessel head replacement
- Containment vessel restoration
- Structures, systems and components inside containment
- Emergency core cooling system and containment spray system sump
- Systems outside containment 7
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Adequacy of Safety Significant Programs
- Corrective action program
- Operating experience program
- Quality audits and self-assessments of programs
- Boric acid corrosion management program
- Reactor coolant system unidentified leakage monitoring program
- In-service inspection program
- Modification control program
- Radiation protection program 8
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Adequacy of Organizational Effectiveness and Human Performance
- Adequacy of root causes
- Adequacy of corrective actions
- Effectiveness of corrective actions 9
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Readiness for Restart
- Systems readiness for restart
- Operations readiness for restart
- Test program development and implementation 10
Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist
- Licensing Issue and Confirmatory Action Letter Resolution
- Resolve three limited ASME code relief requests
- Meet with the NRC to obtain restart approval 11
Davis-Besse Oversight Panel - Public Meeting January 2003 CONTINUING NRC INSPECTIONS
- Organizational Effectiveness and Human Performance
- System Health Reviews
- Safety Significant Program Effectiveness
- Resident Inspection 12
Davis-Besse Oversight Panel - Public Meeting January 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO January 14, 2003, 7:00 pm EST Purpose of Meeting:
Inform the Public of the NRCs Oversight Panel Activities 13
Davis-Besse Oversight Panel - Public Meeting January 2003 GOALS
- One of the goals of this meeting is to receive comments / questions from all interested members of the public. To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.
14
Davis-Besse Oversight Panel - Public Meeting January 2003 AGENDA
- Introduction and Opening Remarks
- Summary of Vessel Head Degradation Issue
- Summary of Todays Public meeting
- Comments/Questions from local members of the public 15