ML040490212
| ML040490212 | |
| Person / Time | |
|---|---|
| Site: | Summer |
| Issue date: | 01/28/2004 |
| From: | Landis K NRC/RGN-II/DRP/RPB5 |
| To: | Byrne S South Carolina Electric & Gas Co |
| References | |
| Download: ML040490212 (55) | |
Text
V. C. Summer Nuclear Station SCE&G Attendees
- Steve Byrne - Senior Vice President
- Jeff Archie - Plant Manager
- Dave Lavigne - General Manager Organizational Effectiveness
- Alan Torres - Manager Planning / Outage
- Ron Clary - Manager Nuclear Licensing
- Brad Stokes - Manager Design Engineering
- Larry Bennett - Plant Support Engineering Supervisor
Purpose of Meeting
- Refuel - 14 Results
- Corrective Action Program Update
- Equipment Reliability Program Overview
Refuel -14 General Overview Alan Torres
Refuel-14 Goal Status
- No Significant Safety Events (Actual 0)
- Duration - 36 days (Actual 46 Days)
- No Industrial Safety Events (Actual 2)
RF- 14
- Total Work
- MWRs - Scheduled 764 / Emergent 292
- STPs - Scheduled 1174 / Emergent 42
- PMs - Scheduled 2602 / Emergent 8
- ECRs - Scheduled 55 / Emergent 11
- Total of 4948 Documents Worked
- Scope Growth of 7.13%
Major Work Activities
- Reactor Vessel
- Ten Year ISI
- Bare metal visual inspections - Head/BMI
- Main Generator Inspection
- ILRT of the Reactor Building
- A Train Electrical Maintenance
- B CCW Heat Exchanger Repair and Coating
- Repair and Coat all 3 Auxiliary Condensers
- C RCP Motor Replacement and Seal Work
Refuel-14 Modifications
- Modifications
- RHR Pump Seal (Concern for Leakage)
- Complete RHR Miniflow Switch Relocation (EQ)
- RHR Vent Addition (Helps Reduce Dose)
- CW Pump Trip Circuitry (Operator Work Around)
- Feedwater Heater Level Transmitter Logic Change (Operational Challenge)
- Gravity Boration Flow Path (Operator Work Around)
Brief Overview of RHR Project
- A RHR Pump Modification
- Spacer Coupling
- Upper & Lower Hub Assembly
- Dose Estimated 2.75 REM (Actual 0.725 REM)
- A RHR Vent Addition
- Dose Estimated 1.1 REM (Actual 0.590 REM)
Modified 8X20 WD/WDF Bearing Housing 18 by 18 seal opening Support stand with an 18 X 18 opening
The Spacer Coupling Upper (Driver)
Hub Assembly Lower (Pump)
Hub Assembly
Outage Challenges
- Seal Injection Indications
- 40 Hours Additional Work to Critical Path
- Dose of 5.8 REM
- Main Generator Hydrogen Leaks
- 55 Hours Delay to Startup and Critical Path
- Water Clarity Issues Prior to Reload
- 66 Hour Delay for Core Reload to Critical Path
- Main Turbine Vibration During Startup
- 16 Hour Delay to Tie to the Grid
Conclusions
- We Conducted a Safe Outage
- No Safety Significant Events
- Two Minor Personnel Injuries
- No Events During Startup
- Presently No Significant Challenges for Extended Run
CORRECTIVE ACTION PROGRAM Dave Lavigne
CORRECTIVE ACTION PROGRAM (CAP)
- CER Status
- CAP History
- Risk Review
- CAP Changes
CORRECTIVE ACTION PROGRAM (CAP)
A Look At The Numbers:
CER STATISTICS 1998 1999 2000 2001 2002 2003 CERs Initiated 516 1527 1907 2431 3925 4526 Average Per Day: 3.035 4.1836 5.2247 6.6786 10.783 12.434
- CERs Open: 5 27 37 99 389 1378 Percent (%) Open: 0.97% 1.768% 1.94% 4.072% 9.911% 30.45%
- Open CERs have a status of Screened, Unscreened or Ready for Approval.
CORRECTIVE ACTION PROGRAM (CAP)
CAP History
- NRC PI&R Inspection, March 2001.
- Corrective Action Program Acceptable, however:
- Corrective Actions not well documented or completed in a timely manner.
- Risk insights not used when classifying issues.
- Not effectively using repetitive condition identification.
CORRECTIVE ACTION PROGRAM (CAP)
CAP HISTORY (continued)
- NRC PI&R Inspection, March 2002
- Improvements noted in corrective action process, however:
- CERs not always generated at threshold expected by management.
- Human performance issues not always addressed.
- Need more management presence at screening committee meetings.
CORRECTIVE ACTION PROGRAM (CAP)
CAP HISTORY (continued)
- WANO/INPO Peer Review, May 2003
- Station including more lo-level deficient conditions in the CAP.
- Increasing backlogs in CAP.
- Multiple extensions of corrective actions.
- Lack of acceptance of corrective actions.
CORRECTIVE ACTION PROGRAM (CAP)
CAP HISTORY (continued)
- VCS Internal Assessments
- QA GAP Analysis (August 2003)
VCS Program Meets Industry Stds.
- Root Cause analysis on repeat events (September 2003)
- Management ownership and oversight.
- Need better screening review of identified conditions.
RISK INSIGHTS
- CERs Reviewed by PSA group for Risk Significance
- Results Reported in Quarterly Trend Report
- Presented at VP Performance Indicator Meeting
CAP CHANGES CAP Changes (Contd)
- Established Management Review Team (MRT)
-Composed of GMs and Managers.
- Review Repetitive Events
- Review Immediate Actions
- Establish CER Ownership
- Monitor Due Date Extensions
CAP Changes (Contd)
- MRT to Review Deleted CERs
- Separated Significance Determination from Condition Evaluation
- Established Priority Vehicle for Actions
CAP Changes (Contd)
- Reinforced Expectations
- Unit Evaluators
- Managers
- Corrective Action Group
CORRECTIVE ACTION PROGRAM (CAP)
SUMMARY
- Continue to adjust CAP to meet/exceed industry stds.
- Using Risk Insights to understand plant C/A issues
- Mgmt team committed to self identify and learn from C/A process
V. C. Summer Nuclear Station Equipment Reliability Improvement Overview Larry Bennett
Overview Previous Activity Future plans
Benchmarking NEI Equipment Reliability Benchmarking in 2002 6 Plants Visited for Best Practices
- Prioritization
- Long Range Planning
- Plant Health Committee
Self Assessment
- Gap Analysis to INPO AP-913 Completed in November 2002
- Areas Noted for Improvement:
- System Health Reports do not effectively drive corrective actions and communicate long range plans
- Long term planning for SSCs needs improvement
- Equipment problems are not effectively prioritized
- Critical component classifications not well established
- PM program improvements needed
INPO Equipment Performance Assist Visit
- Conducted in November of 2002
- Validated Self Assessment
- Developed Action Plans for Focus Areas
- Prioritization
- PM Program
- Predictive Maintenance
Plant Health Committee
- PHC Created in November of 2002
- Engineering, Operations, Maintenance, Scheduling, HP, Chemistry
- Prioritization of Equipment Issues Completed January 2003
- PHC Focus List Developed, Communicated to Site
- Initial list had 15 focus issues
- Presently have 10 focus issues
- 8 removed, 3 added
2003 INPO Plant Assessment Areas for Improvement in Equipment Reliability
- Plant trips due to equipment issues
- Unresolved equipment issues
- Some reoccurring equipment issues
Plans for 2004 Equipment Reliability Improvement Project
Equipment Reliability Improvement Project (ERIP) 4 Integrated Phases of Work Aligned with Recognized Industry Standards:
- NEI Standard Nuclear Performance Model
- INPO AP-928, Work Management Process
- INPO AP-913, Equipment Reliability Process
Equipment Reliability Improvement Project ERIP Used at:
- Susquehanna
- Calloway
- Columbia
- Farley - in progress
- Hatch - in progress
ERIP Change Goal Desired Outcome:
Lay a solid foundation on which to build a living long-term maintenance strategy where our processes and people are preventing equipment failures.
ERIP Scope of Work Phase 1 Scoping and Identification of Critical Components Phase 2 Preventive Maintenance Implementation and Feedback Improvement Phase 3 Preventive Maintenance Basis and Maintenance Optimization Phase 4 Performance Monitoring and Prioritization Improvement
ERIP - From Project to Process
- Active Craft Feedback and Ownership
- Proactive Engineering
- High Level of Equipment Reliability
- Optimizing Availability of SSCs.
- Optimizing Maintenance Effectiveness.
- Reduced Generation Lost
- Reduced Operation and Maintenance Cost
Conclusions Steve Byrne