Ltr 08/23/17 Dresden Nuclear Station, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2017004; 05000249/2017004
ML17236A074
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/23/2017
From: Meghani V L
NRC/RGN-III/DRS/EB1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2017004
Download: ML17236A074 (6)


See also: IR 05000237/2017004

Text

August 23, 2017

Mr. Bryan Senior VP, Exelon Generation Co., LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT: DRESDEN NUCLEAR STATION, UNIT 2NOTIFICATION OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION REPORT 05000237/2017004; 05000249/2017004

Dear Mr. Hanson:

On October 30, 2017, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed October 30November 3, 2017. Experience has shown that this inspection is resource intensive both for the NRC inspector and your staff. In order to minimize the impact to your onsite resources, and to ensure a productive inspection for both sides, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group identifies information necessary to ensure that the inspector is adequately prepared. The second group identifies the information the inspector will need upon arrival at the site. It is important that all of these documents are up-to-date, and complete, in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. We have discussed the schedule for inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. D. Walker, of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Mr. V. Meghani at 630-829-9751, or via e-mail at Vijay.Meghani@nrc.gov. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number. This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR

Sincerely,/RA/ Vijay Meghani, Reactor Inspector Engineering Branch 1 Division of Reactor Safety Docket Nos. 50237; 50249 License Nos. DPR19; DPR25

Enclosure:

Baseline Inservice Inspection Document Request cc: Distribution via LISTSERV