Letter Sequence Meeting |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML070370281, ML073100027, ML073510180, ML080360067, ML080430700, ML080500171, ML080530256, ML081010450, ML081010451, ML081120502, ML081700294, ML081720078, ML081760295, ML082040065, ML082050462, ML082100425, ML082810470, ML083120308, ML083240224, ML083250083, ML090130718, ML090340528, ML090720951, ML090760630, ML091320366, ML092020345, ML092430520, ML092440518, ML092460495, ML092460496, ML092460497, ML092460498, ML092460500, ML092540483, ML092680057, ML12319A076, ML13044A498
|
MONTHYEARML0631104352006-11-0707 November 2006 Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes Project stage: Request 05000260/LER-2007-001, Re Automatic Turbine Trip and Reactor Scram Due to Equipment Failure During Performance of the Main Generator Rheostat Test2007-03-0202 March 2007 Re Automatic Turbine Trip and Reactor Scram Due to Equipment Failure During Performance of the Main Generator Rheostat Test Project stage: Request ML0711300782007-04-18018 April 2007 Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Supplemental Response to Requests for Additional Information (RAI) Project stage: Supplement ML0711503662007-04-24024 April 2007 Units 1, 2, & 3 - Fire Protection Program - Post-Fire Operator Manual Actions Project stage: Request ML0711503712007-04-24024 April 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Steam Dryer Evaluations Project stage: Request ML0712905652007-05-16016 May 2007 Withholding Information from Public Disclosure, Response to Nuclear Regulatory Commission (NRC) Request for Additional Information - Round 12 for Browns Ferry EPU: Supplemental to SBWB-64 Project stage: RAI ML0716303492007-06-15015 June 2007 Meeting with the Tennessee Valley Authority Concerning the Status of Browns Ferry Nuclear Plant, Units 1, 2 and 3, Steam Dryer Review Project stage: Meeting ML0718700242007-07-0303 July 2007 Technical Specifications (TS) Change TS-461 - Modification of Restart Large Transient Testing License Condition 2. (G) 2 - Supplement 1 Project stage: Request ML0717801902007-07-0505 July 2007 Request for Additional Information for Extended Power Uprate - Round 13 (TS-431 and TS-418 Project stage: RAI ML0719004762007-07-10010 July 2007 Meeting with the Tennessee Valley Authority (TVA) Concerning the Pending ACRS Meeting on the Browns Ferry Extended Power Uprate Project stage: Meeting ML0721501562007-07-18018 July 2007 Slides from Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting ML0721303712007-07-27027 July 2007 Technical Specifications Changes TS-431 and TS-418, Extended Power Uprate - Steam Dryer Evaluations Project stage: Request ML0721303752007-07-31031 July 2007 CDI Report No. 07-05NP, Revision 0, Finite Element Model for Stress Assessment of Browns Ferry, Unit 1, Steam Dryer to 250 Hz Project stage: Request ML0721400442007-08-0808 August 2007 Summary of Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting 05000259/LER-2007-005, Regarding Automatic Reactor Scram Due to Turbine Trip as a Result of Invalid High Level in Moisture Separator Drain Tank2007-08-0808 August 2007 Regarding Automatic Reactor Scram Due to Turbine Trip as a Result of Invalid High Level in Moisture Separator Drain Tank Project stage: Request ML0723602572007-08-21021 August 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Steam Dryer Limit Curves Project stage: Request ML0724805472007-08-31031 August 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure Project stage: Request ML0727606602007-10-0909 October 2007 Request for Additional Information for Extended Power Uprate - Round 14 (TS-418) Project stage: RAI ML0728902372007-10-18018 October 2007 Request for Withholding Information from Public Disclosure Concerning Round 13 Request for Additional Information for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263 and MD5264) Project stage: RAI ML0729603112007-10-22022 October 2007 Technical Specification (TS) Changes TS-431 & TS-418, Extended Power Uprate - EPU Large Transient Testing Project stage: Request ML0731000272007-11-0909 November 2007 Request for Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418-S) Project stage: Other ML0732303482007-11-15015 November 2007 Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure APLA-35/37 Project stage: Request ML0733304832007-11-21021 November 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Preliminary Findings on Steam Dryer Stress Analysis Project stage: Request 05000296/LER-2007-003, Leak in an ASME Class I Code Reactor Pressure Boundary Pipe2007-11-21021 November 2007 Leak in an ASME Class I Code Reactor Pressure Boundary Pipe Project stage: Request ML0735101802007-12-14014 December 2007 Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Schedule Regarding Analysis for Steam Dryers Project stage: Other ML0734607572007-12-19019 December 2007 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac No. MD5262, MD5263 and MD5264) Project stage: Withholding Request Acceptance ML0735400102008-01-25025 January 2008 Summary of Meeting with Tennessee Valley Authority on Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264), Browns Ferry Units 1, 2, and 3 Project stage: Meeting ML0801504182008-01-25025 January 2008 (Public Version) - Summary of December 10, 2007 Meeting with TVA on Steam Dryer Portion of the Extended Power Uprate Review Project stage: Meeting ML0803205212008-01-25025 January 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) Response to Round 15 Request for Additional Information (RAI) - APLA-38/40, SRXB-71, and SRXB-72 Project stage: Request ML0803600672008-01-25025 January 2008 Steam Dryer RAI 15 Status, Slides Project stage: Other ML0802501652008-01-30030 January 2008 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263, and MD5264) Project stage: Withholding Request Acceptance ML0803805602008-01-31031 January 2008 Technical Specifications (TS) Change TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 Request for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Request ML0804307002008-02-11011 February 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Schedule Regarding EPU Project stage: Other ML0804304462008-02-11011 February 2008 Notification of Potential Part 21 Report Power Supply Unit Is Limited at Elevated Temperatures Project stage: Request ML0803503812008-02-14014 February 2008 Summary of Meeting with Tennessee Valley Authority - on Extended Power Uprate Review Project stage: Meeting ML0806501012008-02-21021 February 2008 Response to Round 16 Request for Additional Information SRXB-73 Project stage: Request ML0805302562008-02-21021 February 2008 Unit 1 - Technical Specifications (TS) Change TS-431 - Extended Power Uprate (EPU) - Fuels Methods Commitments Project stage: Other ML0804506472008-02-27027 February 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0803506982008-02-29029 February 2008 Request for Additional Information for Extended Power Uprate - Round 16 (TS-431 and TS-418) (TACs MD5262, MD5263, MD5264) Project stage: RAI ML0807104982008-03-0606 March 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change TS-418 and TS-431 - Extended Power Uprate (EPU) - Response to Round 16 Request for Additional Information (RAI) - SRXB-74/86 and SRXB-87 Through SRXB-90 Project stage: Request ML0811205102008-03-20020 March 2008 Summary of March 20, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264) - Slides Project stage: Meeting ML0810104502008-04-0404 April 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 and Round 16 Requests for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Other ML0810104512008-04-0404 April 2008 Technical Specifications (TS) Changes TS-431 and TS-418 Extended Power Uprate (EPU) BFN Steam Monitoring Plan Project stage: Other ML0817602952008-04-0909 April 2008 Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Confirmation of Commitment Completions Project stage: Other ML0811205022008-04-16016 April 2008 CDI Incoming Letter Dated April 16, 2008 Regarding NRC Presentation Entitled, Tennessee Valley Authority Browns Ferry Nuclear Plant - Extended Power Uprate Steam Dryers Project stage: Other ML0811302312008-04-17017 April 2008 Public Slides - Summary of April 17, 2008, Meeting Regarding Steam Dryer Portion of the Extended Power Uprate Review, Project stage: Meeting ML0811200332008-04-30030 April 2008 Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Withholding Information from Public Disclosure for Round 15 Fuels Responses Project stage: Withholding Request Acceptance ML0812806272008-05-0101 May 2008 Technical Specifications Change TS-418, Extended Power Uprate Supplemental Response to Round 16 Request for Additional Information - SRXB-87 & SRXB-89 Project stage: Supplement ML0812804712008-05-0202 May 2008 Request for Additional Information for Extended Power Uprate - Round 17 Project stage: RAI ML0805001712008-05-0202 May 2008 Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418) Project stage: Other 2007-07-05
[Table View] |
December 15, 2010, Browns Ferry, Units 1, 2 & 3, Summary of Meeting with Tennessee Valley Authority Extended Power Uprate Plans (TAC Nos. MD5262, MD5263 & MD5264)| ML110190410 |
| Person / Time |
|---|
| Site: |
Browns Ferry  |
|---|
| Issue date: |
02/11/2011 |
|---|
| From: |
Gratton C Plant Licensing Branch II |
|---|
| To: |
|
|---|
| Gratton C, NRR, DORL, 415-1055 |
| Shared Package |
|---|
| ML110190403 |
List: |
|---|
| References |
|---|
| TAC MD5262, TAC MD5263, TAC MD5264 |
| Download: ML110190410 (5) |
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 February 11, 2011 LICENSEE: Tennessee Valley Authority FACILITY: Browns Ferry Nuclear Plant, Units 1, 2, and 3 SUB~'ECT:
SUMMARY
OF DECEMBER 15, 2010, MEETING WITH TENNESSEE VALLEY AUTHORITY ON EXTENDED POWER UPRATE PLANS FOR BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 (TAC NOS. MD5262, MD5263, AND MD5264)
On December 15, 2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA, the licensee) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the resumption of the extended power uprate (EPU) licensing action for Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3, confirm the outstanding scope of the project, and to discuss the licensee's plans to address the outstanding technical issues. A list of attendees is provided in the Enclosure.
The licensee's presentation included a history of the EPU review for the BFN units, a discussion of the plant modifications that have been completed or are planned as part of this project, and a discussion of the open technical issues that need to be addressed before the project can be completed. The licensee closed the presentation with a discussion of the proposed schedule for the important milestones related to the project. The licensee's presentation material can be found at Agencywide Documents Access and Management System Accession No. ML103490867 (this file supersedes a previous version of the presentation material that contained a typographical error).
During the presentation, the licensee stated that it plans to replace the existing steam dryers in each of the BFN units with new dryers through a contract with General Electric Hitachi. TVA also discussed actions they are taking to address containment accident pressure (CAP) issues at the BFN site. The licensee stated that they have performed comprehensive engineering analyses using NRC staff's Draft Guidelines to identify and evaluate strategies to address CAP for all events. The licensee also stated that they are working with the Boiling-Water Reactor Owners Group (BWROG) to formulate implementation strategies for the NRC CAP Guidelines.
The licensee shared its current CAP evaluation results with the NRC staff as they relate to the BFN EPU project, indicating that CAP credit will only be needed for the short-term portion of the loss-of-coolant-accident event. The licensee stated that they plan to submit a letter to the NRC in the first calendar quarter of 2011 with the key assumptions that support the planned strategy to eliminate or mitigate CAP for all events. The NRC staff encouraged the licensee to work with the BWROG to quantify uncertainties associated with CAP analyses.
The staff and the licensee exchanged clarifying questions regarding the licensee's approach to resume the review of the BFN Units 1, 2, and 3 EPU as outlined in the presentation materials, and the efforts by the staff to clarify the crediting of CAP in accident analyses. The licensee indicated that technical basis for addressing CAP for accident analyses will be included in future submittals to the NRC.
-2 Members of the public were in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-1055, or christopher.gratton@nrc.gov.
Christopher Gratton, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, and 50-296
Enclosure:
List of Attendees cc w/encls: Distribution via Listserv
MEETING WITH TENNESSEE VALLEY AUTHORITY EXTENDED POWER UPRATE, BROWNS FERRY 1, 2, 3 December 15, 2010 9:00 a.m. - 11 :00 a.m.
U.S. Nuclear Regulatory Commission Two White Flint North 10-A1 11555 Rockville Pike Rockville, Maryland Attendees Name orQamzatlon Contact Nurn ber Christopher Gratton NRC/DORL 301-415-1055 William M. Bentley TVA 256-729-7893 Marie Gillman TVA 423-751-4884 Ashok Bhatnagar TVA 423-751-6506 Peter Gaillard TVA 423-751-2088 Gordon Arent TVA 423-751-2233 Rod Krich TVA 423-751-3628 Tom Matthews TVA 423-751-2687 Ray Dennis Westinghouse 724-940-8326 Steven Hammer Xcel-MNGP 763-295-1300 Michael Jesse Exelon 610-765-5528 John Rommel Exelon 630-657-3351 Jigar Patel NRRlDRA X3109 Robert Dennig NRRIDSS X1156 Naeem Iqbal NRR/DRA X3346 Arthur Kevin Heller NRRlDSS X6472 i Muhammad Razzaque NRRlDSS X2882 John Huang NRRlDCI X1417 Audrey Klett NRC X0489 Benjamin Parks NRRlDSS X6472 Charles Norton NRRlDORL X7818 Andrew Proffitt NRRlDSS X1418 Shih-Liang Wu NRRlDSS X3284 Mathew Panicker NRRlDSS X2986 Doug Broaddus NRRlDORL X8124 Chakrapani Basavaraju NRRlDE X1221 I Allen Howe NRRIDORL X1453 Richard Lobel NRRlDSS X2865 I Ahsan Sallman NRRlDSS X2380 Swagata Som NRRlDE X8491 TomAlexion NRRIDPR X1326 Patricia Cambell GE -
Ed Schrull GE -
Enclosure
- 2 Judy Sneeden GE -
Mike James GE -
Jairo Pinzon Scientech -
John Fields Xcel Energy -
Roger Pedersen NRR/DIRS X3162 Denise Anderson Westinghouse -
Vijay Kumar Westinghouse -
- 2 Members of the public were in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-1055, or christopher.gratton@nrc.gov.
IRA!
Christopher Gratton, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, and 50-296
Enclosure:
List of Attendees cc w/encls: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDss8cvb MPanici<er, NRR LPL2-2 Rlf Nlqbal, NRR N8anfilippo, EDO RidsAcrsAcnw_MailCTR AHelier, NRR CBasavaraju, NRR RidsNrrDortLpl2-2 MRazzaque, NRR RidsNrrDorl RidsNrrPMBrownsFerry JHuang, NRR RLobel, NRR RidsNrrLABClayton AKlett, NRR A8aliman, NRR RidsOgcRp Resource BParks, NRR 880m, NRR RidsRgn2MailCenter CNorton, NRR TAlexion, NRR C8teger, NRR AProfitt, NRR RPedersen, NRR JPatel, NRR 8Wu, NRR o
ADAMS Accession No. PKG ML110190403 Notice ML103215218 ummary ML110190410 Han d outs ML103490867 OFFICE DORULPL2-2/PM DORULPL2-2/LA DORULPL2-2/BC DORULPL2-21PM NAME ICGratton BClayton DBroaddus (TOrf for) CGratton DATE 101120/11 01120/11 02/11/11 02/11/11 OFFICIAL RECORD COpy