UNITED STATES NUCLEAR REGULATORY COMMISSION ber 26, 2019
SUBJECT:
EDWIN I. HATCH UNITS 1, 2 - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000321/2019411 AND 05000366/2019411
Dear Mr. McGavin:
On August 15, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Edwin I. Hatch Nuclear Plant, Units 1 and 2, and discussed the results of this inspection with Mr. Dean, and other members of the plant staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented one finding of very low security significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest this violation or the significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Nuclear Security and Incident Response; the Director, Office of Enforcement; and the NRC resident inspector at the Edwin I. Hatch Nuclear Plant.
If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Nuclear Security, and Incident Response; and the NRC resident inspector at the Edwin I. Hatch Nuclear Plant This letter and its enclosure will be made available for public inspection and copying at https://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room, in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Binoy Desai, Chief Plant Support Branch Division of Reactor Safety Docket Nos.: 05000321 and 05000366 License Nos.: DPR-57 and NPF-5 Enclosure:
Inspection Report 05000321/2019411 and 05000366/2019411 cc: see page 3 cc:
Allie M. Meadows Site Security Manager Southern Nuclear Operating Co., Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 Michael P. Long Fleet Nuclear Security Operations Manager Southern Nuclear Operating Co., Inc.
P. O. Box 1295 Birmingham, AL 35201-1295 Lisa B. Hogg Fleet Security Project Manager Southern Nuclear Operating Co., Inc.
P. O. Box 1295 Birmingham, AL 35201-1295 Erin Garrison Fleet Security Project Manager Southern Nuclear Operating Co., Inc.
P. O. Box 1295 Birmingham, AL 35201-1295 Steven M. Shipman Fleet Security Project Manager Southern Nuclear Operating Co., Inc.
P. O. Box 1295 Birmingham, AL 35201-1295 Edwin D. (Sonny) Dean Southern Nuclear Operating Co., Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 ML19269C442 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS/PSB RII:DRS/PSB RII:DRP/BR2 RII:DRS/PSB NAME J. Wallo B. Desai A. B. Desai Bl ML19269C DATE 9/ *24 /2019 9/ 25* /2019 9/ 25 */2019 9/ 26 /2019 E-MAIL COPY YES NO YES NO YES NO YES NO