June 19, 2007Mr. Biff Bradley, DirectorRisk Assessment Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
ACCEPTANCE FOR REVIEW OF TOPICAL REPORT (TR) NUCLEARENERGY INSTITUTE 04-10, REVISION 1, "RISK-INFORMED TECHNICAL SPECIFICATION INITIATIVE 5B, RISK-INFORMED METHOD FOR CONTROL OF SURVEILLANCE FREQUENCIES" (TAC NO. MD5333)
Dear Mr. Bradley:
By letter dated April 19, 2007, the Nuclear Energy Institute (NEI) submitted for U.S. NuclearRegulatory Commission (NRC) staff review TR NEI 04-10, Revision 1, "Risk-Informed Technical Specification Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies." The NRC staff has performed an acceptance review of TR NEI 04-10, Revision 1. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by October 31, 2007, and issue its draft safety evaluation by April 14, 2008. The NRC staff estimates that the review will require approximately 230 staff hours including project management time. The review schedule milestones and estimated review costs were agreed upon by an exchange of emails between yourself and Tanya Mensah on May 23, 2007, and May 24, 2007. In accordance with the letter dated January 10, 2003, (Agencywide Documents Access andManagement System Accession No. ML030100090), the fee branch has waived the Section 170.21 of Title 10 of the Code of Federal Regulations fees associated with this TRreview.Sincerely,/RA/Stacey L. Rosenberg, ChiefSpecial Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor RegulationProject No. 689 cc: See next page June 19, 2007Mr. Biff Bradley, DirectorRisk Assessment Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
ACCEPTANCE FOR REVIEW OF TOPICAL REPORT (TR) NUCLEARENERGY INSTITUTE 04-10, REVISION 1, "RISK-INFORMED TECHNICAL SPECIFICATION INITIATIVE 5B, RISK-INFORMED METHOD FOR CONTROL OF SURVEILLANCE FREQUENCIES" (TAC NO. MD5333)
Dear Mr. Bradley:
By letter dated April 19, 2007, the Nuclear Energy Institute (NEI) submitted for U.S. NuclearRegulatory Commission (NRC) staff review TR NEI 04-10, Revision 1, "Risk-Informed Technical Specification Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies." The NRC staff has performed an acceptance review of TR NEI 04-10, Revision 1. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by October 31, 2007, and issue its draft safety evaluation by April 14, 2008. The NRC staff estimates that the review will require approximately 230 staff hours including project management time. The review schedule milestones and estimated review costs were agreed upon by an exchange of emails between yourself and Tanya Mensah on May 23, 2007, and May 24, 2007. In accordance with the letter dated January 10, 2003, (Agencywide Documents Access andManagement System Accession No. ML030100090), the fee branch has waived the Section 170.21 of Title 10 of the Code of Federal Regulations fees associated with this TRreview.Sincerely,/RA/Stacey L. Rosenberg, ChiefSpecial Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor RegulationProject No. 689 cc: See next page DISTRIBUTION
- PUBLICPSPB Reading FileRidsNrrCpnb RidsNrrAplaRidsNrrCptbRidsNrrEgca RidsNrrDprRidsNrrDprPspbRidsNrrPMTMensah RidsNrrLADBaxleyRidsAcrsAcnwMailCenterRidsOgcMailCenter SRosenberg (Hardcopy)RGroverTTjaderADAMS ACCESSION NO.: ML071620171 NRR-106OFFICEPSPB/PMPSPB/LAAPLA/BCITSB/BCPSPB/BCNAMETMensahDBaxleyMRubinTKobetzSRosenberg DATE6/ 18 /076/14 /076/ 1 /076/ 19 /076/ 19 /07OFFICIAL RECORD COPY 3/8/07Nuclear Energy InstituteProject No. 689 cc:Mr. Anthony Pietrangelo, Vice PresidentRegulatory Affairs Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 arp@nei.org Mr. Jack Roe, DirectorOperations Support Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jwr@nei.org Mr. Charles B. Brinkman Washington Operations ABB-Combustion Engineering, Inc.
12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 brinkmcb@westinghouse.com Mr. Gary L. Vine, Executive DirectorFederal and Industry Activities, Nuclear Sector EPRI 2000 L Street, NW, Suite 805 Washington, DC 20036 gvine@epri.com Mr. James Gresham, ManagerRegulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355 greshaja@westinghouse.com Ms. Barbara Lewis Assistant Editor Platts, Principal Editorial Office 1200 G St., N.W., Suite 1100 Washington, DC 20005 Barbara_lewis@platts.com Mr. Alexander Marion, Executive DirectorNuclear Operations & Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 am@nei.org Mr. Jay Thayer, Vice PresidentNuclear Operations Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jkt@nei.org Mr. John Butler, DirectorSafety-Focused Regulation Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jcb@nei.org Mike Melton, Senior Project Manager1776 I Street, NW, Suite 400 Washington, DC 20006-3708 man@nei.orgMr. James H. Riley, Director Engineering Nuclear Energy Institute 1776 I Street, NW Washington, DC 20006-3708 jhr@nei.org