December 4, 2008
Dr. Steven Reese, Director Radiation Center Oregon State University 100 Radiation Center Corvallis, OR 97331-5903
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR OREGON STATE UNIVERSITY
Dear Dr. Reese:
By letters and associated affidavits dated August 22, 2008 and September 17, 2008, you and Dr. Keith E. Asmussen of General Atomics (GA), respectively, requested that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
Attachment 2 to letter dated June 30, 2008, entitled, Oregon State University Response to RAI Regarding Conversion Amendment, Oregon State University TRIGA Reactor dated April 22, 2008
The GA affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reason:
If released, the GA-owned information would create substantial harm to GA by providing competitors and other parties whose interest may be adverse to GA with detailed technical trade secret and commercial information. GA has a very significant investment of resources over many years in the development of this information. This information has been held in confidence by GA and is of a type customarily held in confidence by its owner. The information was transmitted to the NRC in confidence and was marked accordingly. This information is not available from public sources.
We have reviewed your letters and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the following document will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended:
Attachment 2 to letter dated June 30, 2008, entitled, Oregon State University Response to RAI Regarding Conversion Amendment, Oregon State University TRIGA Reactor dated April 22, 2008
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the Nuclear Regulatory Commission (NRC). You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the
NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-3934.
Sincerely, /RA/
William C. Schuster IV, Project Manager Research and Test Reactors, Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Docket No. 50-243
cc: Keith E. Asmussen
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the Nuclear Regulatory Commission (NRC). You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the
NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-3934.
Sincerely, /RA/
William C. Schuster IV, Project Manager Research and Test Reactors, Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Docket No. 50-243
cc: Keith E. Asmussen DISTRIBUTION
- PUBLIC RTR r/f RidsNrrDprPrta RidsNrrDprPrtb
ADAMS ACCESSION NO.: Package: ML083240720 Incoming: ML081770334, ML082350345, ML082400521, & ML082670542 Approval Letter: ML083240732 OFFICE DPR/PRTA/PM DPR/PRTA/LA DPR/PRTA/BC NAME WSchuster wcs EBarnhill eeb KBrock kmb DATE 12/4/08 11/24 11/24/08 OFFICIAL RECORD COPY Keith E. Asmussen, Director Licensing, Safety and Nuclear Compliance General Atomics 3550 General Atomics Court San Diego, CA 92121