License Amendment Request for Revision to Technical Specification Core Operating Limits Report for Realistic Large Break LOCA (Loss-of-coolant Accident) Analysis - Withdrawal of Request for Withholding
ML12088A080
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/21/2012
From: Burton C
Progress Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
HNP-12-042
Download: ML12088A080 (2)


Text

Progress Energy Christopher L Burton Vice President Harris Nuclear Plant Progress Energy Carolinas, Inc.Serial: HNP-12-042 10 CFR 50.90 AR 2 1 -2012 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Shearon Harris Nuclear Power Plant, Unit No. 1 Docket No. 50-400 / Renewed License No. NPF-63

Subject:

References:

License Amendment Request for Revision to Technical Specification Core Operating Limits Report for Realistic Large Break LOCA [loss-of-coolant accident]

Analysis -Withdrawal of Request for Withholding of Peak Cladding Temperature Value 1. Letter from C.L. Burton to the U.S. NRC, "License Amendment Request for Revision to Technical Specification Core Operating Limits Report References for Realistic Large Break LOCA Analysis Response to Request for Additional Information," Serial HNP- 12-023 dated February 23, 2012, ADAMS Accession No. ML12067A182

2. ANP-301 1 Q1 (P), Revision 000, entitled "Harris Nuclear Plant Unit 1 Realistic Large Break LOCA Analysis," February 2012.Ladies and Gentlemen:

In Reference 1, Carolina Power & Light Company (CP&L), doing business as Progress Energy Carolinas, Inc., submitted an affidavit dated February 16, 2012, executed by Gayle F. Elliot, Manager, Product Licensing, for AREVA NP Inc. requesting that certain information contained in Reference 2 be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390.CP&L, on behalf of AREVA NP Inc., requested withholding of the HNP Result Peak Cladding Temperature

[2071 'F] in Reference 2 that has subsequently been determined to be releasable to the public. Therefore, CP&L, on behalf of AREVA NP Inc., withdraws the request for withholding of that parameter and value.P.O. Box 165 New Hill, NC 27562 T> 919.362.2502 F> 919.362.2095 U.S. Nuclear Regulatory Commission Page 2 HINP-12-042 This document contains no new Regulatory Commitments.

Please direct any questions regarding this submittal to Dave Corlett at (919) 362-3137.Sincerely, CLB/jrc cc: Mr. J. D. Austin, NRC Sr. Resident Inspector, HNP Ms. A. T. Billoch Colon, NRC Project Manager, HNP