ML18036B215

From kanterella
Revision as of 00:20, 18 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Responds to NRC 930225 Ltr Re Violations Noted in Insp Repts 50-259/93-02,50-260/93-02 & 50-296/93-02.C/As:containment Purge & SBGT Sys Evaluated & Recommendations Included in Sys Procedures for Appropriate Recurrence Control
ML18036B215
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/24/1993
From: Zeringue O
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9303300135
Download: ML18036B215 (13)


See also: IR 05000259/1993002

Text

acczz.~PgggggAX,DIgW~VTIQN, sYisŽACCESSION NBR:9303300135, DOC.DATE: 93/03/24 NOTARIZED:

NO ACIL:50-259

Browns Ferry Nuclear Power Station, Unit 1, Tennessee 50-260 Browns Ferry Nuclear Power Station, Unit 2, Tennessee 50-296 Browns Ferry Nuclear Power Station, Unit 3, Tennessee AUTH.NAME AUTHOR AFFILIATION

ZERINGUE,O.J.

Tennessee Valley Authority RECIP.NAME

RECIPIENT AFFILIATION

Document Control Branch (Document Control Desk.)DOCKET 05000259 05000260 05000296 SUBJECT: Responds to NRC 930225 ltr re violations

noted in insp repts 50-259/93-02,50-260/93-02

&50-296/93-02.C/As:containment

purge&SBGT sys evaluated&recommendations

included in sys procedures

for appropriate

recurrence

control.DISTRIBUTION

CODE: IE01D COPIES RECEIVED:LTR

ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice

of Violation Response NOTES: RECIPIENT ID CODE/NAME HEBDONiF WILLIAMSgJ.

INTERNAL: ACRS AEOD/DSP/TPAB

DEDRO t NRR/DRCH/HHFBPT

NRR/DRSS/PEPB

NRR PMAS/ILPB2

G FIL 02 RGN2 FILE 01 EXTERNAL EG&G/BRYCE

i J~H~NSIC COPIES LTTR ENCL 1 1 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1-1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME ROSS,T.AEOD/DEIB AEOD/TTC NRR/DORS/OEAB

NRR/DRIL/RPEB

NRR/PMAS/ILPBl

NUDOCS-ABSTRACT

OGC/HDS3 RES MORISSEAU,D

NRC PDR COPIES LTTR ENCL 1 1 1 1'1 1 1 1 1 1 1 1 1 1 1 1.1 1 1 0 NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE IIELP US TO REDUCE WASTE!CONTACT TIIE DOCUMEN'I'ONTROL

DI>V, ROOM Pl-37 (EXT.504-2065)TO ELIMINATE YOUR NAME FROM DISTRIBUTlON

LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24

Tennessee Valley Autttority, Post Olfice Box 2OOO.Decatur, Alabama 35609-WOO O.J."Ike" Zeringue Vice PresldenlBrowns

Perry Nuclea Pia~t MAR 34 1993 U.S.Nuclear Regulatory

Commission

ATTN: Document Control Desk Washington, D.C.20555 Gentlemen:

In the Matter of Tennessee Valley Authority Docket Nos.50-259 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)-NRC INSPECTION

REPORT 50-259, 50-260, 296/93-02 REPLY TO NOTICE OF VIOLATION (NOV)This letter provides TVA's reply to the NOV transmitted

by letter from Paul J.Kellogg to M.0.Medford dated February 25, 1993.In the transmitted

letter, NRC cited TVA with a technical specifications

violation.

This violation had three examples for failure to conduct required surveillance

tests.Example 1 discussed a failure to perform the Unit 2 refueling crane prerequisite

surveillance

test prior to fuel movement.Example 2 identified

a missed halogenated

hydrocarbon

test on the Unit 2 train B CREV unit.Example 3 characterized

a foreman that missed a prerequisite

signoff.As described in the enclosures

of this letter, TVA agrees that the violation occurred as stated.Enclosure 1 provides TVA's"Reply to the Notice of Violation" (10 CFR 2.201).280i2i 9303300i35

930324 PDR ADDCK 05000259 8'PDR~(p0

U.S.Nuclear Regulatory

Commission

eR 2,4 l993 If you have any questions regarding this reply, please telephone G.D.Pierce at (205)729-7566.Sincer'ely, (i'Z(((i(g(.

0 J.Zeringue.Enclosure

cc (Enclosure):

NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35611 Mr.Thierry M.Ross, Project Manager U.S.Nuclear Regulatory

Commission

One White Flint, North.11555 Rockville Pike Rockville, Maryland 20852 Mr.B.A.Wilson, Project Chief U.S.Nuclear Regulatory

Commission

Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

s

,)EHCLOSURE Tennessee Valley Authority Browns Ferry Huclear Plant (BFH)Reply to Hotice of Violation (HOV)Inspection

Report Humber 50-25 260 2 6 93-02 RESTATEMENT

OF VIOLATION"Technical Specification 6.8.1, Procedures, requires that written procedures

shall be established, implemented, and maintained

covering surveillance

and test activities

and the activities

recommended

in Appendix A of Regulatory

Guide 1.33, Revision 2, February,1978.

Appendix A of Regulatory

Guide 1.33 includes administrative

procedures

for performing

maintenance.

Contrary to the above, these requirements

were not met for the following three examples: Technical Specification 4.10.D requires the Reactor Building crane operability

surveillance, Surveillance

Instruction

0-4.10.D, be performed prior to the handling of new fuel.Between January 10 and January 18, 1993 new fuel was handled with the Reactor Building crane: without first performing

this surveillance.

This was identified

by the licensee on January 27, 1993.2.Site Standard Practice 6.50, Post-Maintenance

Testing, Section'3.1.2 requires that post-maintenance

testing shall be sufficiently

comprehensive

to ensure that corrective

and/or preventive

maintenance

work does not adversely affect equipment operability.

On November 28, 1992, a seven day limiting condition for operation was entered,to

perform maintenance

on the Control Room Emergency Ventilation

Unit B.The unit was breached and internal charcoal trays removed during this maintenance

activity.Following its replacement

on November 29, 1992, Surveillance

Instruction

0-4.7.E.3.B

was not performed as required to verify the maintenance

activity did not adversely affect its operability.

This was identified

by the licensee on December 30, 1992.3.Site Standard Practice 6.2, Maintenance

Management

System, provides for the planning and performance

of work orders.This instruction

was not followed when on February ll, 1993, an NRC inspector identified

work being conducted on the High Pre'ssure Coolant'Injection

system using Work Order 93-00507-1

without the job pre-requisites

being signed by the foreman as having been verified.This is a Severity Level IV Violation (Supplement

I)applicable

to all three units."

~2 REPLY TO EXAMPLE 1 l.Reason for Example 1 This event was a result of ambiguous or missing instructions

as to who should signoff a prerequisite

verification

step 4.3.1 of General Operating Instruction

for new fuel operations.

As a contributing

factor to this event, there was a lack of formal guidance to determine the status of completed SIs.Knowledge of whether or not an SI had been performed is not necessarily

information

that the refuel floor shift manager or mechanical

foreman would have available.

Nevertheless, the refuel floor'shift

manager signed off the step after the mechanical

foreman stated that SI had been performed.

2.Corrective

Steps Taken and Results Achieved New fuel receipt and inspection

activities

involving use of the overhead crane to handle fuel bundles and spent fuel casks were immediately

suspended.

The reactor building crane surveillance

to check and inspect the overhead crane on the refuel floor was performed and successfully

completed.

GOIs were revised to identify work control as the required signoff organization

to verify SI completion.

Operations

personnel were instructed

to verify the latest performance

of SIs through work control.3.Corrective

Steps That[have been or]Will Be Taken To Prevent Recurrence

No further actions are required to preclude recurrence

of this violation.

4.Date When Full Compliance

Will Be Achieved TVA considers that full compliance

was met when Operations

personnel were instructed

to verify the latest performance

of SIs through work control and when the GOIs were revised on March 12, 1993.

REPLY TO EXAMPLE 2 Reason for Example 2 This event was a result of issuing the work order without sufficient

details and insufficient

procedural

controls which allowed inappropriate

removal of the charcoal adsorber tray.This resulted in a lack of a detailed maintenance

procedure for the disassembling

of the CREV units.Therefore, no disassembly

or special requirements

was provided in the System, Instrument

Maintenance

Index (SIMI).This lack of a maintenance

procedure affected both the planners and the craftsmen in the performance

of their work activities.

A contributing

factor to this event is that the calibration

of the temperature

instrument

is a new preventive

maintenance

activity.The SIMI documents generally provide special requirements

and configuration

changes involved in calibration

of a component, and the SIMI document was reviewed during the preparation

of the work order.However, at the time of the activity (or event), the referenced

SIMI for this work plan did not contain any special notes or disassembly

information.

Consequently, the work plan did not include sufficient

instructions

for disassembling

the CREV unit.As with the work order planners, the craftsmen reviewed the applicable

SIMI document.Since the SIMI document did not contain any specific configuration

control information, the craftsmen also presumed that no configuration

changes were required.Consequently, the charcoal adsorber trays were removed to gain access to a temperature

instrument

without documenting

the activity as a configuration

change as required by the procedure.

2.Corrective

Steps Taken and Results Achieved Upon being informed of the condition, Operations

personnel declared the CREV train B inoperable, and a seven-day limiting condition for operation (LCO)was entered.A halogenated

hydrocarbon

test was initiated and satisfactorily

completed after which operability

of CREV train B was reestablished.

The applicable

SIMI document was revised to include information

on the configuration

changes associated

with calibrating

of the temperature

instrument.

Preventive

maintenance

task files were revised to include specific steps for disassembling

of the CREV units.

Training was conducted with maintenance

personnel concerning

the circumstances

surrounding

this event.The containment

purge and standby gas treatment systems were evaluated, and recommendations

were included in these system procedures

for appropriate

recurrence

control.Finally, procedures

for performing

both troubleshooting

and configuration

control of instruments

and electrical

equipment were revised.These revisions ensure that intrusive disassembly

of major plant equipment is no longer allowed without proper administrative

controls.3.Corrective"Steps That[have been or]Will Be Taken To Prevent Recurrence

No further actions are required to preclude recurrence

of this violation.

4..Date When Full Compliance

Will Be Achieved TVA considers that full compliance

occurred when appropriate

procedures

were revised on March 5, 1993.REPLY TO EXAMPLE 3 l.Reason For Example 3 This violation example is the result of a lack of attention to details.Electrical

maintenance

personnel were disconnecting

the electric operator on a motor operated valve in support of mechanical

maintenance

activities.

The craftsman signed off step 1.0 of the work instructions.

This signature affirmed that the craftsman reviewed and understood

the precautions/limitations

and work instructions.

The next step in'the work instructions

(1.1)required a Foreman/Designee

to sign off that the prerequisites

of the instructions

have been met.However, the craftsman,did

not sign off the step as the designee or obtain a foreman's signature prior to proceeding

to the next step.Contributing

factors for this oversight are: (1)In other work instructions, the step which requires a concurrence

signature that the prerequisites

have been met is generally the foreman's responsibility.

In the work instruction, there is no option for a designee to sign off that the prerequisites

were met.Therefore, the craftsman did not sign off step 1.1 of this work instruction

as'I

(.

'l the designee.(2)Even though the individual

who was the foreman for this event has received an orientation

on BFN expectations

for foreman activities, the foreman had just been promoted for the Unit 2 refueling outage.Therefore, he was not fully aware of all the responsibilities

of the position.2.Corrective

Steps Taken and Results Achieved Work activities

on this MOV repair were immediately

suspended.

The foreman on this work activity was interviewed

and subsequently

the foreman resigned from the position.A meeting was conducted with electric maintenance

foremen and craftsmen to emphasize the need to pay attention to details and to emphasize work expectations

during outages.3.Corrective

Steps That[have been or]Will Be Taken To Prevent Recurrence

No further actions are required to preclude recurrence

of this violation.

4.Date When Full Compliance

Will Be Achieved TVA considers that full compliance

was met when the individual

resigned the position and after the work expectation

meeting was conducted.

[-