UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 October 21, 2013 Mr. Eric Site Vice President
FirstEnergy Nuclear Operating Company Beaver Valley Power Station P. O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT: BEAVER VALLEY POWER STATION
- NRC TEMPORARY INSTRUCTION 2201/004, "INSPECTION OF IMPLEMENTATION OF INTERIM CYBER SECURITY MILESTONES 1-7," REPORT 05000334/2013407 AND 05000412/2013407
Dear Mr. Larson:
On September 13, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed a security temporary instruction inspection at your Beaver Valley Power Station, Units 1 and 2. The inspection covered the implementation of interim milestones associated with your cyber security program, as outlined in your approved cyber security plan (CSP) and described in Temporary Instruction (TI) 2201/004, "Inspection of Implementation of Interim Cyber Security Milestones 1-7." The enclosed inspection report documents the inspection results, which were discussed on September 13, 2013, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license related to the implementation of interim cyber security milestones. The inspection was conducted in accordance with NRC TI 2201/004, "Inspection of Implementation of Interim Cyber Security Milestones 1-7." The team reviewed selected procedures and records, observed activities, and interviewed personnel.
The report documents two violations for which t he NRC is exercising enforcement discretion.
The NRC is not taking enforcement action for these violations because they meet the criteria established in an NRC Memorandum from Barry C. Westreich, Director, Cyber Security Directorate, Office of Nuclear Security and Incident Response, to each regional office and Director, Division of Reactor Safety, Subject: Enhanced Guidance for Licensee Near-Term Corrective Actions to Address Cyber Security Inspection Findings and Licensee Eligibility for
"Good-Faith" Attempt Discretion dated July 1, 2013 (ADAMS Accession Number ML13178A203). Consistent with the NRC Memorandum, you should inform Keith Young, the inspection team leader, in the Region I Office at 610-337-5293, when you complete corrective actions associated with these violations.
Enclosure contains Sensitiv e Unclassified Non-Safeguards Information. When separated from enclosure, the transmittal document is decontrolled. In accordance with Title 10 of the Code of Federal Regulation (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Managem ent System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will
not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the
affidavit requirements for your response.
Sincerely,
/RA/ John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety
Docket Nos. 50-334; 50-412 License Nos. DPR-66; NPF-73 Enclosure:
Inspection Report Nos. 05000334/2013407 and 05000412/2013407 w/Attachment: Supplemental Information
cc w/o encl; wo/OUO-SRI: Distribution via ListServ cc w/encl; w/OUO-SRI: D. Craine, Manager, Nuclear Security D. Allard, Director, PA DEP M. Bear, State Liaison Officer, State of Ohio
ML13294A508 (Cover letter) ADAMS ACCESSION NUMBER: ML13294A501 (Cover letter w/enclosure) NonPublic Designation Category: MD 3.4 NonPublic A.3 Cover Letter SUNSI Review X Non-Sensitive Sensitive X Publicly Available Non-Publicly Available Cover Letter w/Enclosure SUNSI Review Non-Sensitive X Sensitive Publicly Available X Non-Publicly Available OFFICE RI/DRS RI/DRS NAME KYoung JRogge DATE 10/7/13 10/17/13 Distribution w/encl; w/OUO-SRI: R. Albert, NSIR C. Johnson, NSIR S. Coker, NSIR B. Desai, DRS, RII R. Skokowski, DRS, RIII M. Haire, DRS, RIV G. West, NSIR M. King, DRS, RII R. Daley, DRS, RIII G. Miller, DRS, RIV N. Coleman, OE
Distribution w/o encl; w/o OUO-SRI: W. Dean, RA (R1ORAMAIL Resource) D. Lew, DRA (R1ORAMAIL Resource) D. Roberts, DRP (R1DRPMAIL Resource)
M. Scott, DRP (R1DRPMAIL Resource)
R. Lorson, DRS (R1DRSMAIL Resource)
J. Trapp, DRS (R1DRSMAIL Resource)
G. Hunegs, DRP B. Bickett, DRP G. Stock, DRP
A. Dugandzic, DRP D. Spindler, DPR, SRI E. Carfang, DRP, RI P. Garrett, DRP, AA J. Rogge, DRS
K. Young, DRS D. Rich, RI OEDO
RidsNrrPMBeaverValley Resource
RidsNrrDorlLpl1-2 Resource ROPreports Resource