IR 05000361/2013004

From kanterella
Revision as of 16:37, 11 May 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
IR 05000361-13-004 and 05000362-13-004, 6/24/2013 - 9/23/2013, San Onofre Nuclear Generating Station - NRC Integrated Inspection Report
ML13308C438
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 11/04/2013
From: Lantz R E
NRC/RGN-IV/DRP/RPB-D
To: Peter Dietrich
Southern California Edison Co
Lantz R
References
IR-13-004
Download: ML13308C438 (12)


Text

November 4, 2013

Mr. Peter Dietrich Senior Vice President and Chief Nuclear Officer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674

-0128

SUBJECT: SAN ONOFRE NUCLEAR GENERATING STATION

- NRC INTEGRATED INSPECTION REPORT 05000361/2013004 and 05000362/2013004

Dear Mr. Dietrich:

On September 23, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the San Onofre Nuclear Generating Station Units 2 and 3 facility. The enclosed inspection report documents the inspection results which were discussed on September 17, 2013, with Mr. Rich St. Onge , Director, Nuclear Regulatory Affairs , and other members of your staff.

The inspections examined activities conducted under your license as they relate to safety and compliance with the Commission

's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings were identified during this inspection.

By letter dated June 12, 2013, Southern California Edison (SCE)

submitted a Certification of Permanent Cessation of Power Operations to the NRC certifying that Units 2 and 3 have permanently ceased power operations (ADAMS Accession No. ML131640201). On June 28 and July 22, 2013, SCE certified that all fuel had been permanently removed from the Unit s 3 and 2 reactors, respectively (ADAMS Accession Nos. ML13183A391 and ML13204A304). On September 3, 2013, the NRC notified SCE that the Operating Reactor Assessment Program had ceased and that implementation of the Decommissioning Power Reactor Inspection Program began, effective July 23, 2013 (ADAMS Accession No.

ML13246A435). U N I T E D S T A T E S N U C L E A R R E G U L A T O R Y C O M M I S S I O N R E G I O N I V1600 EAST LAMAR BLVD A R L I N G T O N , T E X A S 7 6 0 1 1-4511 In accordance with 10 CFR 2.390 of the NRC's

"Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ B. Hagar for Ryan E. Lantz, Chief Project Branch D Division of Reactor Projects Docket Nos.: 50

-361, 50-362 License Nos: NPF

-10, NPF-15 Enclosure: Inspection Report 05000361/201300 4 and 05000362/201300 4 w/ Attachment: Supplemental Information cc w/ encl: Electronic Distribution