IR 05000456/2014008

From kanterella
Revision as of 12:48, 11 May 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
IR 05000456-14-008 & 05000457-14-008; 01/21/2014 - 03/27/2014; Braidwood Station, Units 1 and 2; Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
ML14087A444
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 03/27/2014
From: Daley R C
Engineering Branch 3
To: Pacilio M J
Exelon Generation Co, Exelon Nuclear
Dariusz Szwarc
References
IR-14-008
Download: ML14087A444 (16)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532

-4352 March 27, 2014 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Co., LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2 EVALUATION S OF CHANGES, TESTS, AND EXPERIMENTS AND PERMANENT PLANT MODIFICATIONS BASELINE INSPECTION REPORT 05000 456/20 1 4008; 05000 457/20 14008

Dear:

Mr. Pacillio:

On March 27, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed an Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications inspection at your Braidwood Station, Units 1 and 2. The enclosed inspection report documents the inspection results which were discussed on March 27, 2014, with Mr. P. Raush and other members of your staff. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

The NRC inspectors did not identify any findings or violations of more than minor significance.

In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 50

-456; 50-457 License Nos. NPF

-72; NPF-77 Enclosure:

Inspection Report 05000456/2014008; 05000457/2014008 w/Attachment: Supplemental Information cc w/encl: Distribution via ListServŽ U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No: 50-456; 50-457 License No

NPF-72; NPF-77 Report No:

05000 456/20 1 4008; 05000 457/20 1 4008 Licensee: Exelon Generating Company, LLC Facility: Braidwood Station, Units 1 and 2 Location: Braceville, IL Dates: January 21 through March 27, 2014 Inspectors:

D. Szwarc, Senior Reactor Inspector N. Féliz Adorno, Reactor Inspector I. Hafeez, Reactor Inspector Approved by:

Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety 1 Enclosure

SUMMARY OF FINDINGS

IR 05000 456/20 1 4008, 05000 457/20 1 4008; 01/21/2014

- 0 3/2 7/2014; Braidwood Station, Units 1 and 2; Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications.

This report covers a two-week announced baseline inspection on evaluations of changes, tests, and experiments and permanent plant modifications. The inspection was conducted by Region III based engineering inspectors.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG

-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

A. N RC-Identified and Self-Revealed Findings

Cornerstone: Initiating Events

No findings of significance were identified.

B. Licensee-Identified Violations

No violations of significance were identified.

2

REPORT DETAILS

REACTOR SAFETY

Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity 1R17 Evaluation

s of Changes, Tests, and Experiments and Permanent Plant Modifications (71111.17)

.1 Evaluation of Changes, Tests, and Experiments

a. Inspection Scope

The inspectors reviewed seven safety evaluations performed pursuant to Title 10, Code of Federal Regulations (CFR) 50.59 to determine if the evaluations were adequate and that prior NRC approval was obtained as appropriate. The inspectors also reviewed 13 screenings where licensee personnel had determined that a 10 CFR 50.59 evaluation was not necessary. The inspectors reviewed these documents to determine if:

the changes, tests, and experiments performed were evaluated in accordance with 10 CFR 50.59 and that sufficient documentation existed to confirm that a license amendment was not required; the safety issue requiring the change, tests and experiment was resolved; the licensee conclusions for evaluations of changes, tests, and experiments were correct and consistent with 10 CFR 50.59; and the design and licensing basis documentation was updated to reflect the change.

The inspectors used, in part, Nuclear Energy Institute (NEI) 96-07, "Guidelines for 10 CFR 50.59 Implementation," Revision 1, to determine acceptability of the completed evaluations, and screenings. The NEI document was endorsed by the NRC in Regulatory Guide 1.187, "Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments," dated November 2000. The inspectors also consulted Part 9900 of the NRC Inspection Manual, "10 CFR Guidance for 10 CFR 50.59, Changes, Tests, and Experiments."

This inspection constituted seven samples of evaluations an d 13 samples of screenings as defined in IP 71111.17-04.

b. Findings

No findings of significance were idenfied.

.2 Permanent Plant Modifications

a. Inspection Scope

The inspectors reviewed seven permanent plant modifications that had been installed in the plant during the last three years. This review included in

-plant walkdowns for portions of the modified diesel generator governor booster; backup power supplies for the steam generator power operated relief valves; isolation valves in the safety injection system; temporary scaffolds; and electrical circuits related to high energy line break (HELB) in the diesel generator rooms, miscellaneous electric rooms, and engineered safety features switchgear rooms.

The modifications were selected based upon risk significance, safety significance, and complexity. The inspectors reviewed the modifications selected to determine if:

the supporting design and licensing basis documentation was updated; the changes were in accordance with the specified design requirements; the procedures and training plans affected by the modification have been adequately updated; the test documentation as required by the applicable test programs has been updated; and post-modification testing adequately verified system operability and/or functionality. The inspectors also used applicable industry standards to evaluate acceptability of the modifications. The list of modifications and other documents reviewed by the inspectors is included as an attachment to this report.

This inspection constituted seven permanent plant modification samples as defined in IP 71111.17-04.

b. Findings

No findings of significance were identified.

OTHER ACTIVITIES

(OA)

4OA2 Problem Identification and Resolution

.1 Routine Review of Condition Reports

a. Inspection Scope

The inspectors reviewed several corrective action process documents that identified or were related to 10 CFR 50.59 evaluations and permanent plant modifications. The inspectors reviewed these documents to evaluate the effectiveness of corrective actions related to permanent p lant modifications and evaluations of changes, tests, or experiments. In addition, corrective action documents written on issues identified during the inspection were reviewed to verify adequate problem identification and incorporatio n of the problems into the corrective action system. The specific corrective action documents that were sampled and reviewed by the inspectors are listed in the attachment to this report.

b. Findings

No findings of significance were identified.

4OA6 Meetin gs

.1 Exit Meeting

Summary O n March 2 7, 2014 , the inspector s presented the inspection results to Mr. P. Raush and other members of the licensee staff. The licensee personnel acknowledged the inspection results presented.

.2 Interim Exit Meeting

On February 20, 2014, the inspectors presented the inspection results to Mr. J. Bashor and other members of the licensee staff.

.3 Interim Exit Meeting

O n February 7, 2014, the inspector s presented the inspection results to Mr. M. Kanavos , and other members of the licensee staff. The inspectors confirmed that all proprietary material reviewed during the inspection was returned to the licensee staff.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION KEY POINTS OF CONTAC

T Licensee

M. Kanavos, Plant Manager
M. Marchionda, Plant Manager
J. Bashor, Engineering

Director

A. Ferko, Operations Manager
R. Belair, Mechanical Design Engineering Manager
P. Raush, Regulatory Assurance

Manager

D. Riedinger, Engineering Training
G. Wilhelmsen, Design Engineering Manager
M. Abbas, NRC coordinator

Nuclear Regulatory Commission

J. Benjamin, Senior Resident Inspector
R. Daley, Chief, Reactor Safety, Engineering Branch 3
E. Duncan, Chief, Reactor Projects, Branch 3

LIST OF ITEMS OPENED, CLOSED AND DISCUSS

ED Opened , Closed, and Discussed

None

LIST OF DOCUMENTS REVIEWED The following is a list of documents reviewed during the inspection.

Inclusion on this list does not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that selected sections of portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report.

CFR 50.59 EVALUATIONS

Number Description or Title

Date or Revision

BRW-E-2011-122 Installation of Backup Power Supplies for the Steam Generator Power Operated Relief Valves October 21, 2011

BRW-E-2012-0 85 Change In-Core Decay Time for A1R16

April 13, 2012

BRW-E-2012-120 Eliminating Action 3.3.y.D from TRM 3.3.y

May 30, 2012

BRW-E-2012-126 Install Time Delayed Auto-Restart for U

-1 (U-2) VD Fans in Support of HELB Mitigation Strategy

August 12, 2013

BRW-E-2012-155 Lake Screen House Traveling Screen Level Control September 7, 2012

BRW-E-2012-156 Install Time Delay Auto

-Restart for U

-1 (U-2) VX Fans in Support of

HELB Mitigation Strategy January 31, 2013

BRW-E-2012-186 Abnormal Component Position Sheet for Closing the Isolation Valves to the MSIV

Hydraulic Accumulator Manifolds' Relief Valves September 11, 2012

CFR 50.59 SCREENINGS

Number Description or Title

Date or Revision BRW-S-2011-0 84 Retention of a Temporary Scaffold Installed in the 2A RHR Heat Exchanger Room Beyond 90 Days

June 9, 2011

BRW-S-2011-0 88 Revised NPSH Required Value for the CV Pumps

June 23, 2011

BRW-S-2011-097 Incorporate Time Delay Relay into 1

& 2 VD Fans High Differential Pressure Trip Circuit Due to Turbine Building High Energy Line Break (HELB)

July 14, 2011

BRW-S-2011-138 Revision to UFSAR Section 9.2.2.5 "Test and Inspections" and Revision

of Related Procedures

August 31, 2011 BRW-S-2011-162 Retention of Three Non

-Permanent Scaffolds Installed in the U1 Auxiliary Building on the 426' Elevation Beyond 90 Days

October 13, 2011 BRW-S-2012-101 Receiving Bulk Loads of Sodium Bromide into 0CF19 T May 4, 2012

BRW-S-2012-124 UFSAR Change to Table 3

-2-1 for Aux Safeguard Relay Cabinet Indicating

Lights (1/2 EL

-LV002 & June 13, 2012

10 CFR 50.59 SCREENINGS

Number Description or Title

Date or Revision 003) BRW-S-2012-150 Revise EDG Fuel Calculations to Address Frequency and CDBI Identified Issues

July 31, 2012

BRW-S-2012-228 Revision of the <75 VDC DC Ground V alue for a Bus Cross Tie to a <103 VDC Action Value. October 27, 2012 BRW-S-2012-238 UFSAR Update for Generic Letter 2008

-01 Response November 9, 2012 BRW-S-2013-039 ESF Switchgear Room Fan 1(2)VX01C DP Switch Setpoint Change and Non

-ESF Switchgear Room Vent Fan 1(2)VX02C DP Switch Setpoint Change

April 9, 2013

BRW-S-2013-041 Transferring a 4160V or 6900V Bus from a Unit Auxiliary Transformer to a System Auxiliary Transformer April 10, 2013

BRW-S-2013-069 Retention of Temporary Scaffold S

-1543 Beyond 90 Days May 10, 2013

BRW-S-2013-348 Turbine Building Floor Drain Sump Level High High

February 14, 2013 CALCULATIONS

Number Description or Title

Date or Revision 19-T-6 Diesel Generator Loading During LOOP / LOCA

- Braidwood Unit 1

6F BRW-00-0010-M Byron/Braidwood Uprate Project

- Spent Fuel Pool Temperature Analysis

April 11, 2012

BRW-04-0005-M RHR, SI, CV and CS Pumps NPSH During ECCS Injection Mode

July 7, 2011 BRW-11-0115-M Evaluation of the Potential for CV Pump Gas Binding

November 10, 2011 BRW-96-362-I Diesel Oil Storage Tank Level Setpoints

October 5, 2012

BRW-97-0274 Containment Spray Additive Tank Level Switch LO

-2 Setpoint Analysis

2A PSA-B-98-08 Byron/Braidwood ECCS Flow Calculations for Safety Analysis 3E

CORRECTIVE ACTION PROGRAM DOCUMENTS INITIATED DURING INSPECTION

Number Description or Title

Date or Revision

1611719 NRC Poses Question on 50.59 Screening BRW

-S-2013-348 January 23, 2014

1611724 Old Calculation Needs to be Superseded

January 23, 2014

1613724 NRC 2014 50.59 Inspection, Error in Procedures BWAR 2-15-A11 ~ D11 January 28, 2014

1615733 Missing Records for Scaffold Installed in 2A RHR HX Room January 31, 2014

1616558 Deficiencies Noted During an NRC Walkdown

February 3, 2014

1617606 EDG Governor Booster Line Slopes Not In Accordance with EC

February 5, 2014

1617670 Permanent Scaffolds Missing Documentation

February 5, 2014

1617930 50.59 Document Not Aligned with Scaffold Procedure February 6, 2014

1618112 Lessons Learned: NRC MODS/50.59 Baseline Inspection

February 6, 2014

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title

Date or Revision

1142820 GL 08-01: Procedure Enhancement for 1/2BWOSR 3.5.2.2-2 November 19, 2010 1146838 NRC ID - Revise Calculation to Show Disposition of Vortex in CSAT

November 30, 2010 1234663 B4 Trend Code: 2LDS

-SW007 As Found OOT

June 28, 2011

237140 Non-Conservative Inputs to HELB Analysis

July 6, 2011

264955 SOER 7-02 Event Readiness

-CW Pump Trip Lifted

September 19, 2011 1269263 NRC MOD/50.59 Inspection

- Concrete Compressive Strength

September 27, 2011 1323285 GL 2008-01 Analyses and Evaluations Require an UFSAR Update

February 6, 2012

1353449 LR Revise UFSAR Table 3.2

-1 for LV Lights

April 13, 2012

1383554 PI&R Action to Address Previous Issue Not Adequate June 29, 2012

1409900 Potential Unidentified Condition with MSIV Accumulator

September 6, 2012 1433324 Label Request for EC 389506

November 29, 2012 1452606 2B DG Governor Booster

- Improve Oil Inlet Line Arrangement

December 15, 2012 1460488 CCP: Need Labels Made For New VD Temperature Switches February 8, 2013

1463427 EC 389506 Revision 001 Label Request

February 15, 2013

1466005 Scheduling Conflict with HELB Mods and DOST Sprinkler Mods

February 22, 2013

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title

Date or Revision

1468255 1HS-VD040 As Found Wiring did not Match Design Drawing CCP

February 28, 2013

1473152 1WF040A - Essential Service WTR Sump PMP 1A Discharge Check

February 9, 2013 1493072 CCP :Unit 1 Drawing is Referred in Unit 2

April 26, 2013

1543966 Retesting of 1TS

-VD002A Required Due to OOT M&TE September 5, 2013 1543967 Retesting of 1TS

-VD002B Required Due to OOT M&TE September 5, 2013 1589107 2013 FASA for Pre

-NRC MOD/50.59 Inspection Deficiency

- 50.59 Screen

November 22, 2013 DRAWINGS Number Description or Title

Date or Revision

20E-0-3600 Braidwood Unit 1& 2 Electrical Floor

and Wall 1 20E-1-4030VD01 Schematic Diagram Diesel Generator Room 1A HVAC System Ventilation Fan 1A 1VD01CA

M 20E-1-4030VD03 Schematic Diagram Diesel Generator Room 1A HVAC System Ventilation

and Exhaust Fans Auxiliary Relays, Switches

and Alarms -Part I O 20E-1-4030VD04 Schematic Diagram Diesel Generator Room 1A HVAC System Ventilation and Exhaust Fans Aux. Relays, Switches and Alarms Part II

L 20E-1-4030VD05 Schematic Diagram Diesel Generator 1A HVAC Sys. Diesel Oil Storage Room Exhaust Fans 1A

and 1B 1VD02CA and 1VD02CB L 20E-1-4030VD06 Schematic Diagram Diesel Generator 1B HVAC Sys. Diesel Oil Storage Room Exhaust Fans 1C

and 1D 1VD02CC and 1VD02CD L 20E-1-4030VD09 Schematic Diagram Diesel Generator Room 1B HVAC System Ventilation & Exhaust Fans Aux. Relays, Switches

and Alarms Part II

L 20E-1-4030VD11 Schematic Diagram Diesel Generator 1A

and Day Tank Room CO2 Fire Protection System Fire Damper Control

J 20E-1-4030VD12 Schematic Diagram Diesel Generator 1B & Day Tank Room CO2 Fire Protection System Fire Damper Control

J 20E-1-4507A Internal and External Wiring Diagram Diesel Generator HVAC Local Control Stations HIS

-VDO42 E 20E-1-4511B Internal Wiring Diagram Diesel Generator Room 1A Vent System Local Control Panel 1VD01JA PT.2

G 20E-1-4511E Internal-External Wiring

Diagram Diesel Generator

T

DRAWINGS Number Description or Title

Date or Revision

From 1A Vent. System Local Control Panel 1VD01JA Part

-5 D-10239 Schematic for A/DV Self Contained Hydraulic Actuator H M-136, Sheet 2

Diagram of Safety Injection

AF M-152, Sheet 20

Control Diagram Starting System and Alarms

G M-2097 HVAC/C&I Diagram Diesel Generator Room Ventilation System

-VD, sheet number 6

E M-4097-1VD05 Control Logic Diagram Diesel Oil Storage Room Vent Fan Control

C M-61, Sheet 2

Diagram of Safety Injection

AJ M-97 Diagram of Diesel Generator Rooms

1A & 1B Ventilation System

W MODIFICATIONS

Number Description or Title

Date or Revision

EC 374070 Diesel Generator Governor Booster

EC 385013 Add Redundant Isolation Valves in Series with 2SI8801 A/B

EC 388473 Install Time Delayed Auto

-Restart for U-1 VE Fans in Support of HELB Mitigation Strategy

EC 388475 Install Time Delayed Auto

-Restart For U

-1 VD Fans in Support of HELB Mitigation

EC 389506 Install High Temperature Trip for DOST Ventilation

Fans 3 EC377536 2A CV Pump Impeller Replacement

EC383595 Incorporate NPSH Required for Replacement Impeller for the 2A CV Pump into the NPSH Analysis from the RWST

PROCEDURES

Number Description or Title

Date or Revision

1BwEP-1 Loss of Reactor or Secondary Coolant Unit 1

205 1BwOS XLE-R1 Unit One Locked Equipment Surveillance

1BwOSR 3.8.1.2-1 1A Diesel Generator Operability Surveillance

2BwEP-1 Loss of Reactor or Secondary Coolant Unit 2

205 2BwOS XLE-R1 Unit Two Locked Equipment Surveillance

BwAR 1-17-B13 Alarm Response Procedure for CW Pump dP Low

BwAR 1-17-D13 Alarm Response Procedure for Intake Bay Level

BwAR 1-17-E13 Alarm Response Procedure for Traveling Screen Trouble 8 BwOP MS-5 MSIV Accumulator Operability Check

BwOP SI-M1 Operating Mechanical Lineup Unit 1

BwOP SI-M2 Operating Mechanical Lineup Unit 1

2 MA-AA-716-025 Scaffold Installation, Modification, and Removal Request Process

MA-AA-716-040 Measurement and Test Equipment Evaluation

OTHER DOCUMENTS

Number Description

or Title Date or Revision

PP-CV-5 IST Evaluation CV Pump New Ref Values

July 28, 2010

WO 10450738

Add Isolation Valves Upstream of 2SI8801A&B

October 29, 2012

WO 1314278

1LS-WF025 Essential Service Water Sump Level Switch June 21, 2013

WO 1538365

Thermal Performance Test at Start of Outage

October 8, 2013

WO 1566935

CE Perform MOD Testing per CC

-AA-107 ATT 1 EC 389506 March 15, 2013

WO 1566935

IM Bench Cal Temp Switches per EC 389506

OAP (HAMMOCK) Testing per CC

-AA-107 ATT 1 EC 389506 December 8, 2012 WO 1566937

IM - 1TS - VD002B Calibrate per EC 289506

August 29, 2013

WO 384197 SEP Pump Curve/Full Flow Test

October 26, 2009

LIST OF ACRONYMS USE

D ADAMS Agencywide Documents Access and Management System

CDBI Component Design Basis Inspection

CFR Code of Federal Regulations

CS Core Spray

CSAT Containment Spray Additive Tank

DG Diesel Generator

DOST Diesel Oil Storage Tank

EC Engineering Change

ECCS Emergency Core Cooling System

EDG Emergency Diesel Generator

FASA Focused Area Self-Assessment

FIN Finding GL Generic Letter

HELB High Energy Line Break

HVAC Heating, Ventilation, and Air Conditioning

HX Heat Exchanger

IMC Inspection Manual Chapter

IST Inservice Testing

LOCA Loss of Coolant Accident

LOOP Loss of Offsite Power

MSIV Main Steam isolation Valve

NCV Non-Cited Violation

NEI Nuclear Energy Institute

NPSH Net Positive Suction Head

NRC U.S. Nuclear Regulatory Commission

PARS Public Available Records System

RHR Residual Heat Removal

SDP Significance Determination Process

SI Safety Injection

UFSAR Updated Final Safety Analysis Report

WO Work Order

Mr. Michael J. Pacilio

Senior Vice President, Exelon Generation Co., LLC

President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road

Warrenville, IL 60555

SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2 EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS AND PERMANENT PLANT MODIFICATIONS BASELINE INSPECTION REPORT 05000456/2014008; 05000457/201400

Dear: Mr. Pacillio

On February 7, 2014, the
U.S. Nuclear Regulatory Commission (NRC) completed an Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications inspection at your Braidwood Station, Units 1 and 2. The enclosed inspection report documents

the inspection results which were discussed on March 27, 2014, with Mr.

P. Raush, and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

The NRC inspectors did not identify any findings or violations of more than minor significance.

In accordance with Title 10, Code of Federal Regulations

(CFR), Section 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html

(the Public Electronic Reading Room).

Sincerely, /RA/

Robert

C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50

-456; 50-457 License Nos. NPF

-72; NPF-77 Enclosure:

Inspection Report 05000456/2014008; 05000457/2014008

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServŽ

DOCUMENT NAME:

G:\DRS\Work in Progress

\Misc Boilers

\con 5.doc -Publicly Available

-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII NAME DSzwarc:ls

RCDaley DATE 0 3/27/14 0 3/27/14 OFFICIAL RECORD COPY

Letter to Michael J. Pacilio

from Robert C. Daley

dated March 27, 2014. SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2 EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS AND PERMANENT PLANT MODIFICATIONS BASELINE INSPECTION REPORT 05000456/2014008; 05000457/201400

DISTRIBUTION

Ernesto Quinones

RidsNrrDorlLpl3

-2 Resource

RidsNrrPMBraidwood Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Steven Orth

Allan Barker

DRPIII DRSIII Carole Ariano

Linda Linn

Patricia Buckley

ROPreports.Resource@nrc.gov