05000361/FIN-2009005-09
From kanterella
Revision as of 19:41, 28 October 2017 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Finding | |
|---|---|
| Title | Failure to Implement Fire Protection Plan Requirements Related to Hot Work Activities |
| Description | Three examples of a self-revealing noncited violation of Technical Specification 5.5.1.1.d, was identified for the failure of contractor personnel to properly implement the requirements of a fire protection procedure for the control of hot work activities. Specifically, between September 1 and 29, 2009, three examples were identified where contractor personnel failed to properly implement the requirements of Procedure SO123-XV-1.41, Steps 6.1.1 and 6.4.1.3, in that, combustible materials were not covered or stored at a distance of 35 feet from the ignition source or flame, and no evaluation was performed. This finding was entered into the licensees corrective action program as Nuclear Notification NN 200604378. The finding is greater than minor because it is associated with the protection against external factors (fires) attribute of the Initiating Events Cornerstone and affects the cornerstone objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Additionally, if left uncorrected, the practice of conducting hot work in a manner that results in unintended combustion of nearby materials would have the potential to lead to a more significant safety concern in that it could result in a fire in or near risk significant equipment. Manual Chapter 0609, Appendix M, Significance Determination Process Using Qualitative Criteria, was used since Appendix F, Fire Protection Significance Determination Process, does not address the potential risk significance of shutdown fire protection findings, and Appendix G, Shutdown Operations Significance Determination Process, does not address fire protection findings. The NRC management review was performed by using the Manual Chapter 0609, Appendix F, Phase 1 Worksheet, to establish a bounding analysis. Using the bounding analysis, the finding is determined to have very low safety significance because the finding represented a low degradation rating, in that, it did not have any significant effect on the likelihood that a fire might occur, or that a fire which does occur might not be promptly suppressed. This finding has a crosscutting aspect in the area of human performance associated with work practices because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety was supported H.4(c) (Section 4OA3) |
| Site: | San Onofre |
|---|---|
| Report | IR 05000361/2009005 Section 4OA3 |
| Date counted | Dec 31, 2009 (2009Q4) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71153 |
| Inspectors (proximate) | L Ricketson G Guerra R Lantz P Elkmann J Adams J Reynoso G Warnick C Osterholtz A Fairbanks M Bloodgood R Schmitt |
| CCA | H.2, Field Presence |
| INPO aspect | LA.2 |
| ' | |
Finding - San Onofre - IR 05000361/2009005 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (San Onofre) @ 2009Q4
Self-Identified List (San Onofre)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||